Osterling v. Frick

131 A. 250, 284 Pa. 397, 1925 Pa. LEXIS 525
CourtSupreme Court of Pennsylvania
DecidedOctober 7, 1925
DocketAppeal, 102
StatusPublished
Cited by54 cases

This text of 131 A. 250 (Osterling v. Frick) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Osterling v. Frick, 131 A. 250, 284 Pa. 397, 1925 Pa. LEXIS 525 (Pa. 1925).

Opinion

Opinion by

Me. Justice Walling,

F. J. Osterling brought this suit against the executors of the estate of the late H. C. Frick to recover for his services as architect in the erection of the Union Arcade building, Pittsburgh. Jury trial being waived, the case *400 was heard before the court and resulted in a judgment for plaintiff of $109,406.75, including interest, from which he brought this appeal. A careful examination of the voluminous record discloses no ground for reversal.

Plaintiff’s employment was arranged largely by correspondence in which he undertook to perform the full services of an architect, to the owner’s satisfaction, for three per cent of the cost of the building. Preliminary sketches and outline plans were approved by Prick in March, 1915. The shaft or main part of the building was to be six stories in height, above the basement, the first two stories to be of cut stone and the four above of terra cotta, later changed to cut stone. The plans also provided for three additional stories under a mansard or sloping roof, the entire frame work to be of structural steel. To expedite the construction, a contract for the steel was given the American Bridge Company, April 26,1915, on a tonnage basis, and the general contract for the building was let to the George A. Fuller Company, of New York, June 24, 1915. This contract, drawn by plaintiff, provided for the completion of the building May 1, 1916. The Fuller Company let a contract to Samuel Holmes for the cut stone work of the first and second stories, which stated that the stone was to fie obtained from a quarry owned by plaintiff’s brother: A large amount of terra cotta was specified for the building, including the roof and interior finish. This was obtained from the Northwestern Terra Cotta Company of Chicago, by a subcontract made July 6, 1915. Other material, etc., was obtained through subcontracts with divers parties. By whomsoever the work was to be done, it was to be under the general supervision and control of the plaintiff, as architect.

The building was finished August 1, 1917, and thereafter plaintiff presented a bill of $321,325 for his services, less a credit of $40,000 paid October 1,1915. Frick declined payment and, after his death (December 2, *401 1919), this suit was brought against his executors. The main question raised on the appeal is as to the validity of a $40,000 credit allowed defendants by the trial court as damages sustained by Frick on account of plaintiff’s delay in the performance of his duty as architect. Much testimony was taken on this branch of the case and it was very ably and earnestly contended for appellant, both at bar and in the printed brief, that such finding was not supported by the evidence; but an examination of the record has led us to the opposite conclusion. In cases tried before the court under the Act of April 22, 1874, P. L. 109, we are concluded by the trial court’s findings of the facts, when based on sufficient evidence (Sturdevant et al. v. Thomson, 280 Pa. 233; Stein v. W. H. Bradford Co., Inc., 278 Pa. 321; Gillespie et al. v. Hunt et al., 276 Pa. 119; New York & Pa. Co. v. N. Y. Cent. R. R., 267 Pa. 64), that is, evidence sufficient to support a verdict. In the instant case, the evidence showed it was plaintiff’s duty not only to supply the design and erection plans but also enlarged detail plans and such information as to enable the contractor and subcontractors to prepare shop drawings from which, when approved by the architect, the necessary material could be fabricated. The detail plans and necessary information should have been supplied within sixty days after the respective contracts were let. For example, detail plans for the structural steel should have been furnished before June 26, 1915, but were not until several months thereafter. As the structural steel work follows the foundations such undue delay greatly retarded the construction. In the general contract of June 24, 1915, Holmes is named as subcontractor for the cut stone, as above mentioned, and a copy of the contract with him was given plaintiff July 2, 1915, but he did not furnish the necessary detail plans therefor until late in October. Holmes, being unable to secure the desired stone from plaintiff’s brother, obtained the same elsewhere, but was hampered by the architect’s undue delay in furnishing *402 the detail plans and also by his persistent objections to the quality of the stone, which continued even after they were set in the building, until he was overruled by Frick. The undue delay of the architect in supplying the detail plans and necessary information for the structural steel and cut stone, to which we have referred, alone justified the $40,000 set-off, as the evidence shows that each month’s delay in completion of the building occasioned a loss to the owner of over $20,000. There is a clause in the general contract to the effect that the detail plans for the terra cotta should be drawn by the terra cotta company, although that was normally the work of the architect, for which reason we have not relied upon architectural delay as to that feature of the case. Different parts of the construction were, however, so interdependent that a delay of one affected the others. For example, a delay of the steel construction necessarily delayed the installing of the cut stone and terra cotta. Furthermore, it takes a considerable time to fabricate material after the plans are complete. In many instances delays resulted from the architect’s neglect to approve shop drawings; but, under the trial court’s finding, the extent thereof was not sufficiently definite to warrant a conclusion thereon adverse to the plaintiff. The evidence points to other delays of the architect occurring at later periods, but what we have said sufficiently vindicates the $40,000 allowance for delay.

We have been discussing this branch of the case from the standpoint of defendants’ evidence, but plaintiff strenuously denied every charge of delay on his part and submitted evidence in support of this denial, which, however, made an issue of fact for the trial court to pass upon. In addition to the direct evidence there were circumstances tending to support defendants’ contention. The expert evidence was that plaintiff should have had at least ten assistants for a timely preparation of the work in question, whereas he only had three or four and their time was divided between this and other work. *403 There is also evidence that plaintiff admitted his lack of sufficient help, which fact may account for the many complaints that his plans came tardily, by piecemeal and only after repeated and urgent requests. Again, almost without exception, those connected with the building complained bitterly of the architect’s delays and none more so than Frick. It is scarcely conceivable that such universal complaint could be groundless.

No one contends that the architect is chargeable with the entire fifteen months’ delay, on the contrary, a considerable part thereof came from changes in the plans. For example, in November, 1915, when it became apparent that the building could not be finished by May 1, 1916, the architect’s suggestion of two additional stories in the shaft of the building, making eight stories below the mansard roof, was adopted, and at other times, notably in March, 1916, further changes were made, including that of the interior to pure Gothic design.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GRUVER v. KINCAID
W.D. Pennsylvania, 2023
Gruver v. Kincaid
W.D. Pennsylvania, 2022
Fallabel v. Brophy-Wolter
6 Pa. D. & C.5th 129 (Carbon County Court of Common Pleas, 2008)
Commonwealth v. Carson
913 A.2d 220 (Supreme Court of Pennsylvania, 2006)
Spang & Co. v. United States Steel Corp.
545 A.2d 861 (Supreme Court of Pennsylvania, 1988)
Martin v. Owens-Corning Fiberglas Corp.
528 A.2d 947 (Supreme Court of Pennsylvania, 1987)
Borough of Yeadon v. Montgomery
455 A.2d 785 (Commonwealth Court of Pennsylvania, 1983)
Draft Systems, Inc. v. Rimar Manufacturing, Inc.
524 F. Supp. 1049 (E.D. Pennsylvania, 1981)
Aiken Industries, Inc. v. Estate of Wilson
383 A.2d 808 (Supreme Court of Pennsylvania, 1978)
Paramount Lithographic Plate Service, Inc. v. Hughes Printing Co.
2 Pa. D. & C.3d 677 (Philadelphia County Court of Common Pleas, 1977)
Burly Construction Corp. v. Commonwealth
284 A.2d 841 (Commonwealth Court of Pennsylvania, 1971)
Bell Telephone Co. v. Daniel
45 Pa. D. & C.2d 717 (Chester County Court of Common Pleas, 1968)
Altoona Clay Products, Inc. v. Dun & Bradstreet, Inc.
246 F. Supp. 419 (W.D. Pennsylvania, 1965)
Smail v. Flock
180 A.2d 59 (Supreme Court of Pennsylvania, 1962)
Berke v. Bregman
176 A.2d 644 (Supreme Court of Pennsylvania, 1962)
Doden v. Housh
105 N.W.2d 78 (Supreme Court of Iowa, 1960)
Ross v. Houck
136 A.2d 160 (Superior Court of Pennsylvania, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
131 A. 250, 284 Pa. 397, 1925 Pa. LEXIS 525, Counsel Stack Legal Research, https://law.counselstack.com/opinion/osterling-v-frick-pa-1925.