Louisiana Paving Co. v. STATE, DEPT. OF HWYS.

372 So. 2d 245, 1979 La. App. LEXIS 3590
CourtLouisiana Court of Appeal
DecidedMay 29, 1979
Docket12627
StatusPublished
Cited by9 cases

This text of 372 So. 2d 245 (Louisiana Paving Co. v. STATE, DEPT. OF HWYS.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louisiana Paving Co. v. STATE, DEPT. OF HWYS., 372 So. 2d 245, 1979 La. App. LEXIS 3590 (La. Ct. App. 1979).

Opinion

372 So.2d 245 (1979)

LOUISIANA PAVING COMPANY, INC.
v.
STATE of Louisiana Through the DEPARTMENT OF HIGHWAYS.

No. 12627.

Court of Appeal of Louisiana, First Circuit.

May 29, 1979.

O. P. Barnes, III, Monroe, for plaintiff-appellee Louisiana Paving Co., Inc.

Sharon P. Frazier, Baton Rouge, for defendant-appellant State of Louisiana, Dept. of Highways.

Richard B. Sadler, Alexandria, for third party defendant-appellee Lambda Const. Co., Inc.

Before LANDRY, COVINGTON and PONDER, JJ.

LANDRY, Judge.

Defendant (Department) appeals from judgment awarding plaintiff (Paving) $65,390.00, on the basis of equitable estoppel, *246 for work performed by Paving as subcontractor of Lambda Construction Company, Inc. (Lambda), prime contractor for construction of a road project for the Department. The work performed by Paving was executed pursuant to a verbal agreement between Paving and the Department's employees. Paving has answered the appeal requesting an increase in the award. We affirm.

On January 28, 1971, the Department entered into a written contract with R. C. Asphalt, Inc. (now Lambda) for construction of State Project 8-09-21, the Chamber-Alexandria Highway, Rapides Parish. The contract was to be executed in accordance with the Department's Specifications for Roads and Bridges (October, 1966) as modified by special provisions and plans on file in the Department's Baton Rouge office. Lambda subcontracted with Paving to perform the earthwork required for the project, in strict compliance with the terms of the prime contract "and to the satisfaction of and in compliance with the directions of the Owner or Owner's Engineers." The Department's refusal to pay Paving for certain work performed in deviation from the prime contract prompted this litigation. In essence Paving maintains the deviation was authorized by the Department's engineer and the Department defends on the ground the deviation was not authorized in writing as required by the prime contract.

The dispute is over the placement and movement of a five foot dirt surcharge at three different locations on the project. Surcharging is the placing of surcharge material (dirt) on the roadbed for a period of 90 days to test the roadbed for stability, that is, to determine whether it will subside under the weight. The contract required a surcharge of five feet of dirt excavated from a nearby borrow pit, said dirt being classified as "special borrow excavation" under the contract. Payment for surcharge on the project was fixed at a unit price of $1.95 per cubic yard. The volume of surcharge utilized was determined by cross-sectioning the borrow pit.

As regards surcharge, Sheet 35, Part II, of the project plans provides:

"Placing and Removing the surcharge will be paid for under Item No. 203(5). The cost of trimming the embankment to its final dimensions after the surcharge is removed will also be included in the price bid on Item No. 203(5). This trimmed material and the surcharge shall be used in the Embankment in another location on the project. (No Additional Payment)"

It is agreed that the foregoing provision contemplates movement of the surcharge material, after its use as surcharge, and incorporation of the dirt into the project as embankment fill, and further, that the cost of moving the surcharge forward into the embankment was included in the unit price of $1.95 per cubic yard stipulated in the prime contract. In the course of the work, Paving's project manager, Willie Plumlee, concluded that the project could be expedited if the project specifications were altered by utilizing surcharge material as the "select material" which forms part of the base course for the highway, instead of using the surcharge as embankment material.

Base course in this instance consisted of a soil-cement base composed of select material (in this case dirt), cement, water, and other materials mixed together to form the roadbed which was then overlaid with a surfacing of asphalt coating known as hot-mix. Base course in this case was to be paid for at the unit price of $6.00 per cubic yard, mixed and in place on the roadbed, all materials and labor being furnished by the contractor. In effect, Plumlee discovered that the surcharge material met the specifications for select base course material and that the surcharge could therefore be used as a base course component. He suggested that when surcharge dirt was removed after the 90-day test period, it be used as base course material instead of embankment material and pointed out that this change would expedite completion of the project by a significant amount of time. Plumlee obtained verbal approval of the proposed change from the Department's project engineer, *247 Ronnie Luno, and thereafter changed the method of handling surcharge dirt.

The contract [Item 203(5)] pertinently provides the following with respect to payment for special borrow where both select material and special borrow are excavated from the same pit:

"EXCAVATION AND EMBANKMENT: Section 203 of the Standard Specifications is amended as follows....
If the contractor obtains selected materials for base course ... from borrow pits used for special borrow excavation, the volume of materials used in base course ... computed from plan dimensions, plus 15% for shrinkage, will be deducted from borrow pit measurements."

The above provision requires a deduction from borrow pit measurements, in determining payment for special borrow, for the amount of surcharge ultimately incorporated into base course inasmuch as such material was not utilized for embankment purposes as envisioned by the contract. After obtaining Luno's approval of the suggested change in construction sequence, Paving moved surcharge material ahead to other locations on the project and incorporated the material into base course. Paving's claim is for additional work allegedly entailed during the change of work sequence.

Paving contends that its agent, Plumlee, was assured by the Department's project engineer, Luno, that Luno's superiors approved of payment for the movement of surcharge to base course under Item 203(5), "Special Borrow Excavation," at a unit price of $1.95 per cubic yard. Allegedly, Plumlee was informed that a memo to this effect would be placed in the project file. It is conceded that no written order was issued by the Department approving the change. It is also conceded the contract provides that no extra work would be paid for by the Department unless it was approved in writing.

Paving claims reimbursement in the sum of $192,325.25 for moving 65,490 cubic yards of surcharge into base course at $1.95 per cubic yard; reloading surcharge areas to the extent of 21,905 cubic yards at $1.95 per cubic yard; and hauling, moving, and removing the aforementioned 21,905 yards of surcharge at $1.00 per cubic yard.

It is stipulated that a written contract existed between Lambda and the Department and that a written subcontract exists between Lambda and Paving. It is also stipulated that no written contract was entered into between Paving and the Department.

The trial court found that while there was no written modification of the contract, Paving changed the construction sequence in reliance upon verbal agreement with the Department's agents, which agreement appears supplemented by written notations on the plans and by written evidence of such approval placed in the project file in the Department's Baton Rouge office.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Red River Parish Port Commission v. Headwaters Resources Inc.
698 F. Supp. 2d 684 (W.D. Louisiana, 2010)
Bartlett Const. Co. Inc. v. St. Bernard Council
763 So. 2d 94 (Louisiana Court of Appeal, 2000)
CLOUD CONST., INC. v. Schneider, Inc.
491 So. 2d 32 (Louisiana Court of Appeal, 1986)
Robinson v. North American Royalties, Inc.
463 So. 2d 1384 (Louisiana Court of Appeal, 1985)
John Bailey Contractor, Inc. v. State
425 So. 2d 326 (Louisiana Court of Appeal, 1983)
Parish Concrete, Inc. v. Fritz Culver, Inc.
399 So. 2d 694 (Louisiana Court of Appeal, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
372 So. 2d 245, 1979 La. App. LEXIS 3590, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louisiana-paving-co-v-state-dept-of-hwys-lactapp-1979.