Michigan Consol. Gas Co. v. Panhandle Eastern Pipe Line Co.

173 F.2d 784, 1949 U.S. App. LEXIS 2912
CourtCourt of Appeals for the Sixth Circuit
DecidedApril 7, 1949
Docket10834
StatusPublished
Cited by22 cases

This text of 173 F.2d 784 (Michigan Consol. Gas Co. v. Panhandle Eastern Pipe Line Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michigan Consol. Gas Co. v. Panhandle Eastern Pipe Line Co., 173 F.2d 784, 1949 U.S. App. LEXIS 2912 (6th Cir. 1949).

Opinion

SIMONS, Circuit Judge.

The controversy involves the jurisdiction of the district court to entertain -a suit for the specific performance of a contract between a pipe-line company and a distributor in view of broad regulatory powers conferred upon, the Federal Power Commission under the Natural Gas Act, 15 U.S. C.A. § 717 et seq. The Federal Power Commission, various gas companies, public service commissions and others, intervened as defendants and moved for a dismissal of the complaint. The court, in a well-considered opinion, 80 F.Supp. 27, concluding that Congress had committed the regulation of pipe-line companies to the supervision of the Commission and not to the courts, in respect to the specific grievances of the appellant, granted the motions.

No factual controversy is involved and the question is solely one of statutory construction. The appellant, a Michigan corporation, is a local utility furnishing gas to the metropolitan area of Detroit, and Panhandle is a Delaware Corporation engaged in interstate transportation and sale of natural gas. Under a series of contracts between the two, Panhandle obligated itself to- deliver to Consolidated its requirements of natural gas up to 125,000,000 cubic feet daily, and to build and maintain such pipeline system as would be adequate for such delivery. Over several periods during three years prior to the filing of the complaint, Panhandle’s pipe-line system had not been equal to the demands of Consolidated’s customers. This resulted in curtailment of delivery to Consolidated under orders of the Commission, from which appeals are now pending. Consolidated, however, asserts that it does not in this cause raise any question as to their validity. It seeks performance of the contractual obligation of Panhandle only insofar as such performance is possible within the provisions of present or future valid orders of the Commission. The curtailment orders were based upon findings of the Commission that a dominant, if not controlling factor with respect to the supply of gas available from Panhandle’s system east of Edgerton Station, is the physical capacity of that station. All gas to Michigan and Ohio customers comes through a compressor station at Edgerton, Indiana, a few miles west of the Ohio state line. While the Commission could not definitely determine its delivery capacity, it did determine that it was not sufficient to supply all customers east thereof with full contract deliveries at all times. The Commission therefore ordered that on days of deficiencies in deliveries all Ohio and Michigan customers should receive full contract requirements except the two largest customers,- — the appellant and the Michigan Gas Storage Company — and that these should share the balance of the gas available on a percentage basis specified in the order.

The inadequacy of the facilities at Ed-gerton had long been recognized, and in 1946 Panhandle secured from the Commission a certificate of convenience and necessity permitting improvement of its facilities there, along with other improvements to its system. The Panhandle pipe-line, as its name indicates, originates in Texas oil fields, and the construction authorized, designated as “Group B” facilities, includes additional compressor facilities in Texas, Oklahoma and Kansas and additional pipeline facilities at various points in the states of Kansas, Missouri, Illinois, Indiana, Ohio and Michigan. Only that portion of “Group B” facilities proposed to be installed immediately west and east of the Edgerton Compressor Station are the subject of Consolidated’s prayer for performance. The Commission found that the estimated cost of the “Group B” facilities is approximately $23,751,550; that they are necessary to augment the present system capacity so that it may be able better to meet increased firm market demands; that they are required for the continuance of adequate service to customers and that their construction and operation will have no adverse effect on existing rates and services.

The appellant’s -argument is that its suit for specific performance states a case over which the court normally has jurisdiction *787 as one between citizens of different states. The Natural Gas Act, it says, does not supersede the court’s jurisdiction unless the relief prayed for will conflict with the Commission’s jurisdiction and authority under it. The Commission has no authority to grant the relief sought since it has only such powers as the Act gives to it, either expressly or by necessary implication. Section 717f(a) provides that the Commission may, if it finds such action necessary or desirable in the public interest, order a Natural Gas Company to extend or improve its transportation facilities if no undue burden will thereby be placed upon such natural-gas company, subject, however, to the proviso in that section, “that the Commission shall have no authority to compel the enlargement of transportation facilities for such purposes, or to compel such natural-gas company to establish physical connection or sell natural gas when to do so would impair its ability to render adequate service to its customers.”

The Commission may, so the argument runs, require extensions and improvements in existing transportation facilities only so long as they do not involve enlargement. It is expressly denied authority for enlargement, and while there may be cases where there is doubt as to whether an extension or improvement involves enlargement, this is not such case, for prior to the filing of its petition for a certificate of public necessity and convenience, Panhandle’s pipe-line up to a point 28.28 miles west of Edgerton Station was a double pipe-line. The installation of the authorized facilities at Edger-ton would extend the double pipe-line portion of the Panhandle system to a point inside the State of Michigan, and therefore would constitute an enlargement of transportation facilities as that term is used in the § 717f(a) proviso, for the new facilities involve laying a second pipe-line along the present single pipe-line for a few miles west and east of Edgerton. None of the parties, it says, have disputed this fact. Further, it is said that while §§ 717f (c) and 717f(e) forbid any natural-gas company to increase its transportation facilities without permission of the Commission, the order of the Commission is purely permissive and not obligatory upon the gas company which is left free to install or not install the authorized facilities as it may see fit. While the Commission may attach conditions to its permission it did not do so in this case insofar as present subject matter is concerned, and it is now too late to add conditions. So the view is urged upon us that the delegation of such limited powers to the Commission indicates no purpose of the Congress to deprive the court of its normal jurisdiction to grant the relief asked.

The appellant also puts it in another way. Specific performance of a contractual obligation which is outside the regulatory powers of the Commission, is a proper function for the federal court when there is no primary jurisdiction in the Commission. The Commission has already investigated, declared the need for and authorized the facilities sought. Since it has no power to compel their construction and operation, no preliminary petition is required to exhaust administrative remedies. The Commission has already acted to the limit of statutory authority and no primary jurisdiction remains for it to exercise.

A collateral question is also involved.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atlanta Gas Light Co. v. Federal Power Commission
476 F.2d 142 (Fifth Circuit, 1973)
Atlanta Gas Light Co. v. Southern Natural Gas Co.
338 F. Supp. 1039 (N.D. Georgia, 1972)
Michigan Consolidated Gas Company, a Corporation v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Michigan Gas Utilities Company, Central Illinois Light Company, Michigan Gas Storage Company, City of Indianapolis, Indiana, Northern Indiana Fuel& Light Co., Southeastern Michigan Gas Co., Citizens Gas Fuel Company, Missouri Power& Light Company, Missouri Public Service Company, Central Illinois Public Service Company, Illinois Power Company, Illinois Commerce Commission, Missouri Public Service Commission, Public Service Commission of Indiana, Indiana Gas & Water Company, Inc., Intervenors. Michigan Wisconsin Pipe Line Company, a Corporation v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Missouri Public Service Company, Central Illinois Public Service Company, Intervenors. American Louisiana Pipe Line Company, a Corporation v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Missouri Public Service Company, Central Illinois Public Service Company, Intervenors. County of Wayne, Michigan, a Municipal Corporation and Body Politic v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Intervenor. Milwaukee Gas Light Company, a Corporation v. Federal Power Commission, Panhandle Fastern Pipe Line Company, Intervenor. Wisconsin Fuel and Light Company v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Intervenor. Natural Gas Distributors, Inc., a Corporation v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Intervenor. State of Wisconsin and Public Service Commission of Wisconsin v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Intervenor. City of Detroit, Mich., a Municipal Corporation v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Intervenor. Wisconsin Public Service Corporation v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Intervenor. Michigan Consolidated Gas Company, a Corporation v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Central Illinois Light Company, Michigan Gas Utilities Company, Battle Creekgas Company, Michigan Gas Storage Company, Missouri Power & Light Company,missouri Publicservice Company, Illinois Power Company, Illinois Commerce Commission, Missouripublic Service Commission, Indiana Gas & Water Company, Inc., Intervenors
283 F.2d 204 (D.C. Circuit, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
173 F.2d 784, 1949 U.S. App. LEXIS 2912, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michigan-consol-gas-co-v-panhandle-eastern-pipe-line-co-ca6-1949.