Old Dominion Electric v. PJM Interconnection, LLC

24 F.4th 271
CourtCourt of Appeals for the Fourth Circuit
DecidedJanuary 19, 2022
Docket20-1483
StatusPublished
Cited by19 cases

This text of 24 F.4th 271 (Old Dominion Electric v. PJM Interconnection, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Old Dominion Electric v. PJM Interconnection, LLC, 24 F.4th 271 (4th Cir. 2022).

Opinion

PUBLISHED

UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT

No. 20-1483

OLD DOMINION ELECTRIC COOPERATIVE,

Plaintiff – Appellant,

v.

PJM INTERCONNECTION, LLC,

Defendant – Appellee.

Appeal from the United States District Court for the Eastern District of Virginia, at Richmond. M. Hannah Lauck, District Judge. (3:19-cv-00233-MHL)

Argued: October 28, 2021 Decided: January 19, 2022

Before MOTZ, KING, and HARRIS, Circuit Judges.

Affirmed by published opinion. Judge King wrote the opinion, in which Judge Motz and Judge Harris joined.

ARGUED: Joseph Michael Rainsbury, MILES & STOCKBRIDGE PC, Richmond, Virginia, for Appellant. Lucas M. Walker, MOLOLAMKEN, LLP, Washington, D.C., for Appellee. ON BRIEF: Thomas M. Wolf, MILES & STOCKBRIDGE PC, Richmond, Virginia, for Appellant. Robert M. Rolfe, Brian A. Wright, HUNTON ANDREWS KURTH LLP, Richmond, Virginia; Jeffrey A. Lamken, Washington, D.C., Jennifer E. Fischell, MOLOLAMKEN LLP, New York, New York, for Appellee. KING, Circuit Judge:

In this appeal, plaintiff Old Dominion Electric Cooperative challenges the district

court’s dismissal of its state law claims seeking nearly $15 million in damages from

defendant PJM Interconnection, LLC. Following a severe cold weather outbreak in

January 2014, Old Dominion unsuccessfully sought to recover certain electricity

generation costs from PJM in an administrative proceeding before the Federal Energy

Regulatory Commission (“FERC”). Old Dominion subsequently instituted the underlying

litigation in Virginia state court, pursuing four putative state law claims against PJM which

seek the same relief unsuccessfully claimed before FERC.

PJM timely removed the state court proceedings to the Eastern District of Virginia,

pursuant to 28 U.S.C. § 1441(a). PJM maintained therein that Old Dominion’s complaint

contests electricity transmission rates set forth in PJM’s federally filed tariff and that the

district court was vested with federal question jurisdiction under 28 U.S.C. § 1331. PJM

promptly moved to dismiss the complaint for failure to state a claim, while Old Dominion

moved for a remand to state court.

On March 31, 2020, the district court denied Old Dominion’s remand motion and

dismissed each of its claims with prejudice. See Old Dominion Elec. Coop. v. PJM

Interconnection, LLC, No. 3:19-cv-00233 (E.D. Va. Mar. 31, 2020), ECF No. 26 (the

“Dismissal Opinion”). In so ruling, the court determined that, consistent with our 2004

decision in Bryan v. BellSouth Communications, Inc., 377 F.3d 424 (4th Cir. 2004), Old

Dominion’s putative state law claims effectively challenge the terms of PJM’s federal

tariff. As such, and in accord with the principles enunciated by the Supreme Court in Gunn

2 v. Minton, 568 U.S. 251 (2013), and Grable & Sons Metal Products, Inc. v. Darue

Engineering & Manufacturing, 545 U.S. 308 (2005), the court ruled that the claims present

a substantial federal question. In granting PJM’s motion to dismiss, the court further

resolved that the so-called “filed-rate doctrine” barred it from awarding damages on Old

Dominion’s claims. On appeal, Old Dominion maintains that PJM’s tariff stands only as

a defense to its putative state law claims and that the district court consequently lacked

subject matter jurisdiction over those claims. As explained herein, Old Dominion’s

contentions are unpersuasive and are rejected. We therefore affirm the judgment of the

district court.

I.

A.

Old Dominion is a nonprofit electric utility that serves customers in Virginia,

Maryland, and Delaware. It generates and markets wholesale electric power, in part from

the operation of three natural-gas-fired power plants in Virginia and Maryland. PJM, on

the other hand, is not a utility but is instead a “regional transmission organization,” an

entity that operates the electrical grid in a defined geographic area and in accord with

extensive regulatory oversight by FERC. PJM is charged with supervising the transmission

of electricity in its market region, which consists of 13 states and the District of Columbia.

In fulfilling that responsibility, PJM controls the transmission facilities owned by its

member utilities — including Old Dominion. See 18 C.F.R. § 35.34(j), (k).

3 PJM’s relationship with each of its member utilities is governed by FERC’s

regulatory framework. The Federal Power Act vests FERC with exclusive regulatory

authority over “the transmission of electric energy in interstate commerce and the sale of

such energy at wholesale in interstate commerce,” directing FERC to ensure that all “rates

and charges made, demanded, or received by any public utility for or in connection with

the transmission or sale of electric energy” be “just and reasonable.” See 16 U.S.C.

§§ 824(a), 824d(a). Accordingly, FERC requires regional transmission organizations like

PJM to file schedules of proposed electricity transmission rates with the agency for its

approval. Once authorized by FERC, those rates are set forth in tariffs, which “[c]arry the

force of federal law,” in the same sense as ordinary federal regulations. See Bryan v.

BellSouth Commc’ns, Inc., 377 F.3d 424, 429 (4th Cir. 2004). Further, under the regulatory

rule known as the “filed-rate doctrine,” the transmission rates charged by utilities in

association with the generation and sale of electric power may not be higher or lower than

those set forth in FERC-approved tariffs. See Ark. La. Gas Co. v. Hall, 453 U.S. 571, 576

(1981).

PJM’s FERC-approved tariffs include (1) its Open Access Transmission Tariff (the

“PJM Tariff,” or simply “the Tariff”) and (2) its Amended and Restated Operating

Agreement (the “Operating Agreement”). The PJM Tariff prescribes rules controlling

PJM’s management of the mid-Atlantic energy market and, as relevant in this appeal, fixes

the price at which power generators may offer their energy production to PJM in standard

4 electricity auctions — specifically at $1000 per megawatt-hour. See J.A. 127. 1 The

Operating Agreement, to which participating utilities like Old Dominion subscribe, reflects

the terms of the Tariff. The Operating Agreement further affords PJM expansive powers

to take “measures appropriate to alleviate an Emergency, in order to preserve reliability”

in the electric market, principally by calling on its member utilities “to start, shutdown, or

change output levels of [their] generation units” at any time. See Old Dominion Elec.

Coop. v. FERC, 892 F.3d 1223, 1228 (D.C. Cir. 2018). As the relevant regulatory tariffs,

the PJM Tariff and Operating Agreement together “conclusively and exclusively

enumerate the rights and liabilities of the contracting parties.” See Marcus v. AT&T Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
24 F.4th 271, Counsel Stack Legal Research, https://law.counselstack.com/opinion/old-dominion-electric-v-pjm-interconnection-llc-ca4-2022.