OCR, Inc. v. United States

39 Cont. Cas. Fed. 76,695, 31 Fed. Cl. 716, 1994 U.S. Claims LEXIS 162, 1994 WL 450611
CourtUnited States Court of Federal Claims
DecidedAugust 23, 1994
DocketNo. 10-86 C
StatusPublished

This text of 39 Cont. Cas. Fed. 76,695 (OCR, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
OCR, Inc. v. United States, 39 Cont. Cas. Fed. 76,695, 31 Fed. Cl. 716, 1994 U.S. Claims LEXIS 162, 1994 WL 450611 (uscfc 1994).

Opinion

OPINION and ORDER

TURNER, Judge.

This opinion addresses plaintiffs motion for partial summary judgment filed on May [717]*71718, 1993, and defendant’s cross-motion for summary judgment filed on July 27, 1993. We conclude that plaintiffs motion should be denied and that defendant’s cross-motion should be (1) granted as to count I of the complaint but (2) denied as to count II of the complaint.

I

OCR, Inc., by complaint filed January 6, 1986, seeks relief for alleged breach by the Department of Justice (DOJ) of two separate service contracts, one an express, written contract for the keying of some information as well as the optical scanning of certain documents into a computerized data base (Contract No. 4C-M-CIV-0014) and the other an implied-in-fact contract for the optical scanning of document contents into a computerized data base (allegedly formed after the expiration of Contract No. 2C00007, an express, written contract for optical scanning).

In count I of the complaint, plaintiff challenges the contracting officer’s (CO’s) decision terminating the keying/scanning contract for default. Plaintiff claims that the termination was for the convenience of DOJ and seeks $819,598 in damages. In count II, plaintiff seeks $14,197 which it claims is due for certain invoiced work and for related expenses pertaining to the implied-in-fact optical scanning contract.

Plaintiff has moved for partial summary judgment on the issue of liability of defendant for damages arising from the default termination of the keying/scanning contract challenged in count I. Defendant has moved for summary judgment on both counts I and II.1 We address each count in turn.

II

A

In 1983, DOJ solicited bids from data processing service contractors in connection with a broad, multi-task, litigation support services arrangement. In general, litigation support services entailed the organization and indexing of documents involved in DOJ’s numerous pending civil cases. Plaintiff was the successful bidder for Task D — Data Reduction — of DOJ’s solicitation.2 CACI Federal, Inc., the contractor selected for Task C— Document Processing — was responsible for, among other things, the recording of document titles or subjects and other bibliographical information pertaining to documents, on document coding forms (DCFs).

Task D required plaintiff to key information from CACI coded DCFs onto, magnetic tapes (keying), to convert trial transcripts, depositions and other documents into machine readable media (scanning) and to provide general data conversion or keying services. Def.Br., Appendix at 65-68. Plaintiff subcontracted with MIH, Inc. to perform all the keying work while plaintiff performed all the scanning work.

Plaintiffs keying responsibilities under the Task D contract were triggered by DOJ’s issuance of requests for services generally referred to in this litigation as “delivery orders.” Def.Br., Appendix at 90, 91. Delivery orders included the case name, an estimate of the total amount of DCFs and characters to be keyed, an estimate of the number of DCFs that would be delivered each week and the expected throughput rate per week.3 Pl.Br., Appendix at 49-144. Coded DCFs (prepared by CACI, the Task C contractor) were to be delivered to plaintiff within ten days after issuance of each delivery order. Def.Br., Appendix at 95. Defendant issued the first delivery orders in December 1983. Pl.Br., Appendix at 49. Plaintiff, however, did not receive any DCFs until the third week of March 1984. Pl.Br. at 51, 52.

[718]*718B

Under the terms of the keying contract, plaintiff was ordinarily to deliver completed magnetic tapes within two weeks after its receipt of DCFs to be keyed based on a throughput rate not to exceed five million keyed characters per week. Under an accelerated turnaround schedule, magnetic tapes were to be delivered within one week of receipt of DCFs to be keyed based on a throughput not to exceed two million keyed characters. Def.Br., Appendix at 70, 92. The throughput rate for the regular turnaround schedule was increased from five million to eight million keyed characters per week by bilateral Modification No. 0001, executed March 26,1984. There was no change to the accelerated turnaround schedule. Def. Br., Appendix at 115.

Plaintiff was unable to meet the throughput rates and turnaround times specified in the contract. In addition, plaintiff had problems satisfying the accuracy requirements of the contract. On July 17, 1984, Contracting Officer Michael Dumond issued a cure notice to plaintiff. Def.Br., Appendix at 23-24. This notice referenced DOJ’s concern over MIH’s expressed inability to meet the eight million character keying capacity in spite of plaintiffs agreement to perform at this level. Dumond required plaintiff to ensure that it would be able to meet the eight million characters per week requirement. By letter dated August 10,1984, plaintiff assured Dumond that it would meet required production by employing additional subcontractors. Id. at 25.

Clarisse Abramidis, Case Manager of the Civil Division, by letter of September 20, 1984, notified plaintiff that a large number of errors had been found in the DCF keying work delivered by plaintiff for three specific cases. Def.Br., Appendix at 26. Soon thereafter, Eric Donovan, Case Manager for asbestos litigation, by letter of September 28, 1984, informed plaintiff of the rejection of OCR’s first batch of keying for the asbestos eases because of keying errors. Id. at 41. Sometime in October 1984, plaintiff dismissed MIH as its subcontractor and replaced it with C & M Systems Corporation (C & M). Id. at 146-47, Deposition of Jon P. North, President of OCR; Def.Br., Appendix at 4.

Plaintiff continued to have problems meeting the turnaround times and accuracy requirements of the contract. At a December 7, 1984 meeting, plaintiff was informed that of 22,676 DCFs sent to plaintiff for keying over the period from October 31, 1984 through November 30, 1984, plaintiff had keyed and delivered tapes for only 473 and that all of those tapes were returned for correction of formatting errors. Def.Br., Appendix at 5, Declaration of Abramidis. Shortly after this meeting, plaintiff provided a “Delivery Schedule” which established dates for the delivery of specific keying work, with the completion of all work received to that date by December 20, 1984. Def.Br., Appendix at 32. Plaintiff failed to meet its own deadlines.

C

On January 7, 1985, plaintiff was notified by telegram that the contract was terminated for default because of plaintiffs “failure to deliver keyed material within the delivery time specified in the contract and within the accuracy levels specified in the contract.” Def.Br., Appendix at 35. The CO issued a final default termination decision on January 22, 1985. Id. at 36-37.

Ill

Plaintiff, in its motion for partial summary judgment with respect to count I of the complaint, asserts that DOJ breached Article XII of the keying contract by not delivering DCFs within ten days of the issuance of a delivery order.4 Pl.Br. at 31. Next, plaintiff argues that DOJ breached the contract by failing to deliver keying specifications at the initial stages of plaintiffs performance and [719]*719that this failure to deliver constituted a nondisclosure of superior knowledge.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gould, Inc. v. The United States
935 F.2d 1271 (Federal Circuit, 1991)
Roland Spruill v. Merit Systems Protection Board
978 F.2d 679 (Federal Circuit, 1992)
Total Medical Management, Inc. v. United States
29 Fed. Cl. 296 (Federal Claims, 1993)
Pacific Gas & Electric Co. v. United States
31 Cont. Cas. Fed. 71,411 (Court of Claims, 1983)
Adam v. United States
26 Cl. Ct. 782 (Court of Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cont. Cas. Fed. 76,695, 31 Fed. Cl. 716, 1994 U.S. Claims LEXIS 162, 1994 WL 450611, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ocr-inc-v-united-states-uscfc-1994.