Palatine I v. Planning Board of the Township of Montville

628 A.2d 321, 133 N.J. 546, 1993 N.J. LEXIS 741
CourtSupreme Court of New Jersey
DecidedAugust 5, 1993
StatusPublished
Cited by54 cases

This text of 628 A.2d 321 (Palatine I v. Planning Board of the Township of Montville) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palatine I v. Planning Board of the Township of Montville, 628 A.2d 321, 133 N.J. 546, 1993 N.J. LEXIS 741 (N.J. 1993).

Opinions

The opinion of the Court was delivered by

GARIBALDI, J.

This appeal presents the question of whether a municipal planning board’s grant of preliminary site-plan approval and a building permit insulates a developer in perpetuity against zoning changes. Specifically, is a municipal planning board equitably estopped from denying final site-plan approval and applying post-preliminary site-plan approval zoning amendments to a developer whose preliminary site-plan approval and construction permit have expired? Like the trial court and Appellate Division below, we conclude that it is not. Accordingly, we affirm the judgment of the Appellate Division.

[550]*550I. Facts and Procedural History

Plaintiff, Palatine I (Palatine), is a partnership owning 4.9 acres of land in Montville. In 1982, Palatine applied to the Montville Planning Board (the Board) for preliminary site-plan approval for an office building. The application proposed a 65,000-square-foot two-story building, consisting of two 30,000-square-foot wings connected by a central core. On February 11, 1982, the Board, finding that the application fully complied with all then-existing zoning regulations, granted preliminary site-plan approval. That initial grant of preliminary site-plan approval conferred rights on Palatine for a three year period, ending February 11, 1985. In October 1984, Palatine applied for and received an extension of the preliminary site-plan approval to February 11, 1986. In January 1986, Palatine applied for and received a second extension to February 12, 1987. In granting the second extension, the Board warned Palatine that “this is the last extension of preliminary site plan you can request.”

During the period covered by the second extension, Palatine applied for a construction permit. The permit was issued by Montville’s construction official on April 11, 1986. Palatine paid fees of $4,699.31 for the construction permit. Printed across the bottom of the permit was the following notice:

If construction does not commence within one (1) year of date of issuance, or if construction ceases for a period of six (6) months, this permit is void.

Palatine did commence construction and completed the first wing of the building (Section I) and the central core sometime in 1987 or 1988. Palatine also laid a concrete slab as a foundation for the second wing (Section II), but did not construct the remainder of Section II because of “the sagging real-estate market.” At that stage, Palatine had spent approximately $2,000,000 for construction costs, including $200,000 for a storm sewerage permit and $40,000 for soil improvement. No allocation has been made of the construction costs attributable solely to the construction of Section

II. Palatine still has no plans to build Section II in the foreseeable future.

[551]*551In October 1989, Palatine, having secured tenants for Section I, applied for a certifícate of occupancy for that Section and for final site-plan approval for the entire complex. In 1986 and 1987, after the granting of the preliminary site-plan approval, Montville had amended its zoning ordinances in ways that made them more restrictive than the zoning ordinances in effect at the time of the original approval. Under the new standards, the largest building that could be built on Palatine’s property would be approximately 45,000 square feet. Palatine had already built one 30,000-square-foot wing plus the small core. Roughly speaking, therefore, the net effect of the maximum lot coverage standard, if applied to Palatine, would be that Palatine would have to halve the size of the unbuilt wing or else obtain variances.

In considering Palatine’s application for final site-plan approval, the Board bifurcated its consideration of Section I and the core, which existed, and Section II, which did not. The Board’s resolution stated:

this application was originally submitted in 1981 and the first building has been completed while only a foundation exists for the second building, and the Board notes that no work has progressed on the second building for a period of years. Applicant now wants to rent the first building but preserve his rights under the original Ordinance for the construction of Phase II, the second building; and
the applicant testified that completion of the original project was held up because of economics; and
the Board, based on legal advice, finds that while the first building was in compliance with the 1981 Land Use Ordinance, that building number 2 when completed, must comply with the Ordinance in affect [sic] at the time a new site plan application is approved; and
the Board finds that the application should be bifurcated and approval given only to the first building * * *.

Accordingly, the Board granted final site-plan approval and a certificate of occupancy for the existing structure consisting of Section I and the core. However, the Board denied final site-plan [552]*552approval for Section II because the plans did not comply with current zoning regulations.

Palatine filed a complaint in lieu of prerogative writ in the Law Division on December 19, 1990, naming the Board as the sole defendant. Palatine sought declaratory judgment that it was entitled to final site-plan approval on the entire project and that it could, “at such time as it sees fit,” complete construction of Section II as originally approved under 1982 zoning law. Palatine presented two arguments. The first was that the Board was arbitrary, capricious, and unreasonable and acted contrary to law in concluding “that * * * preliminary site plan approval on building number 2 had expired; and/or * * * [tjhat Palatine is subject to zoning amendments rendering the Building nonconforming after the commencement of construction.” The second theory was that due to Palatine’s reliance on the building permit, the Board was equitably estopped from enforcing against Palatine any zoning amendments adopted after construction began. The Board counterclaimed for declaratory relief, arguing that it had acted within its rights in denying final approval. The parties entered into a stipulation of facts.

After oral argument, the trial court affirmed the Board’s decision to deny Palatine final site-plan approval for Section II and to subject plaintiff to the zoning regulations enacted after the grant of preliminary approval. The trial court stated, however, that a “plausible case might well be made by the plaintiff for getting a variance” from the Montville Board of Adjustment.

Plaintiff appealed, adding as a third theory that the entire proposed building, including both Section I and the unbuilt Section II, was protected as a pre-existing nonconforming structure under N.J.S.A 40:55D-68. The Appellate Division rejected all Palatine’s arguments and affirmed the trial court’s judgment substantially for the reasons expressed in its opinion.

We granted certification, 130 N.J. 601, 617 A.2d 1223 (1992), and now affirm.

[553]*553II. Protection Under Preliminary Site-Plan Approval

A municipality is empowered by N.J.SA. 40:55D-37 to enact an ordinance requiring approval of site plans by the municipal planning board as a condition for issuance of a construction permit. Montville has such an ordinance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D'URSO v. BAMCO, INC.
D. New Jersey, 2023
Newark Cab Ass'n v. City of Newark
235 F. Supp. 3d 638 (D. New Jersey, 2017)
Segal v. Lynch
48 A.3d 328 (Supreme Court of New Jersey, 2012)
Haskins v. First American Title Insurance
866 F. Supp. 2d 343 (D. New Jersey, 2012)
Hemsey v. Board of Trustees
925 A.2d 1 (New Jersey Superior Court App Division, 2007)
Talcott Fromkin v. Freehold Tp.
891 A.2d 690 (New Jersey Superior Court App Division, 2005)
Walsh v. Mattera
879 A.2d 1226 (New Jersey Superior Court App Division, 2005)
Tax Auth. v. Jackson Hewitt
873 A.2d 616 (New Jersey Superior Court App Division, 2005)
Marsden v. Encompass Ins. Co.
863 A.2d 1133 (New Jersey Superior Court App Division, 2005)
Knorr v. Smeal
836 A.2d 794 (Supreme Court of New Jersey, 2003)
D.L. Real Estate Holdings, L.L.C. v. Point Pleasant Beach Planning Board
820 A.2d 1220 (Supreme Court of New Jersey, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
628 A.2d 321, 133 N.J. 546, 1993 N.J. LEXIS 741, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palatine-i-v-planning-board-of-the-township-of-montville-nj-1993.