New Mexico Industrial Energy Consumers v. New Mexico Public Service Commission

725 P.2d 244, 104 N.M. 565
CourtNew Mexico Supreme Court
DecidedAugust 25, 1986
Docket15790
StatusPublished
Cited by22 cases

This text of 725 P.2d 244 (New Mexico Industrial Energy Consumers v. New Mexico Public Service Commission) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Mexico Industrial Energy Consumers v. New Mexico Public Service Commission, 725 P.2d 244, 104 N.M. 565 (N.M. 1986).

Opinion

OPINION

SOSA, Senior Justice.

This case concerns a decision by the New Mexico Public Service Commission (Commission) to develop a methodology to apply in future rate cases brought by the Public Service Company of New Mexico (PNM) to account for excess generating capacity. Appellant, New Mexico Industrial Energy Consumers (NMIEC), moved to intervene. All of the interested parties agreed to form a Task Force to study the problem and make recommendations to the Commission. The Task Force arrived at a Stipulation, which NMIEC did not sign. The Commission held a hearing and subsequently entered a Final Order approving the Stipulation.

NMIEC applied for rehearing. Because the Commission did not act on the application within the twenty days provided by statute, it was deemed denied as a matter of law. NMSA 1978, § 62-10-16 (Repl.Pamp.1984). NMIEC appeals to this Court. We affirm.

NMIEC raises three issues on appeal.

I. Whether the Commission deprived NMIEC of procedural due process of law;

II. Whether the Commission has approved a procedure that is contrary to established law; and

III. Whether there is substantial evidence in the record as a whole to support the decision of the Commission.

BACKGROUND

PNM first proposed the “inventoried capacity methodology” with its application for a certificate of public convenience and necessity to construct a major transmission line, in NMPSC Case 1794, filed on January 21, 1983. The Commission bifurcated this case and docketed Case 1804 solely to consider the concept and consequences of inventorying.

NMIEC moved to intervene in Case 1804 on July 6, 1983. The Commission scheduled a hearing for September 26, 1983, limiting it to cross examination of PNM witnesses on their prefiled testimony. After four days, the hearing was recessed because of a year’s delay in the projected completion dates for Units 1-3 of the Palo Verde Nuclear Generating Station (PVNGS), a principal source of PNM’s excess capacity. The hearing was rescheduled for November 29, 1983. In the interim, both the Commission Staff (Staff) and the New Mexico Attorney General (AG) filed formal discovery requests, but NMIEC did not.

On November 8,1983, the Staff moved to dismiss PNM’s application as premature in light of the delayed construction. The Staff suggested instead creating a task force comprised of representatives of PNM, the Staff and Intervenors, to study the question of uncommitted capacity and propose an appropriate ratemaking methodology. The Commission approved a stipulation on January 19, 1984, whereby all the parties, including NMIEC, agreed to form such a task force and to report their conelusions by August 1, 1984, thus enabling the Commission to hold hearings and reach a final decision in the case no later than May 15, 1985.

The Task Force met at least monthly from February through November, 1984. NMIEC, through its attorneys, attended most of the meetings and participated in the free flow of information and analysis. At the request of Task Force members, including NMIEC, PNM prepared numerous studies to evaluate the different proposed methodologies.

In March, 1984, the Task Force began to discuss specific proposals and to evaluate them according to the group goal of balancing the interests of present and future ratepayers as well as PNM’s shareholders. In fact, the members drafted a statement of principles to guide their deliberations. Foremost of these was the desire to ensure that ratepayer costs would be no higher than under the traditional methodology. A further objective was to provide PNM with incentives to resolve the uncommitted capacity situation and to prevent its recurrence. On October 9, 1984, NMIEC presented its own proposal for an inventorying methodology, one of five reviewed in depth by the task force. PNM analyzed the financial impacts of all the proposals, and presented them to the Task Force and to NMIEC’s expert consultants. None of the proposals satisfied all the Task Force objectives and criteria.

On October 10, 1984, the Commission indicated that it preferred to receive a stipulation rather than a report from the Task Force, and proposed a form for such stipulation. By Order of November 7, 1984, the Commission scheduled a hearing on the matter for December 3, 1984.

On November 7, 8, and 9, 1984, the members of the Task Force convened to seek consensus on a Stipulation, which they drafted on November 13, 1984. The final version presented to the Commission made only minor changes in wording. On November 15 and 16, 1984, representatives of PNM met with attorneys for NMIEC to discuss the Stipulation, which was subsequently signed by all the Task Force members except NMIEC and the United States Executive Agencies (USEA).

On November 20, 1984, the Commission ordered PNM to submit its prefiled testimony by November 26, 1984, and ordered the Staff and Intervenors to prefile their testimony by November 30, 1984. On November 30, 1984, NMIEC filed a motion to vacate the hearing scheduled for December 3, 1984, on the grounds that the hearing date set by the Commission denied NMIEC due process of law by not allowing NMIEC an opportunity to prepare and present rebuttal testimony.

The Commission heard and denied NMIEC’s motion at the outset of the hearing on December 3, 1984. NMIEC remained at the hearing, but presented no testimony nor alternatives to the proposed Stipulation. On December 12, 1984, the Commission entered its Final Order in Case 1804, approving the Stipulation and adopting the inventorying methodology proposed by the Task Force. On January 11, 1985, NMIEC filed its application for rehearing, which was not granted, and consequently was deemed denied by operation of law on January 31, 1985. NMIEC then appealed to this Court.

I. DUE PROCESS

NMIEC bases its claim here on two points: First, that it was denied the right to conduct discovery; and second, that it was not allowed sufficient time to prepare expert rebuttal testimony.

At the outset, we observe that the proceeding below was unique, both in the problem it addressed and in the solutions which evolved. For the purposes of discussion, we assume, but do not decide, that NMIEC has a constitutionally protected interest in a “methodology,” even though present rates are unaffected thereby, and NMIEC will possess the full panoply of procedural rights of intervention in subsequent rate hearings, whenever the inventoried capacity comes on line.

Having identified the property interest, we must determine what process is due it. Mathews v. Eldridge, 424 U.S. 319, 96 S.Ct. 893, 47 L.Ed.2d 18 (1976). The cases cited by NMIEC confirm that due process is a flexible concept whose essence is the right to be heard at a meaningful time and in a meaningful manner. See, e.g., Logan v. Zimmerman Brush Co., 455 U.S. 422, 102 S.Ct. 1148, 71 L.Ed.2d 265 (1982); see also State v. Valdez, 88 N.M.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

N.M. Att'y. Gen. v. N.M. Pub. Regulation Comm'n.
2015 NMSC 32 (New Mexico Supreme Court, 2015)
Martinez v. Public Employees Retirement Ass'n
2012 NMCA 096 (New Mexico Court of Appeals, 2012)
Martinez v. Public Emples Retirement Ass'n
2012 NMCA 96 (New Mexico Court of Appeals, 2012)
TW Telecom of N.M. v. NM Pub. Reg. Comm'n
2011 NMSC 29 (New Mexico Supreme Court, 2011)
Bass Enterprises Production Co. v. Mosaic Potash Carlsbad Inc.
2010 NMCA 065 (New Mexico Court of Appeals, 2010)
PNM v. PRC DEC
New Mexico Supreme Court, 2009
In Re Com'n Investigation
980 P.2d 37 (New Mexico Supreme Court, 1999)
U S West Communications, Inc. v. New Mexico State Corp. Commission
1999 NMSC 016 (New Mexico Supreme Court, 1999)
PNM Electric Services v. New Mexico Public Utility Commission
1998 NMSC 017 (New Mexico Supreme Court, 1998)
Application of Pnm Elec. Services
961 P.2d 147 (New Mexico Supreme Court, 1998)
Dente v. State Taxation & Revenue Department, Motor Vehicle Division
1997 NMCA 099 (New Mexico Court of Appeals, 1997)
Pierce v. State Ex Rel. New Mexico Taxation & Revenue Department
910 P.2d 288 (New Mexico Supreme Court, 1995)
Behles v. New Mexico Public Service Commission
836 P.2d 73 (New Mexico Supreme Court, 1992)
Attorney General v. New Mexico Public Service Commission
808 P.2d 606 (New Mexico Supreme Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
725 P.2d 244, 104 N.M. 565, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-mexico-industrial-energy-consumers-v-new-mexico-public-service-nm-1986.