O. C. Kinney, Inc. v. Paul Hardeman, Inc.

379 P.2d 628, 151 Colo. 571, 1963 Colo. LEXIS 511
CourtSupreme Court of Colorado
DecidedMarch 11, 1963
Docket19969
StatusPublished
Cited by22 cases

This text of 379 P.2d 628 (O. C. Kinney, Inc. v. Paul Hardeman, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O. C. Kinney, Inc. v. Paul Hardeman, Inc., 379 P.2d 628, 151 Colo. 571, 1963 Colo. LEXIS 511 (Colo. 1963).

Opinion

Opinion by

Mr. Justice Sutton.

• We- shall refer to plaintiff in error as plaintiff - as it appeared in the trial .court, and to defendant in error as defendant.

Plaintiff seeks reversal of an .order of the district court granting defendant a summary judgment.

The entire dispute revolves around the question of whether defendant was required to accept plaintiff’s bid for certain sheet metal and related work for the construction of a missile site at Lowry Air Force Base near Denver.

Plaintiff sued on an alleged contract, its complaint stating in pertinent part that “ * * * Defendant requested the Plaintiff among others to bid * * * ” and “That the Defendant represented to the Plaintiff and all other bidders that said contract for such work would be awarded to the lowest bidder for such.” Plaintiff then alleges it acted in reliance on the above representation, expended time and money preparing its bid which was the lowest one submitted, but that defendant thereafter entered into a contract for the work with a higher bidder, $75,000.00 was sought in damages, together with costs.

Defendant’s answer denied the material allegations of the complaint and moved its dismissal on the ground that it failed to “state facts sufficient to constitute a claim * * * upon which relief can be granted.”

Thereafter three depositions were taken, two for defendant and one for plaintiff. The first one was of Everett L. Krieger, plaintiff’s general manager at the time in question and the man who prepared plaintiff’s *573 bid and negotiated with defendant. The second was of Stevens Park Kinney, Secretary of plaintiff corporation. The third was for plaintiff of Erwin Solloway, defendant’s bid estimator, who dealt with Krieger. These depositions can be summarized as disclosing the following undisputed facts:

(1) Defendant did not seek bids from plaintiff, Krieger stating that he heard of the proposed work elsewhere. He thereupon secured bidding data from the federal government and first submitted an erroneous telephone bid on one site to Solloway. This bid was later corrected, reduced to writing and mailed to defendant. Defendant did not reply thereto. It appears that plaintiff’s final bid was for $262,809.00.

(2) That defendant, before accepting a bid on this job, was awarded a contract for a second nearby missile site.

(3) That several other subcontractors submitted bids, among them Sam Fox Sheet Metal Company, which submitted a bid of $299,451.00 on one site and $549,000.00 for the two sites. Defendant accepted the two site bid.

(4) That no direct representations of any kind were ever made by defendant to plaintiff as to how the defendant would determine the successful bidder.

(5) That plaintiff hoped to gross “About $50,000.00” on the job if its bid were accepted.

(6) That plaintiff was a relatively new company in this field and never had had a job this large; that it was quite certain it could procure a performance bond but had not tried to do so in connection with this job because it was waiting to see if it would be awarded the contract.

It appears that after suit was begun defendant procured an affidavit of Glenn E. Loveless, plaintiff’s successor manager to Krieger, by which it was shown that after plaintiff’s bid was submitted it merely “hoped that the prime contractor would wish to divide the work up between sheet metal companies, and at the conference *574 (with one of defendant’s representatives at a later date) I requested that the subcontract for the first site be awarded to O. C. Kinney, Inc. This possibility was discussed. The representative of Paul Hardeman, Inc. made no representations or promises that the contract would be awarded to O. C. Kinney, Inc. I knew * * * (defendant and its associates) would consider all bids on both projects.”

Armed with the affidavit and the three depositions defendant sought relief by “MOTION FOR SUMMARY JUDGMENT” which was granted and judgment entered thereon.

Plaintiff seeks reversal urging in substance that it was error to grant the summary judgment because:

(1) No specific agreement had to be entered into under these facts before defendant would be bound;

(2) That a representation had been made to a class of subcontractors, including plaintiff, which would bind defendant; and,

(3) That the custom in the trade was to accept the lowest bid and since plaintiff’s was the lowest a contract was created by making its bid.

Under the facts disclosed here we conclude that the trial court was eminently correct in its decision. R.C.P. Rule 56 permits a motion for a summary judgment with or without supporting affidavits. And “judgment sought rendered forthwith if the pleadings, depositions, and admissions on file, together with the affidavits, if any, show there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Here no counter affidavit was filed to indicate any genuine issue as to a material fact, and the affidavit and depositions clearly disclosed that plaintiff’s complaint could not be sustained; thus as a matter of law the summary judgment was proper. Parrish v. DeRemer, 117 Colo. 256, 187 P. (2d) 597 (1947); Carter v. Carter, 148 Colo. 495, 366 P. (2d) 586 (1961).

*575 The purpose of a motion for summary judgment is to save litigants the expense and time connected with a trial when, as a matter of law based upon admitted facts, one of the parties could not prevail.

In the instant case the record discloses no meeting of the minds to create an express contract nor can one be implied from proof of custom and usage or from the circumstances shown here. See Milone and Tucci, Inc. v. Bona Fide Builders, Inc., 49 Wash. 2d 363, 301 P. (2d) 759 (1956). A bid is normally considered only as an offer until such time as it is accepted. United States of America v. Farina, et al., 153 F. Supp. 819 (U.S.D.C.N.J. 1957). (Action dismissed under Rule 12 (b) (6) of the Federal Rules of Civil Procedure, 28 U.S.C.A. §2072). Mere notification or knowledge that one’s bid is low cannot of itself create a contract between the parties.

Even if defendant’s uncommunicated desire to have bids submitted could be relied upon by plaintiff, it is obvious that, at best, it was merely an invitation to bid and not an operative offer. Plaintiff’s bid itself constituted the offer and it would take defendant’s acceptance to complete a contract. United States v. Sabin Metal Corporation, 151 F. Supp. 683 at 687, (U.S.D.C., S.D.N.Y.) (1957).

Plaintiff’s assertion that here there was no provision in the specifications reserving the right to defendant to reject any and all bids makes no difference, for it has been held that an owner is under no obligation to accept any bid. Bromley v. McHugh, 122 Wash. 361, 210 Pac. 809 (1922).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Black Education Network, Inc. v. AT&T Broadband, LLC
154 F. App'x 33 (Tenth Circuit, 2005)
Hoon v. Pate Const. Co., Inc.
607 So. 2d 423 (District Court of Appeal of Florida, 1992)
Churchey v. Adolph Coors Co.
759 P.2d 1336 (Supreme Court of Colorado, 1988)
Kaiser Foundation Health Plan of Colorado v. Sharp
741 P.2d 714 (Supreme Court of Colorado, 1987)
Pueblo W. Metro. D. v. Se Colo. Water Con.
689 P.2d 594 (Supreme Court of Colorado, 1984)
Commercial Industrial Construction, Inc. v. Anderson
683 P.2d 378 (Colorado Court of Appeals, 1984)
Kuehn v. Kuehn
642 P.2d 524 (Colorado Court of Appeals, 1981)
Carriger v. Ballenger
628 P.2d 1106 (Montana Supreme Court, 1981)
Ginter v. Palmer & Co.
585 P.2d 583 (Supreme Court of Colorado, 1978)
People in Interest of FLG
563 P.2d 379 (Colorado Court of Appeals, 1977)
Valenzuela v. MERCY HOSPITAL, DENVER, COLORADO
521 P.2d 1287 (Colorado Court of Appeals, 1974)
Abrahamsen v. Mountain States Telephone & Telegraph Co.
494 P.2d 1287 (Supreme Court of Colorado, 1972)
Fort Collins Motor Homes, Inc. v. City of Fort Collins
496 P.2d 1074 (Colorado Court of Appeals, 1972)
Estate of Hall v. FATHER FLANAGAN'S BOYS'HOME
491 P.2d 614 (Colorado Court of Appeals, 1971)
Durnford v. City of Thornton
483 P.2d 977 (Colorado Court of Appeals, 1971)
MJ McGough Company v. Jane Lamb Memorial Hospital
302 F. Supp. 482 (S.D. Iowa, 1969)
Premier Electrical Construction Co. v. Miller-Davis Co.
291 F. Supp. 295 (N.D. Illinois, 1968)
Terrell v. Walter E. Heller & Company
439 P.2d 989 (Supreme Court of Colorado, 1968)
CH Leavell and Co. v. Grafe and Associates, Inc.
414 P.2d 873 (Idaho Supreme Court, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
379 P.2d 628, 151 Colo. 571, 1963 Colo. LEXIS 511, Counsel Stack Legal Research, https://law.counselstack.com/opinion/o-c-kinney-inc-v-paul-hardeman-inc-colo-1963.