Oak Ridge Construction Co. v. Tolley

504 A.2d 1343, 351 Pa. Super. 32, 1985 Pa. Super. LEXIS 10488
CourtSupreme Court of Pennsylvania
DecidedDecember 27, 1985
Docket02929
StatusPublished
Cited by33 cases

This text of 504 A.2d 1343 (Oak Ridge Construction Co. v. Tolley) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oak Ridge Construction Co. v. Tolley, 504 A.2d 1343, 351 Pa. Super. 32, 1985 Pa. Super. LEXIS 10488 (Pa. 1985).

Opinion

HOFFMAN, Judge:

This is an appeal from the lower court’s judgment awarding appellee, Oak Ridge Construction Co. (Oak Ridge), damages for appellants’, the Tolleys’, anticipatory breach of a construction contract. The Tolleys contend on appeal that the lower court erred in (1) finding that they, rather than Oak Ridge, had breached the contract; (2) striking testimony as to the unreasonableness of drilling an 800 foot well; and (3) awarding damages to Oak Ridge. We affirm in part, reverse in part, and remand for further proceedings.

In June, 1982, the Tolleys and Oak Ridge entered into a contract pursuant to which Oak Ridge agreed to construct a residence on the Tolleys’ property for $64,500. 1 The Tolleys provided Oak Ridge with specifications, which were incorporated into the contract, and a plot plan. The specifications contained, inter alia, the following provision:

20. Water Supply
Drill well 150' deep with 40' of 6" casing, lk H.P. submersible pump and a 21 gallon storage tank. Should well be more than 150' a charge of $6.50 per ft. will be made. Should casing be over 40' a charge of $7.00 per ft. will be made. Should well depth require a deep lift pump, extra cost to be borne by owner. Well depth over 100' may require a larger pump.

(Emphasis in original). Before drilling began, Oak Ridge warned the Tolleys that the well might be very deep because other wells in the area had been drilled to depths of *37 760 and 975 feet. Oak Ridge then drilled the well at a place indicated by one of the Tolleys’ employees after referring to the plot plan. It was completed on August 24, 1982, after being drilled to a depth of 800 feet. On August 27, Oak Ridge sent the Tolleys an invoice including charges of $4225 for the extra 650 feet of drilling and $616 for an extra 88 feet of casing, amounts computed using the rates specified in the contract. On September 2, Mr. Tolley wrote Oak Ridge stating that those charges were “in dispute or disagreement. All work under item 20 (Water Supply) ... are [sic] to cease pending satisfactory resolution or settlement under item 13 (Arbitration) of our construction agreement.” 2 Oak Ridge replied on September 7, stating that it believed that the Tolleys had breached the contract by refusing to pay the invoice and that it was giving them ten days notice under paragraph seven of the contract (Termination by Contractor), which provides as follows:

Should owner in any manner, by act or omission, violate or breach any covenant herein, then CONTRACTOR may, at his option, terminate this agreement, upon ten (10) days written notice to OWNER of any such violation or breach. Upon failure of OWNER to correct the same within the ten (10) day period, then, and in such event of termination, CONTRACTOR shall be entitled to receive payment for all unpaid materials, labor, and work of sub-contractors, for work and materials completed, installed, delivered on site, and ordered but undelivered and not installed, plus 20% of the total contract price as liquidated damages. In the event CONTRACTOR shall stop work hereunder, he shall in no way be liable for any loss or damage whatsoever as a result thereof.

Oak Ridge also notified the Tolleys that it was stopping work on the house and named an arbitrator in response to Mr. Tolley’s letter and pursuant to paragraph thirteen of the contract. 3 On September 10, Mr. Tolley responded, *38 stating, “arbitration under our contract is not advised at this time.”

Based upon these facts, the court below found that the Tolleys had committed an anticipatory breach of the contract justifying Oak Ridge’s termination. See Lower Court Opinion dated October 1, 1984 at 11. We disagree.

“An anticipatory breach of a contract occurs whenever there has been a definite and unconditional repudiation of a contract by one party communicated to another. A statement by a party that he will not or cannot perform in accordance with agreement creates such a breach. See 4 Corbin on Contracts § 959, p. 852-856 (1951).”

Jonnet Development Corp. v. Dietrich Industries, Inc., 316 Pa. Superior Ct. 533, 543, 463 A.2d 1026, 1031 (1983), quoting Wolgin v. Atlas United Financial Corp., 397 F.Supp. 1003, 1014 (E.D.Pa.1975), aff'd 530 F.2d 963, 966 (3d Cir.1976). See also McClelland v. New Amsterdam Casualty Co., 322 Pa. 429, 433, 185 A. 198, 200 (1936); Restatement (Second) of Contracts § 250 (1981) [hereinafter cited as Restatement].

In order to constitute a repudiation, a party’s language must be sufficiently positive to be reasonably interpreted to mean that the party will not of cannot perform. Mere expression of doubt as to his willingness or ability to perform is not enough to constitute a repudiation, although such an expression may give an obligee reasonable grounds to believe that the obligor will commit a *39 serious breach and may ultimately result in a repudiation____ However, language that under a fair reading “amounts to a statement of intention not to perform except on conditions which go beyond the contract” constitutes a repudiation. Comment 2 to Uniform Commercial Code § 2-610.

Restatement, supra § 250 comment b (emphasis added).

In the instant case, we cannot say that the language in Mr. Tolley’s letter constituted a “definite and unconditional repudiation” of the contract which “amounts to a statement of intention not to perform except on conditions which go beyond the contract.” The letter merely stated that the charges for work performed under item twenty of the contract’s specifications were “in dispute or disagreement” and requested resolution of the dispute under the arbitration clause of the contract. The letter did not contain an unequivocal refusal to pay the drilling charges or a repudiation of the entire contract. Thus, when Oak Ridge gave the Tolleys ten days notice that it was terminating the contract, the Tolleys had not committed an anticipatory breach.

We must therefore turn to the Tolleys’ contention that Oak Ridge breached the contract either by (1) drilling the well to the allegedly unreasonable depth of 800 feet or (2) stopping work on the house. 4 In connection with their first allegation, the Tolleys argue that the lower court erred *40 in striking testimony concerning the reasonableness of drilling a well to that depth. We disagree.

Questions of the admission and exclusion of evidence are within the sound discretion of the trial court and will not be reversed on appeal absent an abuse of discretion. Lewis v. Mellor, 259 Pa.Superior Ct. 509,

Related

Lystn, LLC v. Stone, R. and Estate of: Hill, J.
Superior Court of Pennsylvania, 2025
FOSTER v. WATSON
W.D. Pennsylvania, 2024
Sharp, J. v. Castro, J.
Superior Court of Pennsylvania, 2020
Fisher v. Rondo Pools
Court of Appeals of Arizona, 2019
American Diabetes Ass'n v. Friskney Family Trust, LLC
177 F. Supp. 3d 855 (E.D. Pennsylvania, 2016)
Manning, R. v. Kelly, W.
Superior Court of Pennsylvania, 2015
Joan Glisson Trust v. Delaware Valley Saving Bank
Superior Court of Pennsylvania, 2014
Joan I. Glisson Trust v. Greater Delaware Valley Savings Bank
32 Pa. D. & C.5th 512 (Delaware County Court of Common Pleas, 2013)
Allegheny Energy Supply Co. v. Wolf Run Mining Co.
53 A.3d 53 (Superior Court of Pennsylvania, 2012)
Eckert v. Lehigh Valley Women's Med. Spec., P.C.
26 Pa. D. & C.5th 1 (Lehigh County Court of Common Pleas, 2012)
Boro Construction, Inc. v. Ridley School District
992 A.2d 208 (Commonwealth Court of Pennsylvania, 2010)
Eastern Electric Corp. v. Shoemaker Construction Co.
657 F. Supp. 2d 545 (E.D. Pennsylvania, 2009)
Alpart v. General Land Partners, Inc.
574 F. Supp. 2d 491 (E.D. Pennsylvania, 2008)
Lucciotti v. American Management Advisors Inc.
2 Pa. D. & C.5th 489 (Bucks County Court of Common Pleas, 2007)
Widmer Engineering, Inc. v. Dufalla
837 A.2d 459 (Superior Court of Pennsylvania, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
504 A.2d 1343, 351 Pa. Super. 32, 1985 Pa. Super. LEXIS 10488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oak-ridge-construction-co-v-tolley-pa-1985.