R.R. Wilmot, Inc. v. American Insurance Co.

642 A.2d 584, 164 Pa. Commw. 175, 1994 Pa. Commw. LEXIS 233
CourtCommonwealth Court of Pennsylvania
DecidedMay 18, 1994
StatusPublished
Cited by1 cases

This text of 642 A.2d 584 (R.R. Wilmot, Inc. v. American Insurance Co.) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.R. Wilmot, Inc. v. American Insurance Co., 642 A.2d 584, 164 Pa. Commw. 175, 1994 Pa. Commw. LEXIS 233 (Pa. Ct. App. 1994).

Opinion

DELLA PORTA, Senior Judge.

R.R. Wilmot, Inc. (Wilmot) appeals from an order of the Court of Common Pleas of Wayne County which sustained the preliminary objections of the American Insurance Company (American Insurance) and dismissed Wilmot’s complaint.

The Quandel Group, Inc. (Quandel) acted as general contractor for the construction of the Western Wayne Middle School, in South Canaan Township, Wayne County. As required by the contract with the Western Wayne School District, Quandel obtained a payment bond with American Insurance acting as surety.

[585]*585In its complaint, Wilmot alleged the following. Earth and Pipe Construction, Inc. (Earth & Pipe) and Soden & Mardane Excavation, Inc. (Soden & Mardane) entered into subcontracts with Quandel for the performance of certain construction-related services at the project. In or about July 1990, Wilmot offered to supply labor, materials and/or equipment in connection with the contracts between and/or among Soden & Mar-dane, Earth & Pipe and Quandel. Wilmot supplied labor, materials and equipment to Earth & Pipe through September 18, 1990 and to Soden & Mardane through September 20, 1990.

Wilmot submitted invoices and work orders totalling $150,241.75 to Earth & Pipe and Soden & Mardane. Of this amount, $76,500.00 had been paid. By letter dated December 13, 1990, Wilmot informed Quan-del that $46,449.00 was due and owing from Earth & Pipe and $27,292.75 was due and owing from Soden and Mardane. Wilmot informed Quandel that if payment in full was' not received, a claim would be filed against the payment bond.

By letter dated January 7, 1991, American Insurance requested that Wilmot complete proof-of-claim forms and return the forms together with itemization and documentation to support the claim. On March 12, 1991, Wilmot filed an action in the Court of Common Pleas of Wayne County against American Insurance for the unpaid balance of $73,-741.25. Wilmot alleged that American Insurance failed to inform Wilmot of any action it had taken with respect to investigation of the claim. Therefore, Wilmot alleged, American Insurance had effectively denied the claim without justification and breached its obligations to Wilmot under the payment bond.

On June 13, 1991 Quandel sent Wilmot a check in the amount of $46,449.00, the amount Wilmot asserted was due from Earth & Pipe. On December 1, 1992, American Insurance filed preliminary objections to Wil-mot’s complaint. American Insurance asserted that Quandel entered into a subcontract with Earth & Pipe but at no time did Quandel enter into a contract with Soden & Mardane. American Insurance asserted that to the extent Wilmot performed work for Earth & Pipe, a subcontractor of Quandel, Wilmot’s work was covered by the payment bond. American Insurance further asserted that the work Wilmot performed for Soden & Mardane was done for a sub-subcontractor and is beyond the scope of the payment bond and Pennsylvania’s Bond Law.1

The trial court regarded American Insurance’s preliminary objections as being in the nature of a demurrer. The court noted that the language restricting protection under the payment bond followed similar language in the Bond Law which states that coverage on public works projects “shall be solely liable for the protection of claimants supplying labor or materials to the prime contractor to whom the contract was awarded, or to any of his subcontractors ...” Section 3(a)(2) of the Bond Law, 8 P.S. § 193(a)(2). The court also noted that the payment bond was executed and delivered under and subject to the Bond Law. The court found that under the clear language of the payment bond, protection is limited to those performing work for the principal and its subcontractors. Applying the definition of “subcontractor” set forth in J.W. Bateson Co. v. United States, 434 U.S. 586, 98 S.Ct. 873, 55 L.Ed.2d 50 (1978), and which was adopted in Lezzer Cash & Carry, Inc. v. Aetna Insurance Co., 371 Pa.Superior Ct. 137, 537 A.2d 857, petition for allowance of appeal denied, 519 Pa. 666, 548 A.2d 256 (1988),2 the trial court held that Wilmot may not recover for work performed for Soden & Mardane, a second-tier subcontractor.3 The trial court then sustained the preliminary [586]*586objections and dismissed Wilmot’s complaint. This appeal followed.4

The sole issue on appeal is whether the trial court erred in sustaining American Insurance’s preliminary objections on the basis that Wilmot was not a proper claimant under the payment bond.5 In reviewing a trial court order sustaining preliminary objections in the nature of a demurrer, this Court’s scope of review is limited to determining whether the trial court abused its discretion or committed an error of law. Factor v. Goode, 149 Pa.Commonwealth Ct. 81, 612 A.2d 591 (1992), petition for allowance of appeal denied, 538 Pa. 654, 624 A.2d 112 (1993).

Wilmot argues that the trial court erred in sustaining American Insurance’s preliminary objections because the payment bond secured by Quandel provides more coverage for subcontractors and assignees of subcontractors than is mandated by the Bond Law. Wilmot argues that the payment bond expressly included Wilmot within its coverage and relies on the following provision:

NOW, THEREFORE, The terms and conditions of this Bond are and shall be that, if the Principal and any Subcontractor of the Principal to whom any portion of the work under the Agreement shall be subcontracted, and if all assignees of the Principal and of any such Subcontractor promptly shall pay or shall cause to be paid, in full, all money which may be due any claimant supplying labor or materials in the prosecution and performance of the work in accordance with the Agreement and in accordance with the Contract Documents, including any amendment, extension or addition to the Agreement and/or to the Contract Documents, for all material furnished or labor supplied or labor performed, then this Bond shall be void; otherwise, this Bond shall be and shall remain in force and effect.

Wilmot specifically relies on the following phrase from the above-quoted paragraph, “and if all assignees of ... any such Subcontractor promptly shall pay or shall cause to be paid, in full, all money which may be due any claimant supplying labor or materials....”

Although the coverage provided in a bond may exceed the statutory requirements, our Supreme Court has cautioned: “[T]he obligation of a bond cannot be extended beyond the plain import of the words used_ Obligations not imposed by the terms of the bond cannot be created by judicial construction or interpretation which extends the terms beyond their normal meaning.” Peter J. Mascaro Co. v. Milonas, 401 Pa. 632, 635, 166 A.2d 15, 17 (1960) (quoting Commonwealth, to use v. Fidelity & Deposit Co. of Maryland, 355 Pa. 434, 437, 50 A.2d 211, 212 (1947)).

In Nicholson Construction Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
642 A.2d 584, 164 Pa. Commw. 175, 1994 Pa. Commw. LEXIS 233, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rr-wilmot-inc-v-american-insurance-co-pacommwct-1994.