Ogunquit Village Corporation v. R. M. Davis, Administrator, Soil Conservation Service

553 F.2d 243, 7 Envtl. L. Rep. (Envtl. Law Inst.) 20381, 9 ERC (BNA) 2160, 1977 U.S. App. LEXIS 13735, 9 ERC 2160
CourtCourt of Appeals for the First Circuit
DecidedApril 20, 1977
Docket76-1425
StatusPublished
Cited by22 cases

This text of 553 F.2d 243 (Ogunquit Village Corporation v. R. M. Davis, Administrator, Soil Conservation Service) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ogunquit Village Corporation v. R. M. Davis, Administrator, Soil Conservation Service, 553 F.2d 243, 7 Envtl. L. Rep. (Envtl. Law Inst.) 20381, 9 ERC (BNA) 2160, 1977 U.S. App. LEXIS 13735, 9 ERC 2160 (1st Cir. 1977).

Opinion

COFFIN, Chief Judge.

The sand dune of Ogunquit, Maine, stretches for more than a mile along the southern Maine coast. Rising twenty feet above a wide sandy beach, the dune is cut off from the mainland by salt water marshes and the Ogunquit River estuary. The dune and beach have long brought tourists to the nearby village of Ogunquit. The dune’s popularity eventually proved its undoing. The grass and shrubs that held the dune in place were trampled, and the sand began to blow away. The estuary’s clam flats were slowly choked by sand from the eroding dune, and sand storms drove visitors away on windy days. Mainland residents began to fear that in a winter storm the sea would break through the dune and wash away their homes. Finally the village of Ogunquit asked the federal Soil Conservation Service (the Service) for its help in restoring the dune. The Service proposed that the dune be rebuilt and replanted. An environmental impact statement was prepared and approved. Work began.

The first section of the reconstructed dune was built of sand dredged from the *244 Ogunquit estuary. The new dune resembled a dike; it was twenty-two feet high with a flat, twenty-five foot top and steep sloping sides. The first part of the project was completed by July of 1974. But not enough wind-blown sand could be dredged from the estuary to complete more than a fifth of the new dune. The Service sought the remaining sand from an inland source. Instead of the fine white quartz sand that is native to the Ogunquit dune, the Service bought coarse yellow sand and gravel. It began to dump this mixture on the beach in December of 1974. The job was finished in about a month. The village protested in January- of 1975, but it was too late. In place of the famous white Ogunquit dune, the villagers found what to many was an ugly yellow bunker. The village, joined by several other plaintiffs, then began this suit.

The district court granted summary judgment in the Service’s favor. The village appeals from only two aspects of the decision below. The district court refused to entertain the village’s claim for breach of contract because the Tucker Act gives district courts jurisdiction over contract claims against federal agencies only if the claim does not exceed $10,000. 28 U.S.C. § 1346(a)(2). The village believes that the district court was obligated to accept pendent jurisdiction over the contract claim, citing National Helium Corp. v. Morton, 455 F.2d 650 (10th Cir. 1971). Beyond noting that this case is inapposite, we agree with the court below that the village’s contention “does not warrant discussion”.

The second issue on appeal is more troubling. The village seeks relief under the National Environmental Policy Act of 1969 (NEPA). 42 U.S.C. §§ 4321 — 47. NEPA requires an environmental impact statement (EIS) whenever a federal agency proposes a major action with significant environmental effects. Id. § 4332(2)(C). The village objected that the EIS filed by the Service was inadequate, and the district court found merit in the attack:

“The record discloses that the inland fill used on the northerly 4,700 feet of the reconstructed dune is composed of sand, obtained from inland sources, which varies substantially in texture and color from the indigenous beach sand. Yet neither the draft nor the final EIS suggested that the inland fill to be used on this portion of the Project was to be of a texture or color different from that of the beach sand. In addition, the EIS nowhere discussed the adverse effect of the use of nonconforming fill on the aesthetics of the beach; nor did the EIS examine the availability of compatible beach sand from other sources.18 The EIS was plainly defective in failing to provide any description of the fill to be used, the environmental consequences of using noncompatible materials, and the possible alternatives to their use.”

Footnote 18 reads:

“The administrative record shows that SCS in fact investigated the possible use of beach sand- from other areas on the Maine coast; but these sources were rejected, apparently because of cost and because of a desire not to deplete the supply of sand in other coastal areas.”

The Service contended that laches barred the village’s claim, but the district court rejected this argument, at least with respect to the texture and color of the sand. 1 The court stated:

“[Pjlaintiffs could not have discovered that the reconstructed dune was to be composed of noncompatible fill until the Project was almost complete, and . plaintiffs filed the present action as soon as reasonably could be expected after they had notice of the characteristics of *245 the fill. It is true that the use of material from inland sources was apparently contemplated from the beginning of the Project’s formulation. . . . Nonetheless, neither the draft EIS, the final EIS, nor any other planning document, gave any indication that the fill was to be anything other than sand compatible with the existing beach sand.19 [Pjlaintiffs registered strenuous objections as soon as the inland fill began to be placed on the dune.”

Footnote 19 reads:

“Indeed, the Preliminary Investigation Report and the draft and final Work Plans may have affirmatively misled by specifying that the suitability of available inland sources would have to be investigated ‘as to their textural characteristics (i. e., size, grading) . . . ” 2

Notwithstanding these conclusions, the court held that neither damages 3 nor equitable relief could be granted once the project was completed. In so concluding, the district court relied on decisions, including our own, which have “declined to apply NEPA to those portions of challenged projects on which construction has been completed or on which work has progressed so far that meaningful future federal decisionmaking has been foreclosed.” Essex County Preservation Ass’n v. Campbell, 536 F.2d 956 (1st Cir. 1976); Jones v. Lynn, 477 F.2d 885, 889-90 (1st Cir. 1973); Boston v. Volpe, 464 F.2d 254 (1st Cir. 1972); Ragland v. Mueller, 460 F.2d 1196 (5th Cir. 1972); Arlington Coalition on Transp. v. Volpe, 458 F.2d 1323 (4th Cir. 1972).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sierra Club v. Pena
915 F. Supp. 1381 (N.D. Ohio, 1996)
Zarrilli v. Weld
875 F. Supp. 68 (D. Massachusetts, 1995)
Gettysburg Battlefield Preservation Ass'n v. Gettysburg College
799 F. Supp. 1571 (M.D. Pennsylvania, 1992)
Environmental Rights Coalition, Inc. v. Austin
780 F. Supp. 584 (S.D. Indiana, 1991)
Blue Ocean Preservation Society v. Watkins
754 F. Supp. 1450 (D. Hawaii, 1991)
Valley Citizens for a Safe Environment v. Aldridge
695 F. Supp. 605 (D. Massachusetts, 1988)
Richland Park Homeowners Ass'n v. Pierce
671 F.2d 935 (Fifth Circuit, 1982)
Wilfredo Marquez-Colon v. Ronald W. Reagan
668 F.2d 611 (First Circuit, 1981)
Alert v. Lewis
2 Mass. Supp. 680 (D. Massachusetts, 1981)
Guilliaem Aertsen v. Moon Landrieu, Etc.
637 F.2d 12 (First Circuit, 1980)
City Of Romulus v. County Of Wayne
634 F.2d 347 (Sixth Circuit, 1980)
Aertsen v. Landrieu
488 F. Supp. 314 (D. Massachusetts, 1980)
Citizens for Responsible Area Growth v. Adams
477 F. Supp. 994 (D. New Hampshire, 1979)
Chamber of Commerce of US v. Dept. of Interior
439 F. Supp. 762 (District of Columbia, 1977)
Jose Ortega Cabrera v. Municipality of Bayamon
562 F.2d 91 (First Circuit, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
553 F.2d 243, 7 Envtl. L. Rep. (Envtl. Law Inst.) 20381, 9 ERC (BNA) 2160, 1977 U.S. App. LEXIS 13735, 9 ERC 2160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ogunquit-village-corporation-v-r-m-davis-administrator-soil-ca1-1977.