Nova Sign Group v. Bunting Graphics, Inc.

CourtSuperior Court of Pennsylvania
DecidedApril 25, 2018
Docket3202 EDA 2017
StatusUnpublished

This text of Nova Sign Group v. Bunting Graphics, Inc. (Nova Sign Group v. Bunting Graphics, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nova Sign Group v. Bunting Graphics, Inc., (Pa. Ct. App. 2018).

Opinion

J-A05002-18 & J-A05003-18

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

NOVA SIGN GROUP : IN THE SUPERIOR COURT OF : PENNSYLVANIA Appellants : : : v. : : : BUNTING GRAPHICS, INC. : No. 3202 EDA 2017 v. : : : TURNER CONSTRUCTION COMPANY :

Appeal from the Order Entered August 25, 2017 In the Court of Common Pleas of Philadelphia County Civil Division at No(s): 02052 October Term, 2015

NOVA SIGN GROUP : IN THE SUPERIOR COURT OF : PENNSYLVANIA : v. : : : BUNTING GRAPHICS, INC. : : Appellants : No. 3287 EDA 2017 : : : : v. : : : TURNER CONSTRUCTION COMPANY :

Appeal from the Order Entered August 25, 2017 In the Court of Common Pleas of Philadelphia County Civil Division at No(s): 02052 October Term, 2015

BEFORE: DUBOW, J., MURRAY, J., and STEVENS*, P.J.E.

____________________________________ * Former Justice specially assigned to the Superior Court. J-A05002-18 & J-A05003-18

MEMORANDUM BY DUBOW, J.: FILED APRIL 25, 2018

In these consolidated appeals,1 Nova Sign Group (“Nova”) appeals at

No. 3202 EDA 2017 from the August 25, 2017 Order granting Bunting

Graphic, Inc’s (“Bunting”) Motion for Summary Judgment. Bunting appeals

at No 3287 EDA 2017 from the same August 25, 2017 Order granting Turner

Construction Company’s (“Turner”) Motion for Summary Judgment. After

careful review, we affirm the Order appealed at No 3202 EDA 2017, and

dismiss Bunting’s appeal at No. 3287 EDA 2017 as moot.

The facts and procedural history are as follows. Turner entered into a

construction management contract with Eagles Stadium Operator, LLC

(“Owner”), the owner of Lincoln Financial Field in Philadephia. On April 16,

2014, Turner entered into a $1,289,128.00 subcontract with Bunting, a

contractor engaged in the manufacture and installation of architectural

signage and ornamental metals. Pursuant to the subcontract, Bunting was

to provide the signage and wayfinding2 for Lincoln Financial Field.

On May 20, 2014, Bunting entered into a $275,000.00 sub-subcontract

with Nova, whereby Nova agreed to install the signage that Bunting

fabricated and delivered to the site.

____________________________________________

1 We have consolidated these appeals sua sponte.

2 Wayfinding includes information systems that guide people through a physical environment.

-2- J-A05002-18 & J-A05003-18

The Sub-Subcontract

The sub-subcontract between Nova and Bunting contained the

following relevant provisions detailing the procedure by which the parties

would handle disputes between them. In particular, the parties agreed that:

(1) if Nova had a claim against the Owner, Nova would pursue that in claim

in the Court of Common Pleas; (2) if Nova had a claim against Bunting, Nova

would pursue that claim in arbitration; and (3) if Bunting believed that

Nova’s claim against it was actually the responsibility of the Owner, Nova

would stay the arbitration until Nova resolved its claim against the Owner:

[11(b)] In case of any dispute between [Bunting] and [Nova], in any way relating to or arising from any act or omission of the Owner or involving the Contract Documents[3], [Nova] agrees to be bound to [Bunting] to the same extent that [Bunting] is bound to Owner, by the terms of the Contract Documents, and by any and all preliminary and final decisions or determinations made thereunder by the party, board or court so authorized in the Contract Documents or by law, whether or not [Nova] is a party to such proceedings. In case of such dispute, [Nova] will comply with all provisions of the Contract Documents allowing a reasonable time for [Bunting] to analyze and forward to the Owner any required communications or documentation. [Bunting] will, at its option, (1) present to the Owner, in [Bunting’s] name, or (2) authorize [Nova] to present to the Owner, in [Bunting’s] name, all of [Nova’s] claims and answer the Owner’s claims involving [Nova’s] work, whenever, [Bunting] is permitted to do so by the terms of the contract documents. . .

[11(c)] Any controversy between [Bunting] and [Nova] not relating to or arising from any action or inaction of the Owner and not involving the Contract Documents shall be decided by arbitration in accordance with the Construction Industry ____________________________________________

-3- J-A05002-18 & J-A05003-18

Arbitration Rule of the American Arbitration Association…If [Bunting] notifies [Nova] that [Bunting] contends any arbitration brought under this Article 11.c. involves a controversy within the scope of Article 11.b., the arbitration shall be stayed until the procedures under Article 11.b. are completed and it is determined thereunder that the controversy does not fall within Article 11.b. [3]The term “Contract Documents” in the sub-subcontract refers to the sub-contract between Bunting and Turner. See Sub- Subcontract, 5/20/14, at 1, Exhibit A.

Sub-Subcontract, 5/20/14, Article 11(b)-(c) (emphasis added).

The Dispute

The dispute that led to the instant matter involves 47 invoices that

Nova provided to Bunting and that Bunting refused to pay. As a result, on

November 26, 2014, Nova submitted a demand for arbitration. Pursuant to

Article 11(c) of the sub-subcontract, Bunting notified Nova by letter of its

belief that “[t]he invoices are for alleged acts that have arisen as a result of

the [O]wner and the contract documents.” Bunting’s Mot. for Sum. J.

Exhibit G, 11/28/14 Bunting Letter. Bunting, thus, requested that Nova stay

the arbitration proceedings until it could be determined whether Nova’s

claims were caused by an act or omission of Owner as provided in Article

-4- J-A05002-18 & J-A05003-18

11(c). Id. On December 3, 2014, Nova denied Bunting’s request to stay

the arbitration by letter.4 Id. Exhibit H, 12/3/14 Nova Letter.

The parties proceeded to arbitration over the non-payment of all 47

Nova invoices. Following hearings, the arbitrator issued a decision on

September 22, 2015, which awarded Nova payment for 35 of the 47

disputed invoices in the amount of $187,421.99. The arbitrator did not issue

a decision on 12 of the invoices because he determined that they involved

the Owner, fell within Article 11(b) of the sub-subcontract and, “as such,

those claims are not arbitrable.” Id. Exhibit F, 9/22/15 Arbitration Award.

The arbitrator further stated that, “[p]er agreement of the parties [Nova]

has reserved its rights to present those non-arbitrable claims in a different

forum.” Id.

On October 20, 2015, Nova filed a Complaint against Bunting raising

claims of Breach of Contract and Unjust Enrichment arising from Bunting’s

refusal to pay the 12 outstanding Nova invoices. On March 3, 2016, Bunting

filed an Answer with New Matter. Nova filed a Reply to Bunting’s New Matter

on March 15, 2016.

On November 22, 2016, Bunting filed a Joinder Complaint against

Turner asserting claims for Contribution/Indemnification, Breach of Contract, ____________________________________________

4 In particular, Nova stated that it “respectfully denies your request and intends to proceed with administration of its Demand for Arbitration in accordance with the applicable rules of the AAA.” 12/3/14 Nova Letter.

-5- J-A05002-18 & J-A05003-18

and Quantum Meruit. Turner filed Preliminary Objections to the Joinder

Complaint on December 22, 2016, to which Bunting filed an Answer on

January 11, 2017. On January 24, 2017, the court sustained Turner’s

Preliminary Objections in part, and dismissed Bunting’s Breach of Contract

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Summers v. CERTAINTEED CORP.
997 A.2d 1152 (Supreme Court of Pennsylvania, 2010)
Stack v. Karavan Trailers, Inc.
864 A.2d 551 (Superior Court of Pennsylvania, 2004)
Eichman v. McKeon
824 A.2d 305 (Superior Court of Pennsylvania, 2003)
Ragnar Benson, Inc. v. HEMPFIELD TOWNSHIP MUNICIPAL AUTHORITY
916 A.2d 1183 (Superior Court of Pennsylvania, 2007)
Office of Disciplinary Counsel v. Kiesewetter
889 A.2d 47 (Supreme Court of Pennsylvania, 2005)
Mariner Chestnut Partners, L.P. Ex Rel. Lamm v. Lenfest
152 A.3d 265 (Superior Court of Pennsylvania, 2016)
Century Indemnity Co. v. OneBeacon Insurance Co.
173 A.3d 784 (Superior Court of Pennsylvania, 2017)
Weissberger v. Myers
90 A.3d 730 (Superior Court of Pennsylvania, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Nova Sign Group v. Bunting Graphics, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/nova-sign-group-v-bunting-graphics-inc-pasuperct-2018.