Norwich Community Development Corp. v. Arbucci, No. 92201 (Jan. 6, 1993)

1993 Conn. Super. Ct. 731
CourtConnecticut Superior Court
DecidedJanuary 6, 1993
DocketNo. 92201
StatusUnpublished

This text of 1993 Conn. Super. Ct. 731 (Norwich Community Development Corp. v. Arbucci, No. 92201 (Jan. 6, 1993)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Norwich Community Development Corp. v. Arbucci, No. 92201 (Jan. 6, 1993), 1993 Conn. Super. Ct. 731 (Colo. Ct. App. 1993).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION CT Page 732 The plaintiff, the Norwich Community Development Corporation, Inc. (NCDC or plaintiff) brought this action against the defendant Nicholas Arbucci (Arbucci or the defendant) for breach of a contract to reconvey a parcel of land on which is located a railroad depot. The defendant City of Norwich was named because it claimed to have an interest of record in the premises by virtue of recorded tax liens for unpaid real estate taxes. The Farmers and Mechanics Bank was admitted as a party defendant because it too claimed an interest in the premises by virtue of judgment liens it had filed against Arbucci. Although both the city and the bank were represented by counsel, they took no part in the trial of the case for reasons that will be readily apparent.

NCDC alleged in its `revised' complaint that it sold to Arbucci on December 30, 1986, real estate in Norwich known as the "Railroad Depot" for a price of $61,000. It further alleged that the transaction was subject to a `land use agreement' which required Arbucci essentially to rehabilitate the depot and to substantially complete the rehabilitation and have the premises ready for tenants within 18 months, and if not, then NCDC would have a right to demand a reconveyance for a price of $56,000. NCDC claims Arbucci did not perform the contract and this suit ensued for a reconveyance of the premises, after it tendered the $56,000 and Arbucci refused to reconvey the premises.

Arbucci filed an answer denying the material allegations of the plaintiff's revised complaint together with a two count counterclaim; the first count alleging that the plaintiff acted in bad faith by impeding portions of the rehabilitation project, and the second count for unjust enrichment in the event a reconveyance of the premises is decreed. The plaintiff denied the material allegations of the counterclaim.

I. CT Page 733

The court, after hearing from eleven witnesses and receiving into evidence a total of eighty exhibits from both parties, finds the following facts. The plaintiff, NCDC, is a nonstock corporation formed to foster development in the City of Norwich and to participate in the rehabilitation of downtown Norwich. NCDC purchased the Providence and Worcester railroad depot and adjacent land for the sum of $250,000, which sum was contributed in part by the city, in part by the Norwich Parking Commission, and in part from its own sources.

NCDC sought developers to rehabilitate the railroad depot and selected the defendant. Thereupon, the parties entered in a real estate contract, Plaintiff's Exhibit B,1 and pursuant to the contract, the plaintiff delivered a warranty deed to the depot together with some land around it to the defendant and obtained a parking use agreement so that the premises would have additional parking, for a total price of $61,000. The issues critical to this case stem from the land use agreement, Plaintiff's Exhibit C, which was the central part of the transaction.

The land use agreement provides in pertinent and relevant part:

"2. . . (c) within eighteen (18) months from December 31, 1986, Developer (Arbucci) will have substantially completed all rehabilitation and premises will be ready for tenants. . . .

3. In the event of Developer's failure to satisfy any of the conditions subsequent as described in paragraph 2 above, Owner [NCDC] may repurchase the premises for a purchase (sic) which shall be the lesser of $56,000, or the then fair market value of the premises and improvements. In the event of a default or breach of the conditions provided in paragraph 2 by Developer and the failure by Owner to demand a reconveyance by December 31, 1989, CT Page 734 then the right of Owner for reconveyance hereto shall terminate. . . .

5. In the event of a default by Developer of any of the conditions set forth in paragraph 2 above, and the failure of Developer to reconvey said premises pursuant to the terms of paragraph 3 above, Owner shall have the right to commence an action in equity seeking a reconveyance and if Owner secures a final judgment ordering a reconveyance of said premises, Owner shall be entitled to reasonable attorney's fees incurred in bringing said action."

II.
Both the real estate contract and the land use agreement were negotiated by the parties and each were represented by counsel throughout. Common sense ordinary meanings must be given to the words and phrases used in the agreement. In this case, the court concludes that the land use agreement was really a specialized form of building contract. The court notes that the defendant was required to perform by June 30, 1988, but experienced difficulties, and the plaintiff granted him a six-month extension. After a meeting in December 1988, attended by defendant's counsel, the plaintiff's representatives informed the defendant that he was in breach and requested that the defendant advise them of what work he planned to do to complete the renovation and in what time frame. When neither the defendant or his attorney responded to the request for this information, this lawsuit ensued.

The building, when purchased by the defendant, was dilapidated, indeed a blight, and needed a considerable amount of reconstruction to both its exterior and interior. The defendant had also obtained a "facade grant" which obligated him to do the exterior brickwork and windows in compliance with certain plans and specifications which were prepared by an architect and approved by the plaintiff and the Norwich Office of Economic Development. See Plaintiff's CT Page 735 Exhibit R.

The plaintiff's expert witness, Gordon Hyde, a licensed architect, inspected the building on November 1, 1990 and May 5, 1992. He compared the condition of the building with the construction plans. He found that on the north face, none of the window wood sash was completed, that there were defects in the window glazing, that some window arches were not in conformity with the plans and that many of the windows were not properly installed on the east face. He also found that the building was not properly secured and that the principal access door was not installed. On the south side, he found that the brick arches were not reconstructed, that "double hung" windows were not installed as required and that many windows needed replacement or repairs. He opined that on the south side virtually all of the work called for still needed to be done to comply with the facade plans.

On the westerly side, he found that with respect to the extension, it needed to be cleaned, scraped and repainted to match, and that none of the required work was done.

Hyde concluded that the exterior work was not substantially completed.

With respect to the interior, he found it generally unfinished. There was no provision for the handicapped lift, and although there was some electrical wiring, ductwork and plumbing installed, none was completed. No toilets or sinks, associated rough plumbing, or other amenities were installed in the restrooms called for in the plans. He also found that the stairs installed did not comply with the code, and part of the ceiling and sheetrocking was incomplete. He noted that the sprinkler system required approval by the fire marshal and no such approval was obtained. He concluded that, in his opinion, the work was not substantially completed, and that the premises were not ready for tenants. He further opined that with a substantial crew of good craftsmen, it would take several months to complete the job in accord with the plan.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Collins v. Sears, Roebuck & Co.
321 A.2d 444 (Supreme Court of Connecticut, 1973)
New Haven Savings Bank v. West Haven Sound Development
459 A.2d 999 (Supreme Court of Connecticut, 1983)
Vines v. Orchard Hills, Inc.
435 A.2d 1022 (Supreme Court of Connecticut, 1980)
Vincenzi v. Cerro
442 A.2d 1352 (Supreme Court of Connecticut, 1982)
Kakalik v. Bernardo
439 A.2d 1016 (Supreme Court of Connecticut, 1981)
Robert Lawrence Associates, Inc. v. Del Vecchio
420 A.2d 1142 (Supreme Court of Connecticut, 1979)
Allen v. Nissley
440 A.2d 231 (Supreme Court of Connecticut, 1981)
Appliances, Inc. v. Yost
443 A.2d 486 (Supreme Court of Connecticut, 1982)
Nor'easter Group, Inc. v. Colossale Concrete, Inc.
542 A.2d 692 (Supreme Court of Connecticut, 1988)
Natural Harmony, Inc. v. Normand
558 A.2d 231 (Supreme Court of Connecticut, 1989)
Eichman v. J & J Building Co.
582 A.2d 182 (Supreme Court of Connecticut, 1990)
Argentinis v. Gould
592 A.2d 378 (Supreme Court of Connecticut, 1991)
Nann v. Pignatelli
485 A.2d 922 (Connecticut Appellate Court, 1984)
Midway Green Corp. v. Board of Tax Review
512 A.2d 984 (Connecticut Appellate Court, 1986)
Sink v. Meadow Wood Country Estates, Inc.
559 A.2d 725 (Connecticut Appellate Court, 1989)
Argentinis v. Gould
579 A.2d 1078 (Connecticut Appellate Court, 1990)
Miller v. Bourgoin
613 A.2d 292 (Connecticut Appellate Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
1993 Conn. Super. Ct. 731, Counsel Stack Legal Research, https://law.counselstack.com/opinion/norwich-community-development-corp-v-arbucci-no-92201-jan-6-1993-connsuperct-1993.