Hammel-Dahl Co. v. United States

158 F. Supp. 8, 1957 U.S. Dist. LEXIS 2388
CourtDistrict Court, D. Rhode Island
DecidedDecember 31, 1957
DocketCiv. A. No. 1973
StatusPublished
Cited by2 cases

This text of 158 F. Supp. 8 (Hammel-Dahl Co. v. United States) is published on Counsel Stack Legal Research, covering District Court, D. Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hammel-Dahl Co. v. United States, 158 F. Supp. 8, 1957 U.S. Dist. LEXIS 2388 (D.R.I. 1957).

Opinion

DAY, District Judge.

Plaintiff, a corporation organized under the laws of the State of Rhode Island, has brought this action to recover a balance alleged to be due and owing to it under a contract for the manufacture and sale of 224 valves to the Atomic Energy Commission. Jurisdiction of this Court exists under the provision of Title 28 U.S.C.A. § 1346(2), the Tucker Act, so-called. Although the plaintiff claims there is due and owing to it the sum of $12,035.80, it seeks judgment in the sum of $10,000, the [9]*9maximum amount recoverable under the Tucker Act, plus interest and costs.

The defendant in its answer admits that all the valves called for by the contract were delivered, but avers that they were not delivered until long after the dates required under the contract between the parties, and counterclaims for damages alleged to have been sustained by it as a result of said delays in delivery. In its counterclaim it alleges that said contract required the plaintiff to commence deliveries on July 1, 1953 and to continue to make such deliveries at the rate of 15% of the total quantity of valves specified in the contract during each month thereafter until 224 valves were delivered; that no deliveries were made until January 1954; that as a result thereof the defendant, after utilizing all available valves similar to those to be supplied by plaintiff, was compelled to convert other valves to meet current construction requirements; that as a result of these conversions the defendant incurred excess costs in the amount of $14,796.58; that while there is due to the plaintiff under the contract by its terms the sum of $11,548.21, payment thereof has been withheld and applied in partial liquidation of the former’s indebtedness in said sum of $14,796.58 and that there is justly due and payable to it the sum of $3,248.37 for which it seeks judgment.

At the outset of the trial the parties stipulated that the balance due plaintiff by the terms of its contract was $12,035.80 and the balance due the defendant, if its counterclaim is found to be valid, is $2,787.35.

From the evidence it appears that on October 20, 1952, the Atomic Energy Commission prepared and forwarded to six manufacturers of valves, including the plaintiff, an invitation to submit a proposal on a fixed unit price basis for the manufacture and delivery of Special Monel Control Valves in accordance with job specifications JS-280, Revision 7, JS-606, Revision 2, which accompanied the invitation. With respect to delivery dates of the valves the invitation stated:

“Deliveries are to start not later than July 1, 1953 and continue at the rate of fifteen per cent of the total quantity per month until completion of the order.”

The invitation recited that the Carbide and Carbon Chemicals Company was assisting and acting as Agent of the Commission in the technical aspects of the procurement covered by the invitation and directed that questions concerning equipment characteristics, engineering designs and other matters be directed to Mr. J. O. Alexander, Carbide and Carbon Chemicals Company, Post Oifice Box P. Oak Ridge, Tennessee, and that a carbon copy of any such correspondence should be sent to the Commission.

The invitation also recited that:

“Because of the rather complicated and unusual nature of this equipment to be manufactured, the extensive quantity and the tight delivery schedule, you are cautioned to review thoroughly all of the data furnished herewith. We point out specifically that time is of the essence in this job and it is essential, therefore, that delivery schedules be met or bettered if possible.”

This invitation was labelled by the Commission as “Inquiry G-202” and proposals in reply thereto were directed to be forwarded in time to reach the Commission not later than November 21, 1952.

The plaintiff, under date of November 20, 1952, submitted its proposal. However, it appears that the Commission thereafter modified its original Inquiry G-202, first on December 3, 1952, and again on December 10, 1952, and it became known as “Inquiry G-202 A”. As late as January 16, 1953 plaintiff wrote to the Commission giving it a schedule of proposed prices for the items covered by the modified invitation and offering, subject to further negotiations, certain comments with respect to the form of contract to be executed by it.

Finally, on April 27, 1953, Contract No. AT(40-1)-1565 was executed, ef[10]*10fective March 4, 1953. It called for the manufacture and delivery of 203 valves of various types and sizes. The provision as to deliveries thereunder appears as Article II of the contract. It reads as follows:

“The work hereunder shall be commenced immediately on execution of this contract and progress as rapidly as is practicable, it being understood and agreed that the Contractor shall begin deliveries by July 1, 1953 and shall continue deliveries thereafter at the rate of 15% of the total quantities of all valves per month until completion of delivery of all items under this contract. Said 15% may be composed of any size or type of valves ordered hereunder.”

Plaintiff failed to begin to make deliveries on July 1, 1953. Despite its failure in this respect the Commission thereafter on July 6, 1953 and again on July 23, 1953 executed modifications of the contract whereby the number of valves to be made pursuant to the contract was increased from 203 to 224. Modification No. 1, executed July 6, 1953, provided that the 16 valves added thereby should be delivered by December 1, 1953. No other change in the delivery schedule was made by these modifications.

On July 6, 1953, plaintiff received written instructions from Carbide that the 203 valves, originally contracted for, should be shipped to it at Oak Ridge, Tennessee. These shipping instructions were modified by Carbide on July 24, 1953 by change notice No. 1 received Tby plaintiff on August 3, 1953 and plaintiff was thereby directed to ship a certain quantity of items to Carbide at Paducah, Kentucky, another quantity to it at Sargent, Ohio, and the balance to :it at Oak Ridge, Tennessee. Instructions for marking the shipments were .•also given, and dates for the deliveries ■of various quantities and types were set forth; the last date for the deliveries ■of certain items being fixed as March’ 1, .1954. Further change notices followed. Change notice No. 2, received August 24, 1953, simply increased the number of valves to be delivered from 203 to 224 as provided in Modification No. 2. Change notice No. 3, dated August 25, 1953, required that each item supplied should be marked with the identification number and change notice No. 4 which was issued January 19, 1954, and received by plaintiff on January 22, 1954, contained a revised acceptable delivery schedule, no deliveries having been made by the plaintiff through December 31, 1953.

It is clear that the plaintiff encountered production and supply difficulties from the very outset. Not only did it fail to make deliveries by July 1, 1953, but in spite of complete assistance and cooperation from Carbide, it was unable to make any deliveries prior to December 31, 1953.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
158 F. Supp. 8, 1957 U.S. Dist. LEXIS 2388, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hammel-dahl-co-v-united-states-rid-1957.