Northwest Airlines, Inc. v. Federal Aviation Administration, Memphis-Shelby County Airport Authority, Intervenor

14 F.3d 64, 304 U.S. App. D.C. 302, 1994 U.S. App. LEXIS 1731
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 4, 1994
Docket92-1245
StatusPublished
Cited by19 cases

This text of 14 F.3d 64 (Northwest Airlines, Inc. v. Federal Aviation Administration, Memphis-Shelby County Airport Authority, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwest Airlines, Inc. v. Federal Aviation Administration, Memphis-Shelby County Airport Authority, Intervenor, 14 F.3d 64, 304 U.S. App. D.C. 302, 1994 U.S. App. LEXIS 1731 (D.C. Cir. 1994).

Opinions

Opinion for the Court filed by Circuit Judge SENTELLE.

Concurring opinion filed by Circuit Judge STEPHEN F. WILLIAMS.

SENTELLE, Circuit Judge:

Petitioner, Northwest Airlines, Inc. (“Northwest”), seeks review of a decision of the Federal Aviation Administration (“FAA”) approving Memphis-Shelby County Airport Authority’s application to impose a $3.00 Passenger Facility Charge (“PFC”) on passengers enplaned at Memphis International Airport. Northwest argues the FAA’s failure to consider the economic and competitive effects of its decision rendered its ruling arbitrary and capricious. See 5 U.S.C. § 706(2)(a) (1988). Northwest also claims that the FAA’s approval of the PFC based on [67]*67Memphis’s proposed alternative project violated the PFC statute’s requirements that PFC applications be tied to “specific projects,” 49 U.S.C. app. § 1513(e)(2) (Supp. II 1990), and that the airlines be consulted about each of these projects before the application is submitted, id. § 1513(e)(ll)(C). Finally, Northwest argues that the FAA violated the statute by allowing Memphis to impose PFCs on frequent flyer customers.

We do not reach Northwest’s frequent flyer argument because the airline failed to exhaust its administrative remedies as required by 49 U.S.C. app. § 1486(e) (1988). On the merits of Northwest’s remaining challenges, we defer to the FAA’s reasonable construction of the PFC statute and reject the petition for review in large part. However, because we find that the FAA did violate the consultation provisions of the statute with respect to Memphis’s proposed alternative project, we conclude that Memphis may not expend its PFC funds to finance this alternative project.

I. BACKGROUND

In 1990, Congress amended the Federal Aviation Act to allow local public airport authorities to petition the FAA for permission to impose PFCs on passengers using the airport. See Pub.L. No. 101-508, § 9110,104 Stat. 1388-357 (codified as amended at 49 U.S.C. app. § 1513(e) (Supp. II 1990)). The statute authorizes the FAA1 to “grant a public agency which controls a commercial service airport authority to impose a fee of $1.00, $2.00, or $3.00 for each paying passenger of an air carrier enplaned at such airport to finance eligible airport-related projects to be carried out in connection with such airport or any other airport which such agency controls.” 49 U.S.C. app. § 1513(e)(1). The FAA may only authorize an airport to collect PFCs in order to finance

specific ... eligible airport-related' projects] which will—
(i)preserve or enhance capacity, safety, or security of the national air transportation system,
(ii) reduce noise resulting from an airport which is, part of such system, or
(iii) furnish opportunities for enhanced competition between or among air carriers.

Id. § 1513(e)(2)(B).

The statute further provides that “[b]efore submission of an application under [the PFC statute], a public agency shall provide reasonable notice to, and an opportunity for consultation with, air carriers operating at the airport.” Id. § 1513(e)(ll)(C). As part of this consultation process, the airport authority must provide air carriers with written notice of “individual projects being considered for funding through imposition” of PFCs. Id. § 1513(e)(ll)(C)(i)(I).

On January 28, 1992, the Memphis-Shelby County Airport Authority (“Memphis”) requested FAA permission to impose a $3.00 PFC on all passengers enplaned at Memphis International Airport. Memphis’s application identified four primary projects that it hoped to finance with PFC revenue: 1) the acquisition-of land and the relocation of roadways and utilities to allow future airport development; 2) construction of a new runway; 3) reconstruction and extension of an existing runway; and 4) construction of a new taxiway. In addition, Memphis’s application identified a backup project for which the PFC revenue would be used in the event that the FAA failed to approve one or more of its primary projects. This alternative proposal was to use PFC revenues to purchase homes in high noise corridors to reduce the impact of noise on communities surrounding the airport. Memphis had not mentioned this alternative “noise compatibility project” when it consulted with Northwest and other airlines prior to submitting its PFC application.

Ón May 28, the FAA authorized Memphis to impose a $3.00 PFC and approved its runway and taxiway projects. Record of Decision, Memphis-Shelby Comity Airport Authority at 2-3 (May 28, 1992). However, because Memphis had yet to secure the re[68]*68quired environmental clearance to proceed with its runway and taxiway projects, see 14 C.F.R. § 158.25(c)(l)(ii)(B), the FAA also approved the noise compatibility project as an “alternative use” for the PFC revenues “in the event that one or more of the primary projects [was] not implemented in a timely manner.” Record of Decision at 4. Thus, the FAA’s decision authorized Memphis only to “impose” the PFC but did not yet grant Memphis approval to “use” the PFC revenue on any particular project. Id.

Northwest now challenges the FAA’s approval of the Memphis PFC.

II. DISCUSSION

A. Standard of Review

Each of Northwest’s objections to the FAA’s approval of the Memphis PFC ultimately attacks the FAA’s interpretation of the PFC statute. We therefore evaluate these challenges under the framework set forth in Chevron U.S.A., Inc. v. Natural Resources Defense Council, Inc., 467 U.S. 837, 842-44, 104 S.Ct. 2778, 2781, 81 L.Ed.2d 694 (1984). Chevron requires us first to ask

whether Congress has directly spoken to the precise question at issue. If we can come to the unmistakable conclusion that Congress had an intention on the precise question at issue our inquiry ends there.... However, if the statute before us is silent or ambiguous with respect to the specific issue[ ] before us, we proceed to the second step. At this stage, we defer to the agency’s interpretation of the statute if it is reasonable and consistent with the statute’s purpose.

Nuclear Info. Resource Serv. v. Nuclear Regulatory Comm’n, 969 F.2d 1169, 1173 (D.C.Cir.1992) (en banc) (citations and internal quotations omitted). We evaluate Northwest’s statutory challenges using this two-step analysis.

B. FAA’s Failure to Consider the Economic and Competitive Effects of its Decision

In comments to the agency, Northwest objected that the imposition of a $3.00 PFC at its Memphis hub would place the airline at a competitive disadvantage with carriers whose hubs did not impose PFCs. Northwest argued that extreme competition in the airline industry would force Northwest to absorb the PFC itself rather than passing the charge along to its passengers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kumar v. Garland
Second Circuit, 2023
Lin v. Garland
Second Circuit, 2021
Greenspan v. Qazi
N.D. California, 2021
Seneca Nation of Indians v. State of New York
988 F.3d 618 (Second Circuit, 2021)
Qwest Corp v. FCC
D.C. Circuit, 2007
Air Trans Assn Amer v. FAA
169 F.3d 1 (D.C. Circuit, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
14 F.3d 64, 304 U.S. App. D.C. 302, 1994 U.S. App. LEXIS 1731, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwest-airlines-inc-v-federal-aviation-administration-memphis-shelby-cadc-1994.