§ 29-2-106 — When statement lien to be filed; rights of subcontractor not abridged by contract between owner and contractor; agreement to extend filing period

Wyoming § 29-2-106
JurisdictionWyoming
Title 29Liens
Ch. 2CONTRACTORS OR MATERIALMEN

This text of Wyoming § 29-2-106 (When statement lien to be filed; rights of subcontractor not abridged by contract between owner and contractor; agreement to extend filing period) is published on Counsel Stack Legal Research, covering Wyoming primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wyo. Stat. Ann. § 29-2-106 (2026).

Text

(a)Except as provided in subsection (c) of this section, any contractor asserting a lien under this chapter shall file his lien statement within one hundred fifty (150) days and every other person asserting a lien under this chapter shall file within one hundred twenty (120) days:
(i)Of the earlier of:
(A)After the last day when work was performed or materials furnished under contract;
(B)From the date of substantial completion of the project on which work was performed or materials were furnished under contract; or
(ii)With respect to a subcontractor, after the last day he performed work at the direction of the contractor or other person authorized to provide direction.
(b)No contract made between the record owner and the contractor shall be construed to affect or restrict the right

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

13
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Wyoming § 29-2-106, Counsel Stack Legal Research, https://law.counselstack.com/statute/wy/29-2-106.