Ragnar Benson, Inc. v. HEMPFIELD TOWNSHIP MUNICIPAL AUTHORITY

916 A.2d 1183, 2007 Pa. Super. 28, 2007 Pa. Super. LEXIS 164
CourtSuperior Court of Pennsylvania
DecidedJanuary 30, 2007
StatusPublished
Cited by52 cases

This text of 916 A.2d 1183 (Ragnar Benson, Inc. v. HEMPFIELD TOWNSHIP MUNICIPAL AUTHORITY) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ragnar Benson, Inc. v. HEMPFIELD TOWNSHIP MUNICIPAL AUTHORITY, 916 A.2d 1183, 2007 Pa. Super. 28, 2007 Pa. Super. LEXIS 164 (Pa. Ct. App. 2007).

Opinion

OPINION BY

JOHNSON, J.:

¶ 1 Kirby Electric, Inc. (Kirby) appeals from an order granting the Hempfield Township Municipal Authority’s (the Authority) motion to enforce a settlement agreement. Kirby contends that the trial court committed legal error when it determined that the parties’ agreement was a settlement agreement and refused to admit documents under the parol evidence rule. Additionally, Kirby asserts that the trial court erred in finding that the settlement amount was established, paid, and received. We' find no merit in any of *1185 Kirby’s contentions. Accordingly, we affirm the trial court’s order.

¶ 2 This case arises out of two separate but subsequently consolidated civil actions filed in the Court of Common Pleas of Westmoreland County. Both cases arise from contract disputes that occurred during the expansion and renovation of the New Stanton Water Pollution Control Plant (the Project), which was owned by the Authority. Under separate written agreements, Kirby contracted with the Authority to perform the Project’s electrical construction, while Ragnar Benson, Inc. (Ragnar) contracted with the Authority to perform the Project’s general construction.

¶ 3 Following a disagreement between the contractors and the Authority that is not relevant for purposes of this appeal, Ragnar filed a complaint against the Authority. In its complaint, Ragnar asserted claims of breach of contract and sought reimbursement for extra costs that were allegedly incurred as a result of the Authority’s failure to properly design a portion of the Project. In turn, the Authority asserted a counterclaim against Ragnar for breach of contract and liquidated damages for an amount exceeding $1,500,000.00.

¶ 4 On May 24, 2002, Kirby commenced a civil action against the Authority and Ragnar, seeking to hold both defendants liable in breach of contract for a total of $496,619.00. In its complaint, Kirby alleged that: the Authority owed it $20,000.00 for its complete performance under the contract (Count I); Kirby was entitled to damages from the Authority for disruption, delay and acceleration caused by Ragnar (Count II); and Kirby was entitled to damages from Ragnar for disruption, delay and acceleration caused by Ragnar (Count III). Kirby’s Count III breach of contract claim against Ragnar was premised on the theory that it was a third-party beneficiary of the general construction contract between Ragnar and the Authority. In its Answer and New Matter, Ragnar joined the Authority as a third-party defendant and sought contribution and/or indemnity under Pa.R.Civ.P. 2252(d). Likewise, in its Answer and New Matter, the Authority joined Ragnar as a third-party defendant and sought contribution and/or indemnity under Pa.R.Civ.P. 2252(d). In addition, the Authority asserted a counterclaim against Kirby for attorney’s fees and defense costs pursuant to their construction contract. On June 21, 2002, the trial court issued an order that consolidated Ragnar’s claim against the Authority with Kirby’s claims against the Authority and Ragnar.

¶ 5 In October 2003, Kirby and the Authority executed a Settlement and Release Agreement (Settlement Agreement) and agreed to settle their claims against one another, with the exception of Kirby’s Count I, $20,000.00 claim against the Authority for completed contractual performance. In the Settlement Agreement, Kirby and the Authority agreed that: (1) Kirby would continue its litigation against Ragnar, (2) the Authority would remain a party to the suit, (3) the Authority would pay Kirby according to an inverse-ratio formula that was based on the amount of settlement or final judgment in the litigation between Kirby and Ragnar, and (4) each party would be permitted to enter unilaterally into a settlement with Ragnar. Specifically, under paragraph 2 of the Settlement Agreement, a declining scale set forth the Settlement Amount that the Authority would be obligated to pay Kirby, based upon the amount that Kirby recovered from Ragnar:

a) Should Kirby’s actual recovery from Ragnar be zero, the settlement amount shall be $100,000.00.;
b) Should Kirby’s actual recovery from Ragnar fall between zero and *1186 $300,000.00, the settlement amount shall be reduced by thirty-three cents for every dollar of actual recovery;
c) Should Kirby’s actual recovery from Ragnar exceed the sum of $800,000.00, the settlement amount shall be zero.

Settlement Agreement, 8/14/03, at 2 ¶ 2. Moreover, paragraph 11 of the Settlement Agreement, which relates to the parties’ ability to settle unilaterally with Ragnar, provides as follows:

a) if the Authority alone settles with Ragnar, the Authority shall pay Kirby the sum of $100,000.00 simultaneously with the execution of any release between the Authority and Ragnar;
b) if Kirby alone settles with Ragnar for less than $200,000.00, the Authority owes Kirby nothing;
c) if Kirby settles with Ragnor for a sum in excess of $200,000.00, the Settlement Amount due and payable by the Authority shall be calculated in accordance with the declining scale
d) if there is a “global settlement agreement,” where all parties release each other from all claims that have been or should be asserted ..., the Settlement Amount shall be calculated in accordance with the global settlement agreement.

Settlement Agreement, 8/14/03, at 9 ¶ 11.

¶ 6 Shortly after the execution of the Settlement Agreement, on October 23, 2003, Kirby filed a motion for summary judgment against Ragnar on the issues of liability and causation. In response, Rag-nar filed a cross-motion for summary judgment on Kirby’s claim against it, arguing, among other things, that Kirby was not an intended third-party beneficiary of the general construction contract between Ragnar and the Authority. On December 9, 2003, the Authority settled with Ragnar, and pursuant to paragraph 11(a) of the Settlement Agreement, simultaneously paid Kirby $100,000.00. On December 31, 2003, the trial court granted Ragnar’s cross-motion for summary judgment against Kirby on the. ground that Kirby was not an intended third-party beneficiary of the general construction contract, and thus, had no legal basis to sue Ragnar for breach of contract. Because the trial court entered summary judgment in favor of Ragnar, which resulted in Kirby obtaining a “zero” recovery from Ragnar, the Authority did not make any additional payment to Kirby under paragraph 2 of the Settlement Agreement. See Settlement Agreement, 8/14/03, at 2 ¶ 2(a).

¶ 7 Kirby then filed an “Emergency Motion for Pretrial Conference,” alleging that the Settlement Agreement could not be construed as a conclusive resolution or final disposition of the case. Anticipating that Kirby would make an attempt to acquire more money from the Authority under the Settlement Agreement, the Authority filed a Motion to Enforce Settlement Agreement. By way of answer and opposition, Kirby asserted that the agreement between it and the Authority was not in fact a settlement agreement, but instead, was an unenforceable “Mary Carter” agreement. See Hammel v. Christian, 416 Pa.Super. 78, 610 A.2d 979

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Patel, J. v. Patel, A.
Superior Court of Pennsylvania, 2026
Liberty Property v. Kendal Heaton Assoc.
2026 Pa. Super. 37 (Superior Court of Pennsylvania, 2026)
Com. v. Cannon, T.
Superior Court of Pennsylvania, 2024
Tomasko, R. v. Citrin, Cooperman and Company
Superior Court of Pennsylvania, 2024
In Re: J.R., Appeal of: M.R.
Superior Court of Pennsylvania, 2024
Kahlon, S. v. Lehigh Valley Health Net.
Superior Court of Pennsylvania, 2023
Petroci, J. v. Dumond Chemicals
Superior Court of Pennsylvania, 2023
In Re: Estate of Dembosky, W., Dec.
Superior Court of Pennsylvania, 2023
Bass Pro v. Harrisburg Mall
Superior Court of Pennsylvania, 2023
O'Malley, J. v. Conway, J.
Superior Court of Pennsylvania, 2022
LG Finacial Consultants v. Lawyers Funding Group
Superior Court of Pennsylvania, 2022
Kaplan, A. v. Weinstein Appraisal
Superior Court of Pennsylvania, 2022
Real Est. Mangmt. Adv. v. U.S. Liability Ins. Co.
Superior Court of Pennsylvania, 2022
9795 Perry Highway v. Bernard, W.
2022 Pa. Super. 52 (Superior Court of Pennsylvania, 2022)
Harley, P. v. Healthspark Foundation
2021 Pa. Super. 205 (Superior Court of Pennsylvania, 2021)
Royer, R. v. UNUM Life Insurance
Superior Court of Pennsylvania, 2021
Peruto, A. v. Catalyst Outdoor Adv.
Superior Court of Pennsylvania, 2021
Oehrle, A. v. Goldsmith, M.
Superior Court of Pennsylvania, 2020
Santander Bank, N.A. v. Express Sign Outlet
Superior Court of Pennsylvania, 2020

Cite This Page — Counsel Stack

Bluebook (online)
916 A.2d 1183, 2007 Pa. Super. 28, 2007 Pa. Super. LEXIS 164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ragnar-benson-inc-v-hempfield-township-municipal-authority-pasuperct-2007.