Nicholson Construction Company v. The Standard Fire Insurance Company

760 F.2d 74, 1985 U.S. App. LEXIS 30530
CourtCourt of Appeals for the Third Circuit
DecidedApril 30, 1985
Docket84-1319
StatusPublished

This text of 760 F.2d 74 (Nicholson Construction Company v. The Standard Fire Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nicholson Construction Company v. The Standard Fire Insurance Company, 760 F.2d 74, 1985 U.S. App. LEXIS 30530 (3d Cir. 1985).

Opinion

760 F.2d 74

NICHOLSON CONSTRUCTION COMPANY, Appellee,
v.
The STANDARD FIRE INSURANCE COMPANY, the General Reinsurance
Corporation, North American Reinsurance Corporation, the
Reinsurance Corporation of New York, Fidelity & Deposit
Company of Maryland, Employers Reinsurance Corporation, and
Aetna Casualty & Surety Company, Appellants.

No. 84-1319.

United States Court of Appeals,
Third Circuit.

Argued Feb. 25, 1985.
Decided April 30, 1985.

Peter F. Marvin (argued), Miller, Schreiber & Sloan, Philadelphia, Pa., for appellants.

William R. Sneed, III (argued), Alan D. Keiser, Kenneth M. Cushman, Pepper, Hamilton & Scheetz, Philadelphia, Pa., for appellee.

Before ADAMS, WEIS and WISDOM,* Circuit Judges.

OPINION OF THE COURT

WEIS, Circuit Judge.

The district court decided that a subcontractor three levels removed from the prime contractor had standing to sue on a construction payment bond. Viewing the issue against the background of the state bonding law, we conclude that the words "as subcontractor or otherwise" in the payment bond do not extend its coverage beyond the two tiers recognized by the statute. Accordingly, we reverse the summary judgment against the sureties.

Plaintiff filed this suit against the surety companies on a payment bond issued in connection with the construction of a sewage plant for the City of Philadelphia. The district court entered summary judgment for plaintiff, and defendants appeal.

The prime contractor for the project was a joint venture composed of Buckley & Company, Inc. and others, hereafter referred to as Buckley. Buckley subcontracted part of the work to C. Hannah Construction Company, which in turn subcontracted to Geofreeze Corporation. That company then subcontracted for specialized drilling services with plaintiff Nicholson Construction Company. Plaintiff, therefore, was a subcontractor to a sub-subcontractor, or three steps removed from the prime contractor.

Before commencing work on the project, Buckley executed a payment bond in favor of the City of Philadelphia on a form provided by the city with defendants acting as sureties. The bond provided for payment of sums due for material furnished, equipment or machinery used, and labor supplied in the prosecution of the work required by the terms of the prime contract.

The bond also included the following provision, which is the subject of this controversy:

"... every person ... who, whether as a sub-contractor or otherwise, has furnished material, rented equipment or machinery, rendered services or supplied or performed labor in the prosecution of the work above mentioned and described, and who has not been paid therefor, may sue in assumpsit on this bond...."

An additional provision stated that any person "who has no contractual relationship, express or implied, with the [prime contractor] shall not have a right of action" on the bond unless written notice was given to the prime contractor within a specified time.

The bond was required by the city in accordance with the Pennsylvania Public Works Contractors' Bond Law of 1967, Pa.Stat.Ann. tit. 8, Sec. 191 et seq. (Purdon Supp. 1984-85). The statute provides that the prime contractor must furnish a performance bond and a payment bond, the latter being for 100 percent of the contract amount. The payment bond "shall be solely for the protection of claimants supplying labor or materials to the prime contractor ... or to any of his subcontractors." Pa.Stat.Ann. tit. 8, Sec. 193(a)(2).

The Act further provides that a claimant "who has a direct contractual relationship with any subcontractor of the prime contractor ... but has no contractual relationship, express or implied, with such prime contractor" may bring an action on the bond only after giving notice to the prime contractor within a specified time. Pa.Stat.Ann. tit. 8, Sec. 194(b).

This suit on the bond was filed when Geofreeze was unable to pay Nicholson for the work it had performed. The sureties defended on the basis that Nicholson had no standing under the terms of the bond because its relationship had not been with Buckley or any of its subcontractors. There being no dispute about the material facts and the parties having agreed on the amount in dispute, the matter was submitted on summary judgment motions. The district court did not prepare a written opinion but entered judgment for plaintiff.

On appeal, the parties agree that Pennsylvania law controls and that the critical issue is the legal effect of the phrase, "whether, as subcontractor or otherwise" appearing in the bond.

The sureties contend that the language of the bond should be read in conformity with the Bond Law. Nicholson concedes that such a reading would preclude recovery because its services were not supplied to a subcontractor but rather to a sub-subcontractor. Nicholson argues, however, that use of the term "or otherwise" establishes an expansive scope for the bond--coverage which exceeds the requirements of the Bond Law and which would include payment for the work performed for Geofreeze.

When, as here, construction of a contract is the issue before an appellate court, the question is one of law and freely reviewable. Ram Constr. Co. Inc. v. American States Ins. Co., 749 F.2d 1049, 1053 (3d Cir.1984). "Construction, which may be usefully distinguished from interpretation is a process by which legal consequences are made to follow from the terms of the contract and its more or less immediate context and from a legal policy or policies that are applicable to the situation." Patterson, The Interpretation and Construction of Contracts, 64 Col.L.Rev. 833, 835 (1964).

No closely analogous situation has been found in the state decisional law. Nicholson relies on cases which make clear that while a bond provided for a municipal construction contract must meet the minimum required by the Bond Law, the undertaking may be broader. See Merion Township School Dist. v. Evans, 295 Pa. 280, 145 A. 288 (1929).

Although the coverage provided in a particular bond may exceed the statutory requirements, the Pennsylvania Supreme Court has cautioned that

"the obligation of a bond cannot be extended beyond the plain import of the words used ... Obligations not imposed by the terms of the bond cannot be created by judicial construction or interpretation which extends the terms beyond their normal meaning."

Peter J. Mascaro Co. v. Milonas, 401 Pa. 632, 635, 166 A.2d 15, 17 (1960) (quoting Commonwealth v. Fidelity and Deposit Co. of Maryland, 355 Pa. 434, 50 A.2d 211 (1947)).

In Tioga County Comm'rs v. C. Davis, Inc., 439 Pa.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jacobs v. Northeastern Corp.
206 A.2d 49 (Supreme Court of Pennsylvania, 1965)
Valley Forge Industries, Inc. v. Armand Construction, Inc.
374 A.2d 1312 (Superior Court of Pennsylvania, 1977)
Can-Tex Industries v. Safeco Insurance Co. of America
460 F. Supp. 1022 (W.D. Pennsylvania, 1978)
Merion Township School District v. Evans
145 A. 288 (Supreme Court of Pennsylvania, 1928)
Commonwealth v. Fidelity & Deposit Co. of Maryland
50 A.2d 211 (Supreme Court of Pennsylvania, 1946)
Peter J. Mascaro Co. v. Milonas
166 A.2d 15 (Supreme Court of Pennsylvania, 1960)
Tioga County Commissioners v. C. Davis, Inc.
266 A.2d 749 (Supreme Court of Pennsylvania, 1970)
Philadelphia v. Fidelity & Deposit Co. of Maryland
46 Pa. Super. 313 (Superior Court of Pennsylvania, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
760 F.2d 74, 1985 U.S. App. LEXIS 30530, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nicholson-construction-company-v-the-standard-fire-insurance-company-ca3-1985.