American Vitrified Products Co. v. Wyer

221 F.2d 447
CourtCourt of Appeals for the Sixth Circuit
DecidedApril 15, 1955
DocketNo. 12259
StatusPublished
Cited by7 cases

This text of 221 F.2d 447 (American Vitrified Products Co. v. Wyer) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Vitrified Products Co. v. Wyer, 221 F.2d 447 (6th Cir. 1955).

Opinion

ALLEN, Circuit Judge.

This is an appeal from a judgment in favor of plaintiffs1 in an action to recover damages alleged to have been sustained due to delivery by defendant, American Vitrified Products Company, of defective sewer pipe and failure to make timely delivery of pipe for the construction of a sewer which plaintiffs were installing in the city of Roosevelt Park, Michigan, in 1951. In the fall of 1950 plaintiffs Wyer and Hansen agreed to form a joint venture for the purpose of bidding upon a contract with the city [449]*449of Roosevelt Park, Michigan, for an extensive sewerage construction contemplated to cost over $500,000. In anticipation of securing this contract plaintiffs ordered from defendant, a manufacturer of vitrified clay pipe, different sizes of pipe in an order dated October 24, 1950. The contract with the city was awarded plaintiffs December 21, 1950. It provided for completion of the project December 31, 1951, but the time was extended by the city to April 30, 1952. The work was virtually completed around November, 1953.

On the same date that plaintiffs’ contract -was signed with the city the joint venture entered into a subcontract with E. H. Wyer, doing business as Wood Coal & Construction Company, whereby that company agreed to construct the Roosevelt Park sewerage system for the joint venture. Under the subcontract it was agreed that the joint venture was to furnish the sewer pipe which had been contracted for with defendant. It was also agreed that the joint venture should pay Wood Coal & Construction Company for the use of its equipment and for labor and material used in the sewer construction. Later, April 24, 1951, the joint venture agreement and the subcontract between the joint venture and Wood Coal & Construction Company were modified in a contract under which E. H. Wyer assumed individual responsibility for the performance of the joint venture’s contract with the city of Roosevelt Park. The obligation of the joint venture to the city, to defendant for sewer pipe, and to furnish sewer pipe for the job remained unchanged.

It is conceded that on February 16, 1951, defendant’s delivery of 4,620 feet of 18-inch pipe was rejected by the engineer for the city of Roosevelt Park upon the ground that it failed to meet the specifications of the contract between plaintiffs and the city; that on October 1, 1951, the 15-inch pipe delivered by defendant was rejected by the city engineer for the same reason; and that later during 1951 10-inch pipe and 12-inch pipe delivered by defendant were rejected by the engineer for the same reason. The pipe so rejected was returned to defendant. Plaintiffs were compelled to secure certain pipe from other sources at an advanced price and to use certain substitute pipe furnished by defendant after, in certain instances, considerable delay.

Plaintiffs contended at the trial that defendant, when it accepted the order for sewer pipe, was aware of the provisions of the contract with the city, the specifications and the requirement for completion by a date certain; that in their work schedule delivered to defendant’s representative March 14, 1951, plaintiffs apprised defendant of their plan and order of operation; and that plaintiffs’ plan and time schedule, which was that the 18-inch pipe should be laid first and completed before any of the smaller pipe was installed, were upset by defendant’s breach of contract in furnishing defective sewer pipe not conforming to contract specifications and in failing to deliver and replace pipe on time. Plaintiffs’ principal contentions were: (1) that the subcontractor was compelled, by defendant’s causing delay in the construction, to lay sewer pipe in wet trench rather than in dry trench as planned; (2) that the subcontractor was forced to work under railroad tracks in highly inclement weather with a substantial increase in time necessary for this part of the operation; (3) that the subcontractor’s equipment was not used for long periods of time, for which periods the plaintiffs were obligated to pay rental; (4) that the subcontractor from time to time had to idle his crews and shut down operations; (5) that the subcontractor had to replace defective pipe furnished by defendant at an increase in cost; (6) that equipment had to be moved unnecessarily because of the delay and irregularity of defendant’s deliveries; (7) that additional labor was required with increase in cost. The principal defenses were: (1) that the joint venture suffered no damages; (2) that the special damages claimed were not within the contemplation of the parties [450]*450when the contract was entered into and hence could not be recovered; and (3) that plaintiffs waived all damages for delay and delivery of pipe of defective quality by failing to object arid by continuing to make payments to defendant upon accounts rendered.

The trial consumed five weeks and the transcript of the testimony covers eleven volumes. Fourteen claims for damages aggregating $103,315.43 were included in the amended complaint filed January 4, 1954, three of which, Claims 1,10 and 14, were withdrawn from the jury by the court. The amount of these claims does not materially affect the aggregate total .and they will not be discussed. Defendant filed a counterclaim for $28,-436.02 with interest, which amount plaintiffs admitted was due defendant for pipe delivered. The court therefore instructed the jury to enter a judgment for defendant in the amount of $31,906.-90. The jury rendered a verdict in favor of plaintiffs for-$47,401.74, the net receipt of plaintiffs under the judgmént being some $15,000.

The principal questions presented are questions of fact which were covered in detail by the court in its careful ruling on defendant’s motion for summary judgment, in its charge to the jury, and in its ruling on the motion for judgment non obstante veredicto.

As to defendant’s contention that the joint venture suffered no damages, the court in its elaborate findings on the motion for summary judgment, which are amply sustained by the record, finds and concludes that the joint venture between Wyer and Hansen, though modified on April 24, 1951, was not dissolved; that the joint venture at all times was obligated to defendant for sewer pipe purchased and to the city of Roosevelt Park for the construction of the sewerage system; and that defendant’s breach of contract which increased the expense of constructing the sewerage system was a damage suffered by the joint venture. Gulf States Creosoting Co. v. Loving, 4 Cir., 120 F.2d 195.

The question whether special damages were recoverable presented a question of fact properly submitted to the jury. Where notice is brought home to the seller that the goods are purchased to be put to a particular use he is chargeable with the consequences for a failure to perform and with the results which such notice fairly apprised him would probably follow upon his breach of contract. Industrial Works v. Mitchell, 114 Mich. 29, 72 N.W. 25. Through its soliciting agent and representative Trues-dale, defendant knew of the special use to which its pipe was to be put; that the city of Roosevelt Park was about to construct an extensive sewer system and prior to October 24, 1950,'had prepared a contract and specifications covering the proposed construction. Plaintiffs were approached in September, 1950, prior to the submission of their bid, by Trues-dale, who solicited an order on behalf of defendant for the necessary pipe.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
221 F.2d 447, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-vitrified-products-co-v-wyer-ca6-1955.