Michigan Consolidated Gas Co. v. Panhandle Eastern Pipe Line Co.

83 F. Supp. 34, 1949 U.S. Dist. LEXIS 2805
CourtDistrict Court, E.D. Michigan
DecidedJanuary 6, 1949
DocketNo. 7706
StatusPublished
Cited by1 cases

This text of 83 F. Supp. 34 (Michigan Consolidated Gas Co. v. Panhandle Eastern Pipe Line Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michigan Consolidated Gas Co. v. Panhandle Eastern Pipe Line Co., 83 F. Supp. 34, 1949 U.S. Dist. LEXIS 2805 (E.D. Mich. 1949).

Opinion

KOSCINSKI, District Judge.

The complaint makes the following allegations :

Plaintiff is a Michigan corporation and is a public utility company engaged in the distribution of gas, including natural gas, for domestic, commercial, industrial and other consumer uses of such gas, and since September 19, 1938 has operated as such a utility in Ann Arbor, Michigan, serving the public of that city and adjoining territory.

The defendant is a Delaware corporation authorized to do business in Michigan, producing natural gas in Kansas and Texas and purchasing natural gas produced by others in Texas, Oklahoma and Kansas.

On or about April 20, 1937, a contract was entered into between Michigan Gas Transmission Corporation, then affiliated with the defendant, and Washtenaw Gas Company for the delivery and sale of natural gas by Michigan Gas Transmission to Washtenaw Gas Company; subsequently, further agreements supplementing this contract were entered into by the interested parties. All of the rights and obligations of the Michigan Gas Transmission Corporation under said contract, as supplemented by later agreements, were transferred to and assumed by the defendant. Also, subsequent to April 20, 1937, all of the rights and obligations of the Washtenaw Gas Company under said contract, as supplemented by later agreements, were transferred to and assumed by the plaintiff.

In pursuance of -the contract, as supplemented by later agreements, defendant agreed to supply the plaintiff with such quantity of gas as would meet its needs and requirements, although there was a clause in the original contract limiting the supply of gas by defendant to plaintiff to 2,000,000 cubic feet per day, due to defendant’s inability to deliver more at that time. Later, however, and up to the time of the filing of this suit, defendant has been supplying plaintiff with all the requirements needed to serve its customers in the Ann Arbor area, and for several years prior to this suit the defendant has been supplying the plaintiff with 5,500,000 cubic feet of gas per day, rather than 2,000,000 cubic feet per day, since the contract for many years has been regarded and acknowledged by both of these parties as an agreement on the part of the defendant to furnish to the plaintiff all of its gas requirements, regardless of the amount of same.

That the Federal Power Commission has recognized the existing contract, as supplemented by later agreements, as a "requirement” contract, under which the defendant is obligated to furnish to plaintiff all of plaintiff’s requirements for gas to be furnished to plaintiff’s customers at Ann Arbor, Michigan, regardless of the amount thereof; that, relying upon the conduct of the defendant, it had, since the execution of the contract, as supplemented by later agreements, supplied gas to more than two thousand customers of the plaintiff at Ann Arbor who have installed equipment for heating of their homes and places of business through the use of natural gas furnished by the defendant, and that such customers are absolutely and entirely dependent upon the supply of natural gas furnished by the defendant for the heating of their homes and places of business. Furthermore, in reliance upon the conduct of the defendant, a number of industrial [36]*36firms at Ann Arbor have installed equipment for the use of natural gas, and that those industrial firms have installed equipment for use of natural gas furnished by the defendant in industrial processes and that they are absolutely and entirely dependent for power to operate such processes upon the natural gas furnished by the defendant; that the daily total requirement of plaintiff’s customers at Ann Arbor for commercial, industrial space heating and domestic purposes during the cold days of the winter season have exceeded 5,500,-000 cubic feet, which amount of gas has, for a period of many years, been furnished by the defendant in accordance with plaintiff’s said customer requirements; that the plaintiff has installed at Ann Arbor facilities for manufacturing certain quantities of manufactured gas to be used to supply plaintiff’s customers at Ann Arbor in case of emergency, but the capacity of such facilities is not sufficient to make up the difference between the requirements of plaintiff’s said customers and 2,000,000 cubic feet per day; that defendant has advised plaintiff that it proposes in the immediate future to take action to limit the natural gas supplied by it to the plaintiff for use of plaintiff’s customers at Ann Arbor to 2,-000,000 cubic feet per day and that the defendant will do so unless prevented by an injunction of this court.

That, furthermore, plaintiff has a reason to believe that the defendant proposes to accomplish its purposes by installation of flow controllers in its pipe line system and so limit the deliveries of gas to plaintiff to 2,000,000 cubic feet per day; that if this is done, plaintiff will suffer great and irreparable injury to its business and great and irreparable hardship will result to plaintiff’s customers at Ann Arbor, and that plaintiff’s customers, domestic, industrial and commercial, will be unable to obtain sufficient heat for their homes and their businesses and their industrial pursuits.

That, under the provisions of the Natural Gas Act, 15 U.S.C.A. § 717, et seq., defendant is required to secure a certificate of public convenience' and necessity from the Federal Power Commission before installing flow controllers, as above referred to; that no such authority has been granted by the Federal Power Commission to the defendant to install such flow controllers so as to limit the deliveries of gas by the defendant to the plaintiff for use at Ann Arbor.

Such are, substantially, the allegations of the complaint.

Plaintiff prays for a temporary injunction restraining the defendant, and all its agents and representatives, during the pen-dency of this suit, from limiting the deliveries of gas by the defendant to the plaintiff for use at Ann Arbor, Michigan, so that such deliveries are less than the daily requirements of plaintiff’s customers at such city, and restraining defendant from installing flow controllers to limit the deliveries of gas by the defendant to the plaintiff for use of plaintiff’s customers at Ann Arbor, Michigan, unless and until a certificate of public convenience and necessity is issued therefor by the Federal Power Commission; and that upon the final hearing of this cause the temporary injunction requested be made permanent.

The complaint in this cause was filed by plaintiff in the Washtenaw County Circuit Court. Without answering, defendant removed the suit to this court alleging diversity of citizenship and the necessary statutory amount involved. Immediately after removal, defendant filed a motion to dismiss plaintiff’s complaint on the grounds, (1) because the complaint fails to state a claim against the defendant upon which relief can be granted, and (2) that this court lacks jurisdiction over the subject matter.

The defendant admits it served notice on plaintiff that upon the expiration of this emergency order it will curtail the supply of gas to plaintiff to 2,000,000 cubic feet per day.

A complaint should not be dismissed on motion without a hearing on merits unless it appears to a certainty that plaintiff would be entitled to no relief under any state of facts which could be proved in support of his claim. Oh a motion to dismiss, the well pleaded facts are to be taken as true.

The situation presented here involves the adjudication of the rights of the respective parties under the contract in [37]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
83 F. Supp. 34, 1949 U.S. Dist. LEXIS 2805, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michigan-consolidated-gas-co-v-panhandle-eastern-pipe-line-co-mied-1949.