Odyssey International, Inc.

Armed Services Board of Contract Appeals·Decided June 2, 2020·No. ASBCA No. 62085, 62145, 62193·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Odyssey International, Inc. ) ASBCA Nos. 62085, 62145, 62193 ) Under Contract No. W912HN-19-C-3005 )

APPEARANCES FOR THE APPELLANT: Brian C. Johnson, Esq. H. Burt Ringwood, Esq. Alan R. Houston, Esq. Strong & Hanni Law Firm Salt Lake City, UT

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Laura J. Arnett, Esq. Anna F. Kutz, Esq. Madeline Crocker, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Savannah

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL

Appellant, Odyssey International, Inc., appeals from (1) the May 2019 default termination of its construction contract for failure to secure bonding (ASBCA No. 62085), (2) the government’s assessment against Odyssey of $1.9 million in allegedly excess reprocurement costs (ASBCA No. 62145), and (3) a related Contractor Performance Assessment System (CPARS) evaluation rating Odyssey’s performance “Unsatisfactory” (ASBCA No. 62193). The government requests summary judgment in these consolidated appeals, contending, inter alia: (1) the government acted within its discretion to terminate the contract for default and Odyssey has not demonstrated that its failure to perform was excusable (ASBCA No. 62085); (2) the government is entitled to the alleged excess reprocurement costs (ASBCA No. 62145); and (3) the CPARS rating was properly issued and not arbitrary and capricious or an abuse of discretion (ASBCA No. 62193). The Board has stayed proceedings pending resolution of the motion, and the parties have not yet engaged in any discovery.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

The following is not in genuine dispute. On March 27, 2019, Odyssey and the government contracted for appellant to construct an air traffic control tower for an Air Force Base in North Carolina, for the amount of $19,832,000 (gov’t mot. at 3 ¶¶ 1, 6; app. resp. at 3 ¶¶ 1, 6). The contract incorporates by reference Federal Acquisition Regulation (FAR) 52.228-15, PERFORMANCE AND PAYMENT BONDS – CONSTRUCTION (OCT 2010) (gov’t mot. at 3 ¶ 7; see app. resp. at 3 ¶ 7). The contract provides that Odyssey submit performance and payment bonds to the government within 10 days after award (gov’t mot. at 4 ¶ 8; see app. resp. at 3 ¶ 8). The contract also incorporates by reference FAR 52.228-1, BID GUARANTEE (SEP 1996), and FAR 52.249-10, DEFAULT (Fixed-Price Construction) (APR 1984) (gov’t mot. at 4 ¶¶ 9-10; see app. resp. at 3 ¶¶ 9-10).

On April 10, 2019, Odyssey’s insurance agent wrote to Odyssey:

We have made vigorous efforts to market your account to these standard-market sureties CNA, Great American, Zurich, and NAS, and one of the leading specialty market sureties, HCC Toyoko Marine. Even with the $1,000,000 capitalization from Whitney’s [Whitney McBride, Odyssey’s principal shareholder (McBride decl. ¶ 1)] home refinance, none of these sureties will bond the [] project. The primary reason with each surety is way too little working capital in the company. To support a $40-50,000,000 backlog, the minimum working capital number is $2,500,000, and usually that is with a hefty bank line of credit and substantial net worth from personal indemnitors. While your profit projections for 2019 are very encouraging, it doesn’t fix working capital soon enough for surety support on this size of work program.

Additionally, . . . [t]he potential Hub-Zone violation is a big cloud until you are absolved of liability . . . .

(App. supp. R4, tab 24 at 30 (alterations added); gov’t mot. at 9 ¶ 46; see app. resp. at 6 ¶ 46, 8 ¶ 8; gov’t reply at 6 ¶ 8) On April 16, 2019, one surety wrote to Odyssey’s insurance agent:

Although the account is thin, the main reason we have to pass on this is due to the Hub Zone investigation in place. The law underlying the false claim (the false claim act) has no individual Hub Zone designation which would mean the company is subject to investigation. So even though the FBI has indicated it is not focusing on the company, there is still a potential that can occur and a surety who issues any bonds for the company who after the fact is found are

2 not what the claim to be (Hub Zone compliant) are subject to triple damages.

We, as a company, have seen this in the past and will not consider any requests with anything pending regarding Hub Zone claims. We would not be willing to consider anything for the account until this issue is completely resolved.

(App. supp. R4, tab 30 at 40-41; see app. resp. at 8 ¶ 10; gov’t reply at 6 ¶ 10) On April 22, 2019, Odyssey wrote to the contracting officer (CO) indicating Odyssey’s inability to obtain performance and payment bonds (gov’t mot. at 4 ¶ 12; app. resp. at 3 ¶ 12). On April 25, 2019, the CO issued a cure notice to Odyssey, requiring Odyssey to produce performance and payment bonds by May 6, 2019 (gov’t mot. at 4 ¶ 13; app. resp. at 3 ¶ 13).

On May 3, 2019, the CO received an email from Odyssey and a May 1, 2019 letter from Odyssey’s insurance agent, re-iterating Odyssey’s inability to obtain performance and payment bonds for the contract (gov’t mot. at 4 ¶ 14; app. resp. at 3 ¶ 14; see R4, tab 4.03). In the email, Odyssey indicated that it was willing to “waive the time granted to cure” and that the government was “free to proceed in replacing Odyssey International, Inc. as the contractor on the project” (gov’t mot. at 4 ¶ 14; app. resp. at 3 ¶ 14 (addressing R4, tab 4.03)). In the letter from the insurance agent to the CO, the insurance agent wrote:

In the summer of 2018, Odyssey was informed that their former chief financial officer was a prime target in a criminal investigation by the US Attorney’s Office. The investigation is ongoing and involves a potential HUB Zone violation by Odyssey and fraud by the former chief financial officer. . . . With all the sureties we approached, the “cloud” of this investigation materially impairs Odyssey’s ability to obtain bonds on new projects until the case is settled.

(R4, tab 4.03 at 265)

As of May 6, 2019, Odyssey had not provided to the government the performance and payment bonds required by the contract for Odyssey to proceed with performance of the contract (gov’t mot. at 5 ¶ 16; app. resp. at 4 ¶ 16). On May 6, 2019, the CO issued a notice terminating the contract for default for failure to provide performance and payment bonds, “effective immediately upon receipt of this Notice” (R4, tab 2.01; see gov’t mot. at 5 ¶ 16; app. resp. at 4 ¶ 16). On May 8, 2019, the CO

3 issued a modification terminating the contract for default “in conjunction with the Notice of Termination dated May 6, 2019” (R4, tab 5.01; see gov’t mot. at 5 ¶ 16; see app. resp. at 4 ¶ 16).

DECISION

Summary judgment shall be granted if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law. Avant Assessment, LLC, ASBCA No. 58867, 15-1 BCA ¶ 36,067 at 176,127 (citing FED. R. CIV. P. 56(a)). All significant doubt over factual issues must be resolved in favor of the party opposing summary judgment, and we draw all justifiable inferences in favor of the nonmoving party. DCX-CHOL Enterprises, ASBCA Nos. 61806, 61807, 20-1 BCA ¶ 37,552 at 182,341. There is no dispute that Odyssey failed to provide the bonds required by the contract; consequently, the government is entitled to judgment as a matter of law in ASBCA No. 62085 that Odyssey defaulted on the contract. Marshall’s Elec., Inc., ASBCA No. 59749, 16-1 BCA ¶ 36,300 at 177,017.

Otherwise, we are not persuaded that the government has met its burden, for at least one reason. The government cites FAR 52.249-10 (mot. at 4 ¶ 10), which, at paragraph (b), provides:

The Contractor’s right to proceed shall not be terminated nor the Contractor charged with damages under this clause, if . .

Free access — add to your briefcase to read the full text and ask questions with AI

Odyssey International, Inc., (asbca 2020).

Odyssey International, Inc. (Odyssey International, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

National Eastern Corp. v. United States
477 F.2d 1347 (Court of Claims, 1973)