Panhandle Eastern Pipe Line Co. v. Michigan Consolidated Gas Co.

177 F.2d 942, 1949 U.S. App. LEXIS 3313
CourtCourt of Appeals for the Sixth Circuit
DecidedNovember 28, 1949
Docket10910
StatusPublished
Cited by44 cases

This text of 177 F.2d 942 (Panhandle Eastern Pipe Line Co. v. Michigan Consolidated Gas Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Panhandle Eastern Pipe Line Co. v. Michigan Consolidated Gas Co., 177 F.2d 942, 1949 U.S. App. LEXIS 3313 (6th Cir. 1949).

Opinion

SIMONS, Circuit Judge.

As in our case of Michigan Consolidated Gas Co. v. Panhandle Eastern Pipe Line Company and Federal Power Commission et al., 6 Cir., 173 F.2d 784, the present controversy involves a consideration of the regulatory powers of the Federal Power Commission under the Natural Gas Act, 15 U.S.C.A. § 717 et seq., although there is brought into the case, upon appeal, an issue respecting the right of the appellee, as a distributor, to a declaratory judgment defining the obligations of the Pipe Line Company under a written contract with it. The major issue, however, is the validity of a temporary injunction granted in the court below to prevent curtailment of gas delivery from the pipe line to the distributor. The earlier case dealt with deliveries to the Detroit district while the present case involves deliveries at Ann Arbor.

The complaint of Consolidated filed originally in a Michigan court but thereafter removed to the District Court of the United States because of diversity, was filed in October, 1948. Upon the removal of the cause Panhandle moved to dismiss it on the ground that it failed to state a claim on which relief could be granted, and on the ground that the district court lacked jurisdiction of the subject matter because the alleged grievance was within the exclusive jurisdiction of the Federal Power Commission. The complaint prayed for specific performance of a 1937 contract, and for temporary and permanent injunctions to compel deliveries of gas in pursuance of Consolidated’s asserted interpretation of the contract. The contract provided that the seller should not be required to supply more than 2,000,000 cubic feet of natural gas, or its equivalent, in any one day, and also provided that there should be no modification of its terms and provisions except by the execution of supplementary written contracts. While a number of supplementary contracts were later entered into no one of them modified this limitation. The complaint alleged, however, that notwithstanding the limitation Panhandle had for years delivered to Consolidated quantities in excess of that amount, and that the contract had been regarded and acted upon as a full-requirements contract and was so recognized by the Commission; that customers had installed gas-burning equipment in reliance upon Panhandle’s conduct in supplying Consolidated with all of its requirements, which during the cold days of winter exceeded 5j4 million cubic feet per day. While Consolidated has facilities for manufacturing gas, their capacity is not sufficient to make up the difference between its needs and the limitation of the formal agreement. The complaint further alleged that Panhandle intended to limit deliveries of natural gas at Ann Arbor to 2,000,000 cubic feet a day, and to accomplish this purpose by installing flow controllers; that this would cause irreparable injury to both Consolidated and its customers, and that Panhandle had failed to obtain from the Commission a certificate of public convenience and necessity for the installation of flow controllers as it was required to do by the Natural Gas Act. The relief prayed was, by injunction, both temporary and permanent to restrain Panhandle from limiting deliveries to Consolidated to less than the daily requirements of its customers, and to restrain it from installing flow controllers.

At a hearing on December 6, 1948, of Panhandle’s motion to dismiss, it submitted to the court an order of the Federal Power Commission of October 28, 1948, in a proceeding entitled “In the Matter of Panhandle Eastern Pipe Line Company, Docket No. G-1141,” which prescribed several rules and regulations for deliveries to customers by the Panhandle system for the period from November 1, 1948, to April 30, 1949. This order provided for daily delivery to *944 Consolidated at Ann Arbor of 5,782,000 cubic feet of gas. In a colloquy with the court at this hearing, counsel for Consolidated conceded that it was getting all the gas it then needed and would get it throughout the winter, and at a -further hearing on December 13, he advised the court as follows, “I s-ay so long as this order of the Commission is in effect, we are protected.” On January 6, 1949, the district court announced in an opinion that it had jurisdiction to decide the case on its merits, and that a preliminary injunction should issue. No findings were made as required by Federal Rules of Civil Procedure, rule 52(a), 28 U.S.C.A., as to interlocutory injunctions. On February 14, 1949, the court entered two orders, the first overruling Panhandle’s motion to dismiss, the second, an injunctional order restraining Panhandle from limiting Consolidated’s gas supply to less than its daily requirements up to S]/z million cubic feet, and from installing flow controllers.

When the court announced its opinion on January 6, 83 F.Supp. 34, the Detroit case had not yet been decided, and it was uninformed of our view upon the scope of Commission authority. It reasoned that the situation presented to it involved the adjudication of the rights of the respective parties to a contract, and that this was a judicial question which only a court -could decide. It held that, taking the well pleaded facts as true, the complaint stated -a cause of action and it rejected the argument that authority to regulate sales of natural gas was given by Congress to the Federal Power Commission. It held the regulatory powers of the Commission restricted to rates and charges, to the issuance of certificates of public convenience and necessity for new or additional facilities, and for abandonment of such facilities because of depleted gas reserves, but that the quantity or amount of gas to be furnished by a natural gas company to a distributing company is a matter of -agreement which may be specifically enforced by the court.

That, where there is controversy as to the meaning and effect of a written contract interpretation may be sought from and made by the declaratory judgment of a court having jurisdiction over the parties, there is no doubt. The granting of a declaratory judgment, however, depends upon the exercise of a sound judicial discretion and is conditioned upon statutory requirement and adjudicated principles. Section 2201, Title 28 U.S.C.A., Federal Judicial Code, the section which defines the remedy, requires the filing of an appropriate pleading by any interested party seeking such declaration.

The complaint here involved does not seek a declaratory judgment either in express terms or by inescapable inference. The complaint is in the usual form of a bill for specific performance of an alleged contract. A doctrine conditioning the exercise of discretion in granting a declaratory judgment that is to -be derived from the cases, is that no declaration should be made unless it serves a useful, practical purpose. United States v. Jones, 9 Cir., 176 F.2d 278; Aetna Casualty & Surety Co. v. Quarles, 4 Cir., 92 F.2d 321; Smith v. Massachusetts Mutual Life Insurance Co., 5 Cir., 167 F.2d 990.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
177 F.2d 942, 1949 U.S. App. LEXIS 3313, Counsel Stack Legal Research, https://law.counselstack.com/opinion/panhandle-eastern-pipe-line-co-v-michigan-consolidated-gas-co-ca6-1949.