Nicholson Construction Co. v. Standard Fire Insurance

760 F.2d 74
CourtCourt of Appeals for the Third Circuit
DecidedApril 30, 1985
DocketNo. 84-1319
StatusPublished
Cited by4 cases

This text of 760 F.2d 74 (Nicholson Construction Co. v. Standard Fire Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nicholson Construction Co. v. Standard Fire Insurance, 760 F.2d 74 (3d Cir. 1985).

Opinion

OPINION OF THE COURT

WEIS, Circuit Judge.

The district court decided that a subcontractor three levels removed from the prime contractor had standing to sue on a construction payment bond. Viewing the issue against the background of the state bonding law, we conclude that the words “as subcontractor or otherwise” in the payment bond do not extend its coverage beyond the two tiers recognized by the statute. Accordingly, we reverse the summary judgment against the sureties.

[75]*75Plaintiff filed this suit against the surety companies on a payment bond issued in connection with the construction of a sewage plant for the City of Philadelphia. The district court entered summary judgment for plaintiff, and defendants appeal.

The prime contractor for the project was a joint venture composed of Buckley & Company, Inc. and others, hereafter referred to as Buckley. Buckley subcontracted part of the work to C. Hannah Construction Company, which in turn subcontracted to Geofreeze Corporation. That company then subcontracted for specialized drilling services with plaintiff Nicholson Construction Company. Plaintiff, therefore, was a subcontractor to a sub-subcontractor, or three steps removed from the prime contractor.

Before commencing work on the project, Buckley executed a payment bond in favor of the City of Philadelphia on a form provided by the city with defendants acting as sureties. The bond provided for payment of sums due for material furnished, equipment or machinery used, and labor supplied in the prosecution of the work required by the terms of the prime contract.

The bond also included the following provision, which is the subject of this controversy:

“... every person ... who, whether as a sub-contractor or otherwise, has furnished material, rented equipment or machinery, rendered services or supplied or performed labor in the prosecution of the work above mentioned and described, and who has not been paid therefor, may sue in assumpsit on this bond____”

An additional provision stated that any person “who has no contractual relationship, express or implied, with the [prime contractor] shall not have a right of action” on the bond unless written notice was given to the prime contractor within a specified time.

The bond was required by the city in accordance with the Pennsylvania Public Works Contractors’ Bond Law of 1967, Pa. Stat.Ann. tit. 8, § 191 et seq. (Purdon Supp. 1984-85). The statute provides that the prime contractor must furnish a performance bond and a payment bond, the latter being for 100 percent of the contract amount. The payment bond “shall be solely for the protection of claimants supplying labor or materials to the prime contractor ... or to any of his subcontractors.” Pa. Stat.Ann. tit. 8, § 193(a)(2).

The Act further provides that a claimant “who has a direct contractual relationship with any subcontractor of the prime contractor ... but has no contractual relationship, express or implied, with such prime contractor” may bring an action on the bond only after giving notice to the prime contractor within a specified time. Pa.Stat. Ann. tit. 8, § 194(b).

This suit on the bond was filed when Geofreeze was unable to pay Nicholson for the work it had performed. The sureties defended on the basis that Nicholson had no standing under the terms of the bond because its relationship had not been with Buckley or any of its subcontractors. There being no dispute about the material facts and the parties having agreed on the amount in dispute, the matter was submitted on summary judgment motions. The district court did not prepare a written opinion but entered judgment for plaintiff.

On appeal, the parties agree that Pennsylvania law controls and that the critical issue is the legal effect of the phrase, “whether, as subcontractor or otherwise” appearing in the bond.

The sureties contend that the language of the bond should be read in conformity with the Bond Law. Nicholson concedes that such a reading would preclude recovery because its services were not supplied to a subcontractor but rather to a sub-subcontractor. Nicholson argues, however, that use of the term “or otherwise” establishes an expansive scope for the bond— coverage which exceeds the requirements of the Bond Law and which would include payment for the work performed for Geo-freeze.

When, as here, construction of a contract is the issue before an appellate court, the question is one of law and freely [76]*76reviewable. Ram Constr. Co. Inc. v. American States Ins. Co., 749 F.2d 1049, 1053 (3d Cir.1984). “Construction, which may be usefully distinguished from interpretation is a process by which legal consequences are made to follow from the terms of the contract and its more or less immediate context and from a legal policy or policies that are applicable to the situation.” Patterson, The Interpretation and Construction of Contracts, 64 Col.L.Rev. 833, 835 (1964).

No closely analogous situation has been found in the state decisional law. Nicholson relies on cases which make clear that while a bond provided for a municipal construction contract must meet the minimum required by the Bond Law, the undertaking may be broader. See Merion Township School Dist. v. Evans, 295 Pa. 280, 145 A. 288 (1929).

Although the coverage provided in a particular bond may exceed the statutory requirements, the Pennsylvania Supreme Court has cautioned that

“the obligation of a bond cannot be extended beyond the plain import of the words used ... Obligations not imposed by the terms of the bond cannot be created by judicial construction or interpretation which extends the terms beyond their normal meaning.”

Peter J. Mascaro Co. v. Milonas, 401 Pa. 632, 635, 166 A.2d 15, 17 (1960) (quoting Commonwealth v. Fidelity and Deposit Co. of Maryland, 355 Pa. 434, 50 A.2d 211 (1947)).

In Tioga County Comm’rs v. C. Davis, Inc., 439 Pa. 285, 266 A.2d 749 (1970), the court stressed the need for stability in an area of the law having great significance for numerous businesses which supply labor and material on public contracts. “When individuals supply labor or material to a bonded job, they should not have to check the exact terms of the bond but should be able to assume that the parties have obeyed the Legislature’s mandate and included in the bond everything required by [the statute].” Id. at 289, 266 A.2d at 751. The existence of the Bond Law thus provides needed predictability to the law of public contracting.

The Tioga opinion lends some support to the sureties’ argument that if a bond is to be read more expansively than required by the statute, the bond’s terms should be explicit. A prime contractor, who is ultimately liable on a payment bond, should not bear the responsibility for unpaid labor and materialmen other than those mentioned in the Bond Law unless the bond expressly includes them.

In discussing the provisions of Miller Act bonds, the United States Supreme Court in J.W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reed v. Rhodes
179 F.3d 453 (Sixth Circuit, 1999)
R.R. Wilmot, Inc. v. American Insurance Co.
642 A.2d 584 (Commonwealth Court of Pennsylvania, 1994)
S. A. Lindstrom Co. v. Pennsylvania National Mutual Casualty Insurance Co.
1 Pa. D. & C.4th 73 (Dauphin County Court of Common Pleas, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
760 F.2d 74, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nicholson-construction-co-v-standard-fire-insurance-ca3-1985.