Oliver-Electrical Manufacturing Co. v. I. O. Teigen Construction Co.

177 F. Supp. 572, 1959 U.S. Dist. LEXIS 2684
CourtDistrict Court, D. Minnesota
DecidedOctober 13, 1959
Docket4-57-Civ.-7
StatusPublished
Cited by7 cases

This text of 177 F. Supp. 572 (Oliver-Electrical Manufacturing Co. v. I. O. Teigen Construction Co.) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oliver-Electrical Manufacturing Co. v. I. O. Teigen Construction Co., 177 F. Supp. 572, 1959 U.S. Dist. LEXIS 2684 (mnd 1959).

Opinion

DEVITT, Chief Judgé.

Plaintiff, a Michigan manufacturing corporation, instituted this action to recover $5,461.96, an unpaid balance due for goods sold and delivered. The defendant’s answer admits the sale and delivery and admits the failure to pay the sum in question. The answer alleges a counterclaim for damages by reason of the plaintiff’s failure to deliver the goods within the time agreed upon.

The defendant is an independent contractor engaged in the business of building electrical transmission lines. Early in 1956, defendant agreed to construct a transmission line for the Ottertail Power Company from Audubon, Minnesota to West Fargo, North Dakota. Under the terms of this agreement, construction was scheduled to begin on August 1, 1956 and to be completed by November 1, 1956. Orders for necessary materials were placed by defendant with various suppliers and manufacturers. Pole-line hardware was to be manufactured by the plaintiff and shipped to the job site in Minnesota.

Included in the hardware order was an item called a “spacer fitting,” which consists of a piece of steel shaped somewhat like an “I.” Spacer fittings are bolted into place at three points between two wooden planks which then form the cross-arms for the transmission line structures.

Teigen’s construction operations consisted basically of four steps. In the first step, the cross-arms are “framed” by bolting thé spacer fittings into place, and the completed cross-arms and poles are hauled to the line site. The next step is “field framing” by which the cross-arms are attached to the poles. This is followed by the “dig, set, and tamp” operation in which the structures are erected. Finally, the “wire stringing” operation completes the process.

The placement of the hardware order was accomplished by assignment of job orders to Wright-Sellers Co., then to Charles Ward Co., both manufacturer’s representatives, and finally to plaintiff. *575 Prior to the final placement of the orders, representatives of Wright-Sellers Co. conferred with defendant concerning deliveries of the orders. Mr. Teigen, it appears, made it clear that materials must be on the job site in July so that he could satisfy his commitments to begin construction on August 1. Similar conferences with respect to time of delivery were held between Wright-Sellers Co. and Charles Ward Co.

On May 15, James Colwell of the Charles Ward Co. visited with plaintiff at his Battle Creek, Michigan plant. After discussing in some detail the general manufacturing problems which the job would entail, one of plaintiff’s officers expressed confidence that plaintiff could manufacture the goods and deliver them when Teigen desired.

Immediately after accepting the job order on May 15,1956, plaintiff wrote the defendant as follows:

“We want you to know that we are aiming for a shipping time on all of this material of early July.
“We are making detailed drawings of the steel spacer and X-brace hardware which we will forward within 3 or 4 days for your approval, and we also understand that of the subject power company. It would be appreciated if you would expedite these approvals as soon as possible in view of the delivery requirements on this material.” [Emphasis supplied.]

In a letter dated the following day, May 16, the plaintiff added:

“In connection with all of your orders mentioned in our May 15th letter, may we call to your attention that we cannot enter a firm order until we have the destination on each of them and also a release for shipment. We would appreciate it if you could forward us these promptly therefore.”

In reply, defendant wrote plaintiff on May 21, 1956 as follows:

“The destination on the above mentioned Purchase Orders will be Hawley, Minnesota. On all the orders, with the exception, of 1966M, we would like delivery not later than July 23rd and if possible, we would like to have delivery not earlier than July 9th.”

The drawings for the hardware items were received by the defendant on May 24, 1956. They were returned on May 29, 1956 with instructions “to proceed with manufacture of them.” On June 14, 1956, Teigen sent releases for shipment accompanied by a letter stating, “As stated previously, we would like to-have delivery not later than August l.”

In a telephone call initiated by the plaintiff on or about July 10, 1956, defendant was informed that the first shipment of spacer fittings could be expected about the third week in August. In subsequent telephone conversations with plaintiff, the defendant and representatives of Wright-Sellers Co. repeatedly insisted delivery be made before August 1. The first shipment of spacer fittings arrived on August 16, 1956. On August 29, 1956 a second shipment was received. Further delays ensued when both shipments were returned to the plaintiff at Battle Creek after they were rejected by the Ottertail Power Company’s engineers as being too brittle. The first shipment of usable spacer fittings arrived on September 11, 1956. Another shipment was accepted on September 17, 1956. Attachment of the spacer fittings to the wooden cross-arms began on September 25 and framing of structures began in early October. Work was carried on throughout the winter of 1956 and was finally completed in May, 1957.

The plaintiff’s contention is that no specific delivery date was provided in the contract and that the plaintiff had only to deliver the goods within a reasonable time after the contract finally came .into existence on June 18 when it received the releases for shipment. It urges that any statements concerning July delivery were made only in general *576 terms of a possible date that could be met if all details were “ironed out” quickly so as to leave it 45 to 60 days to manufacture the spacers.

In my view the evidence fails to support such a conclusion. Despite the plaintiff’s preliminary statement that it could not enter a firm order until releases for shipment were submitted by Teigen, a contract appears to have come into existence when the plaintiff received approval of its drawings and the express authority to manufacture the items in the letter of May 29. The plaintiff reacted to this letter by immediately preparing its plant for manufacturing the items necessary to fill the order. Even if a binding contract did not come into existence until June 18 when Oliver received the releases for shipment, there were no intervening changes in negotiations indicating that July delivery was not an essential term of the contract.

A fair appraisal of the facts is that Oliver accepted the order knowing of the July delivery requirements but was under the impression that it was not an essential term of the contract. Its attitude is summed up in the statement of its president, “We give shipping promises regularly.” In this case, however, knowledge was brought home to Oliver before the order was placed that Teigen had a contract to begin work on August 1 and that consequently, July delivery was a condition of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
177 F. Supp. 572, 1959 U.S. Dist. LEXIS 2684, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oliver-electrical-manufacturing-co-v-i-o-teigen-construction-co-mnd-1959.