North American Contracting Corp. v. Gibson

327 So. 2d 444
CourtLouisiana Court of Appeal
DecidedMay 11, 1976
Docket5266
StatusPublished
Cited by22 cases

This text of 327 So. 2d 444 (North American Contracting Corp. v. Gibson) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North American Contracting Corp. v. Gibson, 327 So. 2d 444 (La. Ct. App. 1976).

Opinion

327 So.2d 444 (1975)

NORTH AMERICAN CONTRACTING CORPORATION et al., Plaintiffs and Appellants,
v.
John GIBSON et al., Defendants and Appellees.

No. 5266.

Court of Appeal of Louisiana, Third Circuit.

February 6, 1975.
Rehearing Denied March 17, 1976.
Writ Refused May 11, 1976.

*446 James L. Fortson, Jr., and Hal V. Lyons, Shreveport, Calvin T. Guidry, Lafayette, for plaintiffs and appellants.

Davidson, Meaux, Onebane & Donohoe by John G. Torian, II, Lafayette, for defendants and appellees.

Before CULPEPPER, GUIDRY and PAVY, JJ.

CULPEPPER, Judge.

This is a suit for damages for breach of a construction contract. The plaintiff, North American Contracting Corporation, was the general contractor for construction of an apartment project. Defendants subcontracted to furnish the carpentry labor. Plaintiff contends defendants failed to perform in a workmanlike manner, failed to follow the specifications and finally "pulled off" the job before completion. Defendants contend they quit work because plaintiff failed to pay them the monthly "draws" to which they were entitled under the contract. The district judge, without assigning reasons, rejected plaintiff's demands and dismissed its suit. Plaintiff appealed.

The apartment project was to be constructed on land owned by Dewey, Cheatham and Howe, Inc., which had previously entered into a contract with North American Contracting Corporation as general contractor. Both Dewey, Cheatham & Howe, Inc. and North American Contracting Corporation are controlled by Mr. R. L. Saucier, Jr. He is named as a party plaintiff, but actually has no individual interest in this suit. Turnkey Constructors, Inc., on the other hand, is owned by defendants, Jerry German and John Gibson. The subcontract provided that Turnkey was to perform the "carpentry work, rough carpentry and finish carpentry". Defendants were to furnish labor only. The general contractor supplied all the materials. The project was to be constructed according to plans and specifications to be provided by the general contractor at a later date. The price to be paid to the defendants was based on the number of square feet or linear feet completed at different stages of construction, as for example, 55¢ per square foot for "rough carpentry" and 30¢ for "trim out", etc. Defendants were to receive a monthly "draw" representing 90% of the price of the work completed in the prior month.

The project was to be financed by a loan from the Great American Mortgage Investment Company to Dewey, Cheatham & Howe, Inc. In this agreement, it was provided that "draws" would be submitted by North American as the work progressed and that the amount of a draw, less 10% "retainage", would be paid to Dewey, Cheatham & Howe, Inc. for ultimate payment to the subcontractors. These draws were to be certified by Dewey, Cheatham & Howe, Inc., North American Contracting Corporation and by the inspecting architect, Mr. Ellis. In effect then, the draws were certified by Mr. Ellis and by Mr. Saucier, since he controlled both corporations. The loan agreement, which had been perfected prior to the instant contract with the subcontractor, Turnkey, allowed a total of $96,000 to be borrowed for carpentry labor. Mr. Ellis was inspecting architect for both the owner and the mortgagee. However, Mr. Saucier also had a "superintendent", Max Lovelace, and later Jim Prine who was to check to be sure work was actually performed. Mr. Ellis was to inspect both workmanship and material and he certified draws by both the subcontractors and the general contractor.

The project was begun in August of 1971. Turnkey began work in the latter part of October or the first part of November of that same year. Work Progressed *447 smoothly for a while but later there was disagreement between the contractor and the subcontractor, Turnkey.

Though the contract provided that the subcontractor would be paid on a square foot basis, Mr. Saucier agreed that the first "draw" would be based simply on defendants' expenses. However, this was only for the first month's draw. Thereafter, the written contract controlled the draws. Mr. Saucier testified that after the first draw, amounts were certified to the mortgagee and a portion of that amount was paid to the subcontractor, Turnkey, according to "eyeball estimates" by him and his superintendent. Mr. Saucier continued to make draws and pay Turnkey in this manner until April of 1972, at which time he paid Turnkey for the work done during March. The trouble started when Saucier refused to pay Turnkey in May for work done during April. Saucier claimed that Turnkey at that point had already been overpaid for the work it had thus far completed. Turnkey disagreed and claimed that North American had breached its contract with Turnkey by failing to pay the amounts due. As a result of this disagreement, Turnkey "pulled off" the job and ceased all work on the project in early June of 1972.

There is no doubt that defendant Turnkey breached its contract with North American by "pulling off" the job without completing it. The first issue is whether defendants were justified in stopping work because they had not been paid the draws due under the contract. We ultimately conclude that at the time defendants pulled off the job, they had been paid more than the amount due them in draws under the contract.

We base our conclusion largely on the opinion of Mr. Jaco LeBlanc, a highly qualified architect, who had practiced for 18 years. Mr. Saucier contracted him in June of 1972 to do a progress report on the project. There is no evidence of any prior relations between them. In June of 1972, LeBlanc made a thorough examination of the project. He took pictures of the work and completed a room-by-room study of the amount of work that had been completed under the contract and of the quality of workmanship.

Mr. LeBlanc found that of the three units to be built in the complex, Unit 1 was 85% complete. He found Unit 2 to be 60% complete and Unit 3 only 50% complete. In Unit 1, for example, he found the paneling was not installed, some base molding was not installed, kitchen cabinets were not installed, hardware was missing, and linen closets were not installed. The photographs introduced into evidence clearly support his statements. Having determined the above percentages of the work completed from his inspection of the project, Mr. LeBlanc computed the monetary value of the carpentry work done by defendants using the square foot basis in the contract. On this basis, he computed that the value of the carpentry work completed by defendants was $49,875.56, including the 10% retainage. Thus, according to Mr. LeBlanc's figures, defendant should have been paid only 90% of that amount, i.e., $44,888, in draws. Actually, defendants had been paid $66,916.30. Thus, at the time they pulled off the job, defendants had received $22,028 in excess of the draws due them.

Mr. LeBlanc's figures must be accepted by us as correct for the reason that he was the only expert who made a detailed inspection to determine the amount due defendants under the contract. The only other witnesses testifying as to the value of the work completed were John Gibson, a defendant, and John Ellis, the "inspecting architect". Mr. Gibson's testimony was of little value. He was unable to recall the exact square footage that he had completed. In fact, he couldn't even estimate it. Mr. Ellis' testimony is of little, if any, value. He testified that he inspected the premises and estimated generally the percentage *448 of work completed at the time of each draw paid to defendants.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Louisiana Gaming Corp. v. Rob's Mini-Mart, Inc.
666 So. 2d 1268 (Louisiana Court of Appeal, 1996)
Grezaffi v. Smith
641 So. 2d 210 (Louisiana Court of Appeal, 1994)
Bond v. Allemand
632 So. 2d 326 (Louisiana Court of Appeal, 1993)
Mini Togs Products, Inc. v. Wallace
513 So. 2d 867 (Louisiana Court of Appeal, 1987)
Simmons v. Sowela Technical Institute
470 So. 2d 913 (Louisiana Court of Appeal, 1985)
FIRST FEDERAL SAVINGS & LOAN OF NATHITOCHES v. American Bank & Trust Co.
461 So. 2d 341 (Louisiana Court of Appeal, 1984)
Maltzahn v. Roch
427 So. 2d 586 (Louisiana Court of Appeal, 1983)
Phillips v. Insilco Sports Network, Inc.
429 So. 2d 447 (Louisiana Court of Appeal, 1983)
Sweeney v. POPEYES FAMOUS FRIED CHICKEN
427 So. 2d 464 (Louisiana Court of Appeal, 1983)
Brown v. State Farm Fire & Cas. Co.
407 So. 2d 1251 (Louisiana Court of Appeal, 1981)
Rogers v. Nelson Dodge, Inc.
407 So. 2d 443 (Louisiana Court of Appeal, 1981)
Boydstun v. Johnson
401 So. 2d 629 (Louisiana Court of Appeal, 1981)
Manzanares v. AMERICAN INTERN. FOREST PRODUCTS, INC.
389 So. 2d 1142 (Louisiana Court of Appeal, 1980)
Smedes-Jardine & Co. v. Romero
376 So. 2d 333 (Louisiana Court of Appeal, 1979)
CENTRAL LOUISIANA ELEC. v. Giant Enterprises
371 So. 2d 641 (Louisiana Court of Appeal, 1979)
Louisiana Power & Light Co. v. Bourgeois
355 So. 2d 597 (Louisiana Court of Appeal, 1978)
Maxwell v. Bernard
343 So. 2d 431 (Louisiana Court of Appeal, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
327 So. 2d 444, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-american-contracting-corp-v-gibson-lactapp-1976.