New Mexico Industrial Energy Consumers v. New Mexico Public Service Commission

808 P.2d 592, 111 N.M. 622
CourtNew Mexico Supreme Court
DecidedFebruary 20, 1991
Docket18381, 18415
StatusPublished
Cited by43 cases

This text of 808 P.2d 592 (New Mexico Industrial Energy Consumers v. New Mexico Public Service Commission) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Mexico Industrial Energy Consumers v. New Mexico Public Service Commission, 808 P.2d 592, 111 N.M. 622 (N.M. 1991).

Opinion

OPINION

BACA, Justice.

The attorney general and New Mexico Industrial Energy Consumers (NMIEC) appeal from a final order issued by the New Mexico Public Service Commission (Commission) in its case No. 2146, Part II. The order has been reported as In re Public Service Company, 101 Pub.Util.Rep. (PUR) 4th 126 (1989) (hereinafter Final Order). In the original application for a hearing, the Public Service Company of New Mexico (PNM) sought authority to restructure certain aspects of its organization. It subsequently moved to withdraw its application. The Commission partially granted the motion to withdraw, but leave to dismiss the case in its entirety was denied. The case was retitled NMPSC Case No. 2146, Part II, and the scope of the hearing was redefined to be a consideration of alternatives to the inventory ratemaking methodology and of problems relating to the phasing in of PNM’s excess generating capacity. Before this case commenced, the Commission docketed NMPSC Case No. 2087 (prudence case) to consider the prudence of PNM investment in the Palo Verde Nuclear Generating Station (PVNGS), the hearing on which was pending at the time of appeal. Subsequent to the filing of this case, NMPSC Case No. 2262 (rate case) was filed. The final order in this case in essence framed the issues to be considered in the rate case, which will determine the rates PNM may recover for its investment in PVNGS and other facets of the utility system. 1 The rate case includes the determination of how generating capacity will be phased into use and rates, or, as expressed by the Commission, “the extent to which it recovers a return of (capital) and on (profit) its investment.”

The Final Order, 101 Pub.Util.Rep. (PUR) 4th at 131-40, summarizes the factual background and discusses the procedural history of this case. For the purposes of this appeal, it is sufficient to understand that PNM over the last several decades had invested in excess generating capacity, including portions of PVNGS. The Commission initially had addressed this problem through inventory ratemaking, see New Mexico Indus. Energy Consumers v. New Mexico Pub. Serv. Comm’n, 104 N.M. 565, 725 P. 2d 244 (1986), which allowed PNM to accrue carrying costs for its investment in capacity not yet needed by energy consumers. That stop-gap solution proved to be ineffective, leading the Commission to consider the problem anew.

This proceeding considered treatment of other capacity in addition to three units of PVNGS. This capacity includes: San Juan Unit 4 (SJ-4), the Southwestern Public Service Company (SPS) contract to supply power to PNM, the Los Alamos County (LAC) contract, and the Modesto, Santa Clara and Redding (M-S-R) 2 contract whereby M-S-R exercised its option to purchase 28.8 percent of SJ-4 in 1983, with PNM repurchasing 105 megawatts (MW) through 1995.

The final order terminated the Commission’s inventory stipulation effective upon resolution of the rate case. The Commission determined that PNM could not recover its entire investment in all three units of PVNGS, excluding Unit 3 from rate base, and requested PNM to submit proposals for decertification and abandonment. The M-S-R contract was permanently excluded; 130 MW of SJ-4 were excluded from base rates until it is no longer a part of excess capacity; PVNGS Units 1 and 2 were included with the precise rate treatment reserved for the rate case subject to the prudence hearings; 147 MW of SJ-4, the SPS contract and the LAC contract all were included in rates. Final Order, 101 Pub. Util.Rep. (PUR) 4th at 181-82.

The attorney general and New Mexico Industrial Energy Consumers (NMIEC) appeal from the final order. PNM has not appealed and along with the Commission has filed a brief in support of the order.

Appellants have raised many issues, claiming that aspects of the final order were not supported by substantial evidence, were arbitrary and capricious, exceeded the jurisdiction of the Commission, or violated the constitution. The attorney general claims that the Commission’s determination that total exclusion of PVNGS would be unfair to the shareholders in PNM is unsupported by substantial evidence and is arbitrary and capricious and that the Commission’s justifications for rejecting total exclusion of PVNGS were not supported by substantial evidence. NMIEC reiterates several of the attorney general’s points and, in addition, argues that, in violation of state and federal statutory and constitutional mandates, the Commission exceeded its jurisdiction by removing power purchased from M-S-R from rate base. NMIEC additionally asserts that the Commission acted arbitrarily and capriciously, and without support of substantia] evidence in adopting the mix of generating plants to be placed in rate base.

“This Court’s role in reviewing orders of an administrative agency is to ensure that the order is neither arbitrary nor capricious, that the order is supported by substantial evidence, and that the order is within the agency’s scope of authority.” Public Serv. Co. v. New Mexico Pub. Serv. Comm ’n, 106 N.M. 622, 626, 747 P.2d 917, 921 (1987). In order to fulfill our role, the issues also must be ripe for judicial review, with a final resolution of the relevant issues by the agency and with a concrete, developed factual record. See Abbott Laboratories v. Gardner, 387 U.S. 136, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967); Midwestern Gas Transmission Co. v. FERC, 589 F.2d 603, 617-18 (D.C.Cir.1978).

I. DOES THE FINAL ORDER EXCEED THE COMMISSION’S JURISDICTION, VIOLATE THE SUPREMACY CLAUSE, OR VIOLATE THE COMMERCE CLAUSE?

NMIEC presents three issues regarding the scope of the Commission’s ability to act. It argues that the Commission exceeded its jurisdiction granted by the New Mexico Public Utility Act, NMSA 1978, Section 62-6-4(B) (Repl.Pamp.1984), by excluding the M-S-R contract from rates. Should we find that the legislature intended to grant the Commission authority to exclude from rates a wholesale purchase, we are then asked to determine whether this conflicts with the Federal Power Act (FPA), 16 U.S.C. Sections 791a-825r (1988), and therefore violates the Supremacy Clause, U.S. Const, art. VI. If the FPA, however, does not apply to the M-S-R transaction, NMIEC presents us with a Commerce Clause issue, asking us to determine whether the final order unconstitutionally burdens interstate commerce in violation of U.S. Const, art. I, section 8, cl. 3.

Before we address these issues on their merits, it is helpful to consider exactly what the Commission did. As discussed earlier, it excluded the M-S-R contract from PNM’s rates. M-S-R had exercised its option to purchase 28.8 percent of SJ-4 from PNM in 1983; as part of the agreement, PNM bought back 105 MW from M-S-R through 1995. At the hearing, PNM posited that the contract should be excluded from jurisdictional rates, and the Commission agreed, stating:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Las Cruces v. N.M. Pub. Regul. Comm'n
New Mexico Supreme Court, 2025
Lucero v. Core Civic, Inc.
New Mexico Court of Appeals, 2022
Citizens for Fair Rates & the Env't v. NMPRC
New Mexico Supreme Court, 2022
State v. Blanton
New Mexico Court of Appeals, 2021
City of Las Cruces v. N.M. Pub. Regulation Comm'n
2020 NMSC 016 (New Mexico Supreme Court, 2020)
Tunis v. Country Club Estates
New Mexico Court of Appeals, 2019
AFSCME v. Bd. of Cty. Comm'rs of Bernalillo Cty.
2016 NMSC 17 (New Mexico Supreme Court, 2016)
Citizen Action New Mexico v. New Mexico Environment Department
2015 NMCA 058 (New Mexico Court of Appeals, 2015)
Citizen Action N.M. v. N.M. Env't Dep't
New Mexico Court of Appeals, 2015
Carlton v. City of Albuquerque
New Mexico Court of Appeals, 2013
La Mesa Racetrack v. State of NM Racing Comm'n
New Mexico Court of Appeals, 2013
E. Navajo Dine v. Environ. Dep't
New Mexico Court of Appeals, 2013
State v. Ebert
2011 NMCA 098 (New Mexico Court of Appeals, 2011)
El Paso Electric Co. v. New Mexico Public Regulation Commission
2010 NMSC 048 (New Mexico Supreme Court, 2010)
In re Louisiana Energy
New Mexico Court of Appeals, 2010

Cite This Page — Counsel Stack

Bluebook (online)
808 P.2d 592, 111 N.M. 622, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-mexico-industrial-energy-consumers-v-new-mexico-public-service-nm-1991.