Orange & Rockland Utilities, Inc. v. Amerada Hess Corp.

59 A.D.2d 110, 397 N.Y.S.2d 814, 96 A.L.R. 3d 1263, 22 U.C.C. Rep. Serv. (West) 310, 1977 N.Y. App. Div. LEXIS 12466
CourtAppellate Division of the Supreme Court of the State of New York
DecidedAugust 15, 1977
StatusPublished
Cited by27 cases

This text of 59 A.D.2d 110 (Orange & Rockland Utilities, Inc. v. Amerada Hess Corp.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orange & Rockland Utilities, Inc. v. Amerada Hess Corp., 59 A.D.2d 110, 397 N.Y.S.2d 814, 96 A.L.R. 3d 1263, 22 U.C.C. Rep. Serv. (West) 310, 1977 N.Y. App. Div. LEXIS 12466 (N.Y. Ct. App. 1977).

Opinion

Margett, J.

This action, for damages as a result of an alleged breach of a requirements contract, raises related but distinctly separate issues as to whether the plaintiff buyer’s requirements occurred in good faith and whether those requirements were unreasonably disproportionate to the estimates stated in the contract.

In a fuel oil supply contract executed in early December, 1969, defendant Amerada Hess Corporation (Hess) agreed to supply the requirements of plaintiff Orange and Rockland Utilities, Inc. (O & R) at plaintiffs Lovett generating plant in Tompkins Cove, New York. A fixed price of $2.14 per barrel for No. 6 fuel oil, with a sulphur content of 1% or less, was to continue at least through September 30, 1974, with the price subject to renegotiation at that time. Estimates of the amounts required by plaintiff were included in the contract clause entitled "Quantity”. Insofar as those estimates are relevant to the instant controversy, they were as follows:

1970 - 1,750,000 barrels

1971 - 1,380,000 barrels

1972 - 1,500,000 barrels

1973 - 1,500,000 barrels

The estimates had been prepared by plaintiff on December 30, 1968, as part of a five-year budget projection. The estimates anticipated that gas would be the primary fuel used for generation during the period in question.1 This was a result of the lower cost of gas and of the fact that gas became readily available for power generation during the warmer months of the year as a result of decreased use by gas customers. Plaintiff expressly reserved its right to burn as much gas at it chose by the inclusion, in the "Quantity” provision of the requirements contract, of a clause to the effect that "[n]othing [112]*112herein shall preclude the use by Buyer of * * * natural gas in such quantities as may be or become available”.

Within five months of the execution of the requirements contract, the price of fuel oil began to ascend rapidly. On April 24, 1970 the market price of the oil supplied to plaintiff stood at between $2.65 and $2.73 per barrel. On May 1, 1970 the price was in excess of $3 per barrel. The rise continued and was in excess of $3.50 per barrel by mid-August, and more than $4 per barrel by the end of October, 1970. By March, 1971 the lowest market price was $4.30 per barrel—more than double the price set forth in the subject contract.

Coincident with the earliest of these increases in the cost of oil, O & R proceeded to notify Hess, on four separate dates, of increases in the fuel oil requirements estimates for the year. By letter dated April 16, 1970, O & R notified Hess that it was expected that over 1,460,000 barrels of oil would be consumed over the period April-December, 1970. Since well over 600,000 barrels of oil had been consumed during the first three months of the year, the total increase anticipated at that time was well in excess of 300,000 barrels over the estimate given in the contract.

Eight days later, by letter dated April 24, 1970, O & R furnished Hess with a revised estimate for the period May through December, 1970. The figure given was nearly 1,580,-000 barrels which, when combined with quantities which had already been delivered or were in the process of delivery during the month of April, exceeded the contract estimate by over 700,000 barrels—a 40% increase.

The following month the estimates were again increased— this time to nearly one million barrels above the contract estimate. Hess was so notified by letter dated May 22, 1970. Finally, a letter dated June 19, 1970 indicates a revised estimate of more than one million barrels in excess of the 1,750,000 barrels mentioned in the contract; an increase of about 63%.

On May 22, 1970, the date of the third of the revised estimates, representatives of the two companies met to discuss the increased demands. At that meeting O & R’s president allegedly attributed the increased need for oil to the fact that O & R could make more money selling gas than burning it for power generation. Hess refused to meet the revised requirements, but offered to supply the amount of the contract estimate for the year 1970, plus an additional 10%.

[113]*113The June 19, 1970 letter referred to above recited that the Hess position was "wholly unacceptable” to O & R. It attributed the vastly increased estimates to (a) an inability to burn as much natural gas as had been planned and (b) the fact that O & R had been "required” to meet higher electrical demands on its "own system” and to furnish "more electricity to interconnected systems” than had been anticipated.

Thereafter, for the remainder of 1970, Hess continued to supply the amount of the contract estimates plus 10%. A proposal by Hess, in October, 1970, to modify the existing contract by setting minimum and maximum quantities, and by setting a price keyed to market prices, was ignored by O & R. Although the proposed modification set a price 65 cents lower than the market price, it was more advantageous for Q & R to insist on delivery of the estimated amounts in the December, 1969 contract (at $2.14 per barrel) and to purchase additional amounts required at the full market price.

During the remainder of the contract period Hess continued to deliver quantities approximately equal to the estimates stated in the subject contract. O & R purchased additional oil for its Lovett plant from other suppliers. The contract between Hess and O & R terminated one year prematurely by reason of an environmental regulation which took effect on October 1, 1973 and which necessarily curtailed the use of No. 6 fuel oil with a sulphur content as high as 1%. During the period 1971 through September, 1973 O & R consistently used more than double its contract estimates of oil at Lovett.2

This action was commenced in mid-1972. O & R’s complaint seeks damages consisting of the difference between its costs for fuel oil during the period in question and the cost it would have incurred had Hess delivered the total amount used by O & R at the fixed contract price of $2.14 per barrel. The trial was conducted in September, 1975 before Mr. Justice Donohoe, sitting without a jury. In an opinion dated March 8, 1976, Trial Term held that plaintiff should be denied any recovery on the ground that its requirements were not incurred in good [114]*114faith. Specifically, Trial Term found that plaintiffs greatly increased oil consumption was due primarily to (a) increases in sales of electricity to other utilities and (b) a net shift from other fuels, primarily gas, to oil. The former factor was condemned on the premise that "[i]ndirectly, O & R called upon Hess to supply the demands for electricity to the members of the [New York Power] Pool. O & R then shared the savings in the cost of fuel with the other members of the Pool”. The latter factor was not elaborated on to any great degree. Trial Term did, however, infer that O & R seized "the opportunity to release its reserve commitment of gas” and thereby reaped very substantial profits.

Although Trial Term stated in its opinion that one of the questions before it was whether plaintiffs demands were unreasonably disproportionate to the estimates set forth in the contract, it failed to reach this question in the light of its conclusion that plaintiff had failed to act in good faith.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BRC Rubber & Plastics, Inc. v. Continental Carbon Co.
876 F. Supp. 2d 1042 (N.D. Indiana, 2012)
Waste Stream Environmental, Inc. v. Lynn Water & Sewer Commission
15 Mass. L. Rptr. 723 (Massachusetts Superior Court, 2003)
MDC Corp., Inc. v. John H. Harland Co.
228 F. Supp. 2d 387 (S.D. New York, 2002)
Simcala, Inc. v. American Coal Trade, Inc.
821 So. 2d 197 (Supreme Court of Alabama, 2001)
Allapattah Services, Inc. v. Exxon Corp.
61 F. Supp. 2d 1308 (S.D. Florida, 1999)
CFSC Capital Corp. XXVII v. W. J. Bachman Mechanical Sheet Metal Co.
177 Misc. 2d 652 (New York Supreme Court, 1998)
Canusa Corp. v. a & R LOBOSCO, INC.
986 F. Supp. 723 (E.D. New York, 1997)
Lenape Resources Corp. v. Tennessee Gas Pipeline Co.
925 S.W.2d 565 (Texas Supreme Court, 1996)
Philadelphia Corp. v. Niagara Mohawk Power Corp.
207 A.D.2d 176 (Appellate Division of the Supreme Court of New York, 1995)
People v. Gaskins
171 A.D.2d 272 (Appellate Division of the Supreme Court of New York, 1991)
People v. Fernandez
150 Misc. 2d 560 (New York Supreme Court, 1991)
People v. Esposito
146 Misc. 2d 847 (New York Supreme Court, 1990)
ILC Data Device Corp. v. County of Suffolk
146 Misc. 2d 462 (New York Supreme Court, 1989)
People v. Spadafora
131 A.D.2d 40 (Appellate Division of the Supreme Court of New York, 1987)
Ausch v. St. Paul Fire & Marine Insurance
125 A.D.2d 43 (Appellate Division of the Supreme Court of New York, 1987)
Shuster v. First National Monetary Corp.
113 Misc. 2d 1058 (Civil Court of the City of New York, 1982)
Alice D. v. William M.
113 Misc. 2d 940 (Civil Court of the City of New York, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
59 A.D.2d 110, 397 N.Y.S.2d 814, 96 A.L.R. 3d 1263, 22 U.C.C. Rep. Serv. (West) 310, 1977 N.Y. App. Div. LEXIS 12466, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orange-rockland-utilities-inc-v-amerada-hess-corp-nyappdiv-1977.