P & N Investments, LLC, d/b/a Dickey's Barbecue Pit v. Frontier Mall Associates, LP

2017 WY 62, 395 P.3d 1101, 2017 WL 2351146, 2017 Wyo. LEXIS 62
CourtWyoming Supreme Court
DecidedMay 31, 2017
DocketS-16-0244
StatusPublished
Cited by15 cases

This text of 2017 WY 62 (P & N Investments, LLC, d/b/a Dickey's Barbecue Pit v. Frontier Mall Associates, LP) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P & N Investments, LLC, d/b/a Dickey's Barbecue Pit v. Frontier Mall Associates, LP, 2017 WY 62, 395 P.3d 1101, 2017 WL 2351146, 2017 Wyo. LEXIS 62 (Wyo. 2017).

Opinions

FOX, Justice.

[¶1] Appellant P & N Investments, LLC (P & N) obtained a franchise for a Dickey’s Barbeque Pit restaurant to be operated in Frontier Mall in Cheyenne, Wyoming, P & N entered into a lease with Frontier Mall Associates, LP (the Mall), which required the Mall to pay P & N a finish allowance when [1103]*1103certain provisions had been satisfied. P & N then entered into a contract with a general contractor, which P & N eventually paid in full for the work done. The general contractor, however, did not pay all the subcontractors. P & N and the Mall now dispute whether the lease provision requiring that.liens be released and work be paid for was satisfied. The district cpurt ruled that the lease language is unambiguous, and, because it is undisputed that subcontractors have not been paid and have not provided evidence regarding satisfaction or waiver of any liens, granted summary judgment in favor of the Mall. We affirm.

ISSUE

[¶2] We rephrase the issue: Do the unambiguous terms of the lease require evidence that subcontractors and the general contractor have been paid in full before the Mall is obligated to pay the finish allowance?

FACTS

[¶3] P & N entered into a ten-year Shopping Center Lease (Lease) with the Mall for approximately 2500 square feet in Frontier Mall in which to operate a Dickey’s Barbeque Pit franchise. The Lease allowed P & N to renovate the space to suit its use as a restaurant. P & N retained East Rochester, New York contractor, CCI Builders and Developers, Inc. (CCI), to act as the general contractor on the project. CCI, in turn, hired a number of local subcontractors to provide materials and perform work on the project.

[¶4] The Lease provided that upon satisfaction of ten express conditions, the Mall would pay P & N a tenant finish allowance of $150,180. The condition that lies at the heart of this dispute requires P & N to provide the Mall satisfactory evidence from P & N’s general contractor and subcontractors that any liens have been satisfied or waived.and an affidavit that “all work has been paid for” before the finish allowance becomes due.

[¶5] Work was completed on the'project in September 2014 and the restaurant opened on schedule. For the purposes of this appeal, it is undisputed that the total cost of construction was $308,929.55 and that P & N paid CCI $308,929.55. P & N submitted an affidavit to the Mall stating:

6. The total cost of construction was three hundred eight thousand nine hundred twenty nine and 55/100 dollars ($308,-929.55). The cost was paid in full by me [Nathaniel Schott, owner of P & N] to CCI.
7. The construction was completed in September 2014,
7. [sic] No liens have been filed on the property or may be filed as a result of construction on the leased premises.

It is also undisputed that CCI did not pay numerous subcontractors a total of approximately $90,000 for work they performed on or materials they provided to the project.1

[¶6] Under Wyoming law, contractors have one hundred fifty days from the date of the completion of their work to assert a lien.2 Thus, CCI and the subcontractors had until February 27, 2015, at the latest, to assert a lien against the property. It is undisputed that no liens have been filed against the property.

[1104]*1104[¶7] Because the Mall has not paid the finish allowance, P & N sued the Mall, asserting claims of breach of contract and unjust enrichment, and seeking declaratory judgment that the Mall must pay the tenant finish allowance because P & N has met the conditions for that payment set forth in the Lease. The Mall counterclaimed, seeking a determination that the Lease terms have not been satisfied and that the requirement to pay the finish allowance has not been triggered. The parties filed cross-motions for summary judgment. The district court concluded that the disputed contract language is unambiguous and requires the submission of evidence of lien release satisfactory to the Mall from the general contractor and the subcontractors and an affidavit that all outstanding amounts owed for the construction, including amounts owed to subcontractors, have been paid. Because there is no dispute that neither of these requirements has been met, the district court granted summary judgment in favor of the Mall. P & N appeals.

STANDARD OF REVIEW

[¶8] We review a grant of summary judgment deciding a question of law de novo. Anadarko Land Corp. v. Family Tree Corp., 2017 WY 24, ¶ 15, 389 P.3d 1218, 1223 (Wyo.2017); Williams v. Sundstrom, 2016 WY 122, ¶ 17, 385 P.3d 789, 793 (Wyo.2016). We use the same materials and follow the same standards as the district court. Leeks Canyon Ranch, LLC v. Callahan River Ranch, LLC, 2014 WY 62, ¶ 12, 327 P.3d 732, 737 (Wyo.2014). Summary judgment can be granted when there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. W.R.C.P. 56(c).

[¶9] When summary judgment is based on interpretation of a contract:

The initial question of whether the contract is capable of being understood in only one way is a question of law for the court. If the court determines that the contract is capable of being understood in only one way, then the language used in the contract expresses and controls the intent of the parties. In such case, the next question, what is that understanding or meaning, is also a question of law. When we review the district court’s summary judgment decisions that a contract is capable of being understood in only one way and what that understanding is, we accord no deference to those decisions.
Claman v. Popp, 2012 WY 92, ¶ 23, 279 P.3d 1003, 1012 (Wyo.2012) (quoting Union Pacific Railroad Co. v. Caballo Coal Co., 2011 WY 24, ¶ 13, 246 P.3d 867, 871 (Wyo.2011)).

Leeks Canyon Ranch, LLC, 2014 WY 62, ¶ 12, 327 P.3d at 737.

DISCUSSION

[¶10] Our “ultimate goal when interpreting a contract ‘is to discern the intention of the parties to the document.’” Comet Energy Servs., LLC v. Powder River Oil & Gas Ventures, LLC, 2008 WY 69, ¶ 6, 185 P.3d 1259, 1261 (Wyo.2008) (Comet I) (quoting Mullinnix, LLC v. HKB Royalty Trust, 2006 WY 14, ¶ 22, 126 P.3d 909, 919 (Wyo.2006)). In so doing, we first consider the “specific terms of the contract and give them their plain and ordinary meaning.” Id.

[¶11] Section 1.5(b) of exhibit B to the Lease provides:

Tenant shall have furnished evidence satisfactory to Landlord from its general contractor and any subcontractors that any and all liens that have been, or may be, filed have been satisfied of record or waived and an affidavit that all work has been paid for[J

Both parties contend that these terms are unambiguous, but they disagree as to the meaning. A disagreement between the parties as to the meaning of the terms of a contract does not give rise to an ambiguity. Omohundro v. Sullivan, 2009 WY 38, ¶ 9, 202 P.3d 1077, 1081 (Wyo.2009). We agree with the district court that the language of this provision is unambiguous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2017 WY 62, 395 P.3d 1101, 2017 WL 2351146, 2017 Wyo. LEXIS 62, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-n-investments-llc-dba-dickeys-barbecue-pit-v-frontier-mall-wyo-2017.