Ohio Farmers Insurance Company and S.C. Nestel, Inc. v. Indiana Drywall & Acoustics, Inc.

970 N.E.2d 674, 2012 Ind. App. LEXIS 654, 2012 WL 2872886
CourtIndiana Court of Appeals
DecidedMay 22, 2012
Docket49A02-1106-CC-534
StatusPublished
Cited by11 cases

This text of 970 N.E.2d 674 (Ohio Farmers Insurance Company and S.C. Nestel, Inc. v. Indiana Drywall & Acoustics, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio Farmers Insurance Company and S.C. Nestel, Inc. v. Indiana Drywall & Acoustics, Inc., 970 N.E.2d 674, 2012 Ind. App. LEXIS 654, 2012 WL 2872886 (Ind. Ct. App. 2012).

Opinion

OPINION

BAKER, Judge.

Appellants-defendants Ohio Farmers Insurance Company (Ohio Farmers) and S.C. Nestel, Inc. (Nestel), appeal the trial court’s denial of their respective motions for partial summary judgment with regard to plaintiff-appellee Indiana Drywall & Acoustics’s (Indiana Drywall) cause against Nestel and Ohio Farmers on its claim for conversion, breach of contract, fraud, and breach of payment on a bond.

Nestel argues that the trial court improperly denied its motion regarding Indiana Drywall’s fraud claim because the designated evidence did not support a claim on that count and Indiana Drywall could prove no damages. In the alternative, Nestel maintains that the trial court improperly denied its motion for judgment on the evidence at trial on that count.

Ohio Farmers argues that the trial court improperly denied its motion for partial summary judgment with regard to Indiana Drywall’s action for breaching the terms of the bond because the designated evidence establishes that Indiana Drywall did not bring its cause of action against Ohio Farmers in a timely fashion under the terms of the bond.

We conclude that the judgment entered in Indiana Drywall’s favor against Nestel was proper, but reverse the denial of Ohio Farmers’s motion for summary judgment with respect to Indiana Drywall’s bond claim.

FACTS

In August 2005, Nestel, along with Horne Development, L.P. and Horne Properties-Bedford, LLC (collectively, Horne) entered into a contract where Nes-tel agreed to construct a Walmart and some other retail stores on property that Horne owned in Lawrence County.

Nestel hired several subcontractors to perform certain aspects of the work associated with the project. One of the subcontractors was Indiana Drywall, and on *678 September 12, 2005, it entered into a “Standard Form of Agreement Between Contractor and Subcontractor” (Contract) with Nestel. Appellants’ App. p. 28£M0. In accordance with the Contract, Indiana Drywall was to furnish all drywall and framing work in relation to the project.

During the course of the project, a dispute arose between Nestel and Home regarding Horne’s claims that Nestel and its subcontractors were wrongfully delaying completion of the project and that there were refusals and delays in making full and prompt payment for labor and materials that had been provided for the project.

By August 22, 2006, Indiana Drywall believed that it had completed all work contemplated under the Contract and various change orders and directives. All of its work was purportedly completed to Nestel and Home’s satisfaction. However, Indiana Drywall told Nestel that it believed that it was entitled to additional compensation for work performed on the project. Nestel disputed the claim, in part, based on certain backcharge claims that Home asserted on the project because of incomplete and defective work of Nes-tel’s subcontractors, as well as delays for which Home asserted claims for liquidated damages.

When Indiana Drywall completed its work on the project, it alleged that Nestel owed it an outstanding balance of $209,075.38. As a result, on August 31, 2006, Indiana Drywall filed a “Notice of Intention to Hold a Mechanic’s Lien” against Horne in the Lawrence County Recorder’s Office in the amount of $209,075.38. Id. at 278, 280-87. Thereafter, Indiana Drywall received a few payments from Nestel that reduced the balance that was allegedly owed to $148,633.75.

When Indiana Drywall started to press Nestel for payment in 2007, Nestel informed Indiana Drywall that it had a payment bond on the project. Apparently in light of Nestel’s payments and assurances following the recording of the lien, Indiana Drywall did not move to foreclose on the lien.

On May 24, 2007, Nestel faxed a one page document to Indiana Drywall, entitled “Payment Bond” that had been issued by Ohio Farmers. Appellants’ App. p. 205, 208-09. Linda Wollom, Indiana Drywall’s secretary, contacted Ohio Farmers and indicated that it had not been paid in full for its work on the project. Wollom asked Ohio Farmers what had to be done to file a claim and Ohio Farmers suggested that she send a “letter of request.” Tr. p. 193. Thereafter, Hansford Kelly, owner and president of Indiana Drywall, prepared and sent a letter to Ohio Farmers seeking payment under the bond for the outstanding balance that Nestel owed in the amount of $148,633.75. The provisions of the payment bond had been recorded in the Lawrence County Recorder’s Office.

In a letter of June 4, 2007, Ohio Farmers acknowledged receipt of Kelly’s May 25, 2007 letter and enclosed a proof of claim for Indiana Drywall’s use in submitting a claim under the bond. Indiana Drywall received a proof of claim form on July 9, 2007. That same day, Indiana Drywall completed the proof of claim form and faxed and mailed it to Ohio Farmers.

Thereafter, Indiana Drywall received a letter, advising that Ohio Farmers would be in contact at some point concerning Indiana Drywall’s claim. Indiana Drywall asked Ohio Farmers to provide it with a copy of its payment bond but Ohio Farmers never did so.

In January 2008, Howard Golden of Nestel contacted Kelly, the owner and president of Indiana Drywall, to see if Indiana Drywall would be willing to waive *679 its lien. In exchange, Golden apparently promised that Nestel would pay Indiana Drywall the outstanding balance of $148,633.75 that was owed.

The conditional release and waiver states in relevant part that

NOW, THEREFORE, for and in consideration of ... $148,633.75, the payment of which has been promised as the sole consideration for this Final Conditional Release and Waiver of Lien which shall become effective only upon the receipt of such payment, Subcontractor hereby waives and releases any and all liens....
This Final Conditional Release and Waiver of Lien is given in order to induce payment of the amount indicated above, and becomes effective only upon receipt of such amount by Subcontractor.

Appellants’ App. p. 264.

According to the wife of Indiana Drywall’s president, Nestel faxed the release and waiver form to Indiana Drywall, and purportedly stated that it would pay Indiana Drywall the outstanding balance of $148,633.75 if the release was signed. Nestel apparently told Greg Kelly — Hans-ford’s son — that Nestel would immediately pay the outstanding balance. However, Nestel never paid and Indiana Drywall subsequently went out of business.

In May 2010, Indiana Drywall received notice for the first time of the specific bond provisions. After obtaining a copy of the bond in June 2010, and having received no further payment from Nestel, Indiana Drywall brought Ohio Farmers into the impending litigation for the purpose of recovering under the bond.

The bond provides in relevant part, that 4. The Surety [Ohio Farmers] shall have no obligation to Claimants [Indiana Drywall] under this Bond until:
4.1 Claimants who are employed by or have a direct contract with the Contractor [Nestel] have given notice to the Surety ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
970 N.E.2d 674, 2012 Ind. App. LEXIS 654, 2012 WL 2872886, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-farmers-insurance-company-and-sc-nestel-inc-v-indiana-drywall-indctapp-2012.