Pacific Development L.C. v. Orton

2001 UT 36, 23 P.3d 1035, 420 Utah Adv. Rep. 3, 121 A.L.R. 5th 723, 2001 Utah LEXIS 72, 2001 WL 409448
CourtUtah Supreme Court
DecidedApril 24, 2001
Docket990744
StatusPublished
Cited by15 cases

This text of 2001 UT 36 (Pacific Development L.C. v. Orton) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Development L.C. v. Orton, 2001 UT 36, 23 P.3d 1035, 420 Utah Adv. Rep. 3, 121 A.L.R. 5th 723, 2001 Utah LEXIS 72, 2001 WL 409448 (Utah 2001).

Opinion

On Certiorari to the Utah Court of Appeals

DURRANT, Justice:

T1 We granted a writ of certiorari to review a court of appeals decision affirming the district court's confirmation of an arbitration award in favor of Orton Excavation. Orton served as a subcontractor on a real estate project developed by Pacific Development, L.C. A dispute arose over the amount Pacific owed Orton for work performed, and the parties entered into a written arbitration agreement that described the scope of their dispute by reference to a single plat of land. The arbitrator made rulings with respect to two plats of land upon which Orton had performed work. Orton sought confirmation of the award in the district court, and Pacific filed a motion to vacate or modify the award on the ground that the arbitrator had exceeded his authority by ruling on both plats and had manifestly disregarded legal authority pertaining to the covenant of good faith and fair dealing implicit in the contract. The district court confirmed the award, and Pacific appealed on the same grounds it had raised before the arbitrator and the district court. The court of appeals affirmed. We affirm in part and reverse in part.

BACKGROUND

12 In 1994, Pacific contracted with Orton to perform sewer, water, and storm drain work within a subdivision Pacific was developing. Orton worked on two plats within the subdivision, known as Plat B and Plat C. A dispute arose over the amount Pacific owed Orton for work Orton performed. Orton recorded a mechanies' lien against the project and sought to foreclose it. Litigation ensued. Eventually, Pacific and Orton executed a written agreement to arbitrate their dispute. 1 That agreement read in pertinent part as follows:

*1037 The parties agree to submit to arbitration all remaining issues arising out of the dispute over a Mechanics' Lien filed against Riderwood Village, Plats B & C.... [The parties] acknowledge that the issues relating to the above-referenced Plat B of Rid-erwood Village have been resolved, and that, therefore, the arbitration will focus on the remaining issues of the dispute, those which relate to Plat C, thereby resolving all remaining issues in the case.

The arbitration took place in 1997. Despite the language stating that only Plat C issues remained unresolved, both parties presented some evidence relating to Plat B. The arbitrator rendered an interim decision with respect to both Plat B and Plat C. Pacific moved for reconsideration, arguing that the arbitrator had exceeded his authority by deciding Plat B issues and by failing to apply the covenant of good faith and fair dealing in his Plat C decision. The arbitrator supplemented and clarified the reasoning supporting his decision but ultimately rejected Pacific's motion and issued a final arbitration award relating to both plats.

13 Orton sought confirmation of the arbitrator's award in the district court pursuant to Section 78-81a-12 of the Utah Code. Pacific responded by filing a motion to vacate or modify the award. Pacific argued that the arbitrator had exceeded his authority by including Plat B in the award. Pacific also argued that the arbitrator had manifestly disregarded the law by refusing to apply the doctrine of good faith and fair dealing to offset Orton's purportedly excessive use of fill material in its work on Plat C.

14 The district court rejected these arguments and confirmed the arbitrator's award. Pacific appealed, renewing the arguments it had presented to the district court. The court of appeals affirmed. See Pacific Dev., L.C. v. Orton, 1999 UT App 217, ¶ 20, 982 P.2d 94. With respect to Pacific's claim that the arbitrator exceeded the seope of his authority, the court of appeals reasoned that Pacific and Orton, by "their conduct and mutual consent, submitted Plat B issues for resolution, expanding the scope of the arbitrator's jurisdiction." Id. 112. The court of appeals also rejected Pacific's contention that the arbitrator had manifestly disregarded the law by refusing to apply an offset based on the doctrine of good faith and fair dealing. See id. I 16.

ANALYSIS

15 On certiorari, Pacific renews the arguments it presented unsuccessfully to the district court and the court of appeals. Specifically, Pacific maintains that (1) the arbitrator improperly ruled upon a dispute that had not been submitted to him in the written agreement, and (2) the arbitrator manifestly disregarded the law by refusing to apply an offset pursuant to the implied covenant of good faith and fair dealing. Orton requests attorney fees for being required to defend the award against Pacific's contentions.

16 Though we here review the court of appeals and not the district court, see Bear River Mut. Ins. Co. v. Wall, 1999 UT 33, ¶ 4, 978 P.2d 460, we note-as a necessary reference for determining the correctness of the decision below-the very limited number of statutory bases upon which courts may reconsider the arbitrator's award. See Buzas Baseball v. Salt Lake Trappers, 925 P.2d 941, 946-47 (Utah 1996). "A trial court faced with a motion to vacate or modify an arbitration award is limited to determining whether any of the very limited grounds for modification or vacatur exist." Id. at 947. On appeal, the appellate court should " 'grant no deference to the district court's conclusions [of law] but review them for correctness'" Id. at 948 (alteration in original) (quoting DeVore v. IHC Hospitals, Inc., 884 P.2d 1246, 1251 (Utah 1994)). On certiorari, we likewise review the decision of the court of appeals for correctness, but further limit our review to the seope of the issues considered by the court of appeals. See Wall, 1999 UT 38, ¶ 4, 978 P.2d 460.

17 Orton brought its action for confirmation of the award in the district court pursuant to the Utah Arbitration Act. Seetion 78-31a-12 of that Act requires the court *1038 to "confirm the award unless a motion is timely filed to vacate or modify the award." Pacific timely moved, under Section 78-81a-14(1), to modify or vacate the portion of the arbitrator's award pertaining to Plat B. Seetion 78-38l1a-14(1) in pertinent part provides: "Upon motion to the court by any party to the arbitration proceeding for vacation of the award, the court shall vacate the award if it appears: ... (c) the arbitrators exceeded their powers...." 2 Both of Pacific's arguments rely upon this ground as a basis for overturning the arbitrator's decision. 3 We address them in the order stated above.

I. THE ARBITRATORS CONSIDERATION OF PLAT B ISSUES

1 8 The written arbitration agreement provided that "[the parties] acknowledge that the issues relating to the above-referenced Plat B of Riderwood Village have been resolved, and that, therefore, the arbitration will focus on the remaining issues of the dispute, those which relate to Plat C, thereby resolving all remaining issues in the case." In other words, payments for Plat B were not in dispute and, once the issues relating to Plat C had been resolved, all disputes would be at an end.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taylor v. Taylor
2022 UT 35 (Utah Supreme Court, 2022)
Ahhmigo v. Synergy
2022 UT 4 (Utah Supreme Court, 2022)
Shipp v. Peterson
2021 UT App 25 (Court of Appeals of Utah, 2021)
State v. Martinez-Castellanos
2017 UT App 13 (Court of Appeals of Utah, 2017)
Westgate Resorts, Ltd. v. Adel
2016 UT 24 (Utah Supreme Court, 2016)
Westgate v. Adel and Consumer Protection
2016 UT 2 (Utah Supreme Court, 2016)
Evans v. EM 1600
2015 UT App 65 (Court of Appeals of Utah, 2015)
Createrra, Inc. v. Sundial, LC
2013 UT App 141 (Court of Appeals of Utah, 2013)
Certain Underwriters at Lloyd's London v. Ashland, Inc.
967 A.2d 166 (District of Columbia Court of Appeals, 2009)
Duke v. Graham
2007 UT 31 (Utah Supreme Court, 2007)
Buckner v. Kennard
2004 UT 78 (Utah Supreme Court, 2004)
Miller v. USAA Casualty Insurance Co.
2002 UT 6 (Utah Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
2001 UT 36, 23 P.3d 1035, 420 Utah Adv. Rep. 3, 121 A.L.R. 5th 723, 2001 Utah LEXIS 72, 2001 WL 409448, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-development-lc-v-orton-utah-2001.