Nussbaum v. Kimberly Timbers, Ltd.

856 A.2d 364, 271 Conn. 65, 2004 Conn. LEXIS 357
CourtSupreme Court of Connecticut
DecidedSeptember 14, 2004
DocketSC 17070
StatusPublished
Cited by28 cases

This text of 856 A.2d 364 (Nussbaum v. Kimberly Timbers, Ltd.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nussbaum v. Kimberly Timbers, Ltd., 856 A.2d 364, 271 Conn. 65, 2004 Conn. LEXIS 357 (Colo. 2004).

Opinion

Opinion

ZARELLA, J.

The plaintiffs, Martin Nussbaum and Kathleen Nussbaum, appeal from the judgment of the trial court denying their application for an order to stay arbitration proceedings instituted by the defendant contractor, Kimberly Timbers, Ltd. The defendant commenced arbitration following the plaintiffs’ failure to pay the balance allegedly due on a contract between the parties for the construction of a new home in Greenwich. On appeal, the plaintiffs claim, first, that the issue of whether the contract is unenforceable because it is contrary to public policy is not an issue within the scope of the arbitration clause contained in the contract, to be decided initially by the arbitrator, and, second, that the trial court improperly determined that the contract and the arbitration clause are enforceable despite the defendant’s failure to comply with all of the provisions of General Statutes § 20-417d pertaining to new home construction contractors. We conclude that the trial court had jurisdiction to determine whether the arbitration clause is enforceable, that the arbitration clause is, in fact, enforceable, and, therefore, that the issue of whether the contract is unenforceable because it violated public policy was one for the arbitrator to decide in the first instance.

The following facts and procedural history guide our resolution of this appeal. In 1999, Public Acts 1999, No. 99-246, otherwise known as the New Home Construction Contractors Act (act),1 was enacted to regulate the activities of new home construction contractors. The act became effective on October 1,1999, and is codified [68]*68at General Statutes § 20-417a et seq. Prior to 1999, there was no requirement in Connecticut that a new home construction contractor be licensed. The defendant, an experienced contractor who had constructed nearly forty homes in the Greenwich area, obtained a license pursuant to the newly adopted statutory scheme on April 14, 2000.

The plaintiffs and the defendant entered into negotiations to construct a new home before the defendant obtained a license. At some point in the negotiations, a contract dated March 10, 2000, and a contract rider dated May, 2000, were drafted, but the parties did not execute and sign the contract and rider until May, 2000. The contract included an arbitration provision.

After the contract was fully performed, a dispute arose as to the remaining amount of money that the plaintiffs owed to the defendant. In accordance with the contract’s arbitration provision, the defendant filed a demand for arbitration with the American Arbitration Association seeking to recover the amount allegedly due, which consisted of the final 10 percent of the contract price. Thereafter, the plaintiffs filed an application for an order to stay the arbitration proceedings and an order to show cause on the ground that the defendant had failed to comply with § 20-417d2 and that [69]*69the contract, therefore, was void and unenforceable. The plaintiffs specifically alleged that the defendant had (1) held itself out as a new home contractor without a license while the parties were engaged in negotiations, and (2) failed to comply with the mandatory notice provisions of § 20-417d. In response, the defendant filed a motion to compel arbitration.

On January 13, 2003, the trial court held a hearing on the defendant’s motion to compel and the plaintiffs’ application to stay.3 Following the hearing, the court issued a ruling from the bench denying the plaintiffs’ [70]*70application to stay the arbitration proceedings and directed the parties to resume arbitration.4 Although the court found that the contract did not contain the notice provisions described in § 20-417d, it rejected the plaintiffs’ claim that the contract was automatically “void.” The court rendered judgment in accordance with its ruling.

The plaintiffs appealed from the judgment of the trial court to the Appellate Court, and we transferred the appeal to this court pursuant to General Statutes § 51-199 (c) and Practice Book § 65-1.5 During oral argument in this court, the panel questioned the parties in an effort to distinguish between the issue of the contract’s enforceability, which the parties had briefed, and the issue of whether the contract’s enforceability was an issue within the scope of the arbitration clause, to be decided by the arbitrator. Thereafter, the parties were ordered to file simultaneous supplemental briefs addressing the following question: “Is the issue of the enforceability of the contract under ...[§] 20-417a et seq. ... a question within the scope of the arbitration clause, to be decided in the first instance by the [arbitrator]?”

[71]*71We begin by noting that Connecticut has adopted a clear public policy in favor of arbitrating disputes. The policy is expressed in General Statutes § 52-408, which provides in relevant part: “An agreement in any written contract, or in a separate writing executed by the parties to any written contract, to settle by arbitration any controversy thereafter arising out of such contract, or out of the failure or refusal to perform the whole or any part thereof . . . shall be valid, irrevocable and enforceable, except when there exists sufficient cause at law or in equity for the avoidance of written contracts generally.” To enforce such agreements in cases in which there is no action pending between the parties and the parties’ contract contains an arbitration clause, General Statutes § 52-410 (a) further provides that “[a] party to a written agreement for arbitration claiming the neglect or refusal of another to proceed with an arbitration thereunder may make application to the superior court for the judicial district in which one of the parties resides ... for an order directing the parties to proceed with the arbitration in compliance with their agreement. . . .”

The plaintiffs claim that, because they alleged that the underlying contract is illegal, the court, rather than the arbitrator, had sole jurisdiction to decide whether there is a valid and enforceable agreement to arbitrate pursuant to § 52-408. The defendant responds that a distinction must be made between contracts that are “void” because they are not properly formed, and thus have no legal effect, and legally valid contracts that are “voidable” because they are subject to substantive defects that ar e not related to contract formation. The defendant argues that although a claim that a contract is void is a threshold determination for the court to decide, a claim that a contract is voidable is more properly submitted to an arbitrator. The defendant contends that the plaintiffs’ claim that the contract is illegal [72]*72because it does not comply with the notice requirements of § 20-417d pertains to the voidability of the contract and, thus, is a claim that should be decided by the arbitrator. The defendant nonetheless argues that the plaintiffs “waived the submission” of their claim regarding the illegality of the contract to the arbitrator when they submitted that claim to the court, and that the arbitrator now “is bound by the law of the case to follow [the trial court’s] ruling that the contract is not voidable.” We agree with the defendant that the arbitrator is required in the first instance to decide the issue of whether the contract is enforceable.

It is well established that “[arbitration is a creature of contract. ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chabad Lubavitch of Western & Southern New England, Inc. v. Shemtov
349 Conn. 695 (Supreme Court of Connecticut, 2024)
Ahmed v. Oak Management Corp.
Supreme Court of Connecticut, 2023
Green v. RXO Last Mile, Inc.
D. Connecticut, 2020
Norwalk Medical Group, P.C. v. Yee
199 Conn. App. 208 (Connecticut Appellate Court, 2020)
Benistar Employer Services Trust Co. v. Benincasa
207 A.3d 67 (Connecticut Appellate Court, 2019)
State v. Newton
194 A.3d 272 (Supreme Court of Connecticut, 2018)
Hinds v. Commissioner of Correction
Supreme Court of Connecticut, 2016
MSO, LLC v. DeSimone
Supreme Court of Connecticut, 2014
Girolametti v. Rizzo Corp.
Connecticut Appellate Court, 2014
Knox v. Smith
14 A.3d 495 (Connecticut Appellate Court, 2011)
Marulli v. Wood Frame Construction Co., LLC
5 A.3d 957 (Connecticut Appellate Court, 2010)
Méndez-Acevedo v. Nieves Rivera
179 P.R. Dec. 359 (Supreme Court of Puerto Rico, 2010)
Méndez Acevedo Y Otros v. Nieves Riveras
2010 TSPR 105 (Supreme Court of Puerto Rico, 2010)
Ungerland v. MORGAN STANLEY AND CO., INC.
35 A.3d 1095 (Connecticut Superior Court, 2010)
State v. Philip Morris, Inc.
959 A.2d 997 (Supreme Court of Connecticut, 2008)
Gosselin v. Gosselin
955 A.2d 60 (Connecticut Appellate Court, 2008)
MBNA America Bank, N.A. v. Boata
926 A.2d 1035 (Supreme Court of Connecticut, 2007)
C. R. Klewin Northeast, LLC v. City of Bridgeport
919 A.2d 1002 (Supreme Court of Connecticut, 2007)
State v. Phillip Morris, Inc.
905 A.2d 42 (Supreme Court of Connecticut, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
856 A.2d 364, 271 Conn. 65, 2004 Conn. LEXIS 357, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nussbaum-v-kimberly-timbers-ltd-conn-2004.