New Haven v. Ct Siting Council, No. Cv 02-0513195 S (Aug. 21, 2002)

2002 Conn. Super. Ct. 10678, 33 Conn. L. Rptr. 187
CourtConnecticut Superior Court
DecidedAugust 21, 2002
DocketNos. CV 02-0513195 S, CV02-0513196 S
StatusUnpublished
Cited by2 cases

This text of 2002 Conn. Super. Ct. 10678 (New Haven v. Ct Siting Council, No. Cv 02-0513195 S (Aug. 21, 2002)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Haven v. Ct Siting Council, No. Cv 02-0513195 S (Aug. 21, 2002), 2002 Conn. Super. Ct. 10678, 33 Conn. L. Rptr. 187 (Colo. Ct. App. 2002).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
The plaintiffs, the City of New Haven ("City") and the Attorney General, have each appealed from the final decision of the defendant, Connecticut Siting Council ("Siting Council"), approving the application of the defendant, Cross-Sound Cable Company, LLC ("Cross-Sound"), to install and operate a high voltage direct current submarine electric transmission and fiber optic cable system ("the cable") that would run from New Haven Harbor underneath the Long Island Sound to Brookhaven, New York. For the reasons discussed below, the court dismisses both appeals.

I
The record discloses the following facts. On July 7, 2000, TransEnergie U.S. Ltd. applied to the Siting Council for a certificate of environmental compatibility and public need ("certificate") concerning an electric cable that would run approximately twenty-four miles under the Long Island Sound from New Haven to Brookhaven. (Return of Record ("ROR"), XXXIX, Item 13, Findings of Fact, p. 1 ¶ 1; p. 12 ¶ 58.) See General Statutes § 16-50k (a).1 The Siting Council found that the cable project was "not essential or necessary for the reliability of the electric power supply of the State or for the development of a competitive market for electricity." (ROR, XXXIX, Item 13, Opinion, p. 3.) The Siting Council denied the application without prejudice, concluding that the limited benefits from the project and its effects on CT Page 10679 the natural environment were not balanced and were in conflict with state policy. (ROR, XXXIX, Item 13, Opinion, p. 3; Decision and Order.)

Cross-Sound, a joint venture of TransEnergie and two other corporations; reapplied for a certificate on July 24, 2001. The new application proposed a different route in an attempt to minimize the impact to shellfish resources in New Haven Harbor. At the same time, Cross-Sound filed a petition for a declaratory ruling that no certificate was required for the construction, maintenance, and operation of an electric converter substation located in the City of New Haven. On January 3, 2002, after numerous public hearings involving the plaintiffs as well as intervenors from the General Assembly, the Office of Consumer Counsel, and various interest groups, the Siting Council granted the certificate for the cable. (ROR, XXXIX, Item 1 (Findings of Fact), pp. 1-2 ¶¶ 1-3, 6, 8; Item 3 (Decision and Order).)2 The plaintiffs appeal from this decision. In a separately docketed ruling, the Siting Council decided that the proposed electric substation "would not have a substantial adverse environmental effect" and thus would not require a certificate. (ROR, XXXIX, Item 6.) The plaintiffs have not appealed from this decision.3

II
At the outset, the court must confront several jurisdictional challenges raised by the defendants. The Siting Council initially argues that both appeals are moot. The premise of its argument is that any harm from the cable stems from the installation process, which the Siting Council alleges is essentially complete. Based on the representations of the parties at oral argument, however, the court finds that at this time the installation process is not complete. Further, operation of the cable after it is installed also has environmental consequences. For example, operation of the cable would cause a temperature increase of .2 degrees Fahrenheit at the surface of the seabed. (ROR, Findings of Fact, p. 6 ¶ 27.) While the Siting Council found that this increase is insignificant (ROR, Findings of Fact, p. 6 ¶ 27; p. 21 ¶ 105; XXXIX, Item 2 (Opinion), p. 3), the court cannot say that "a controversy between the parties no longer exists." (Internal quotation marks omitted.) Crest Pontiac Cadillac. Inc. v. Hadley, 239 Conn. 437, 439 n. 3, 685 A.2d 670 (1996). Therefore, the appeals are not moot.

III
Cross-Sound urges the court to conclude that both plaintiffs lack standing to appeal. The court begins with the principle that the right to appeal an administrative decision is created only by statute and a party must exercise that right in strict compliance with the statute in order CT Page 10680 for the court to have jurisdiction. See New England RehabilitationHospital of Hartford, Inc. v. Commission on Hospitals and Health Care,226 Conn. 105, 120, 627 A.2d 1257 (1993). With respect to decisions of the Siting Council, General Statutes § 16-50q provides that "[a]ny party may obtain judicial review of an order issued on an application for a certificate or an amendment of a certificate in accordance with the provisions of section 4-183." Section 4-183 (a), which is part of the Uniform Administrative Procedure Act, General Statutes § 4-166 et seq. ("UAPA"), provides that "[a] person who has exhausted all administrative remedies available within the agency and who is aggrieved by a final decision may appeal to the Superior Court as provided in this section."

Accordingly, in order to have standing to bring an administrative appeal from a decision of the Siting Council under § 4-183 (a), a person or entity must be aggrieved. See Southern New England TelephoneCo. v. Department of Public Utility Control, 64 Conn. App. 134, 139-43,779 A.2d 817 (2001), cert. dismissed, 260 Conn. 180, ___ A.2d ___ (2002) (holding that General Statutes § 16-35, which provides for appeals from the decisions of the department of public utility control "in accordance with the provisions of section 4-183," incorporates the "final decision" component of § 4-183 (a)). See generally New EnglandRehabilitation Hospital of Hartford, Inc. v. Commission on Hospitals andHealth Care, supra, 226 Conn. 120. "Aggrievement is a question of fact for the trial court and the plaintiff has the burden of proving that fact. . . . Pleading and proof of facts that constitute aggrievement are essential prerequisites to the trial court's subject matter jurisdiction over an administrative appeal." (Citation omitted.) Id. Cf. Ganin v.Smith Wesson Corp., 258 Conn. 313, 348, 780 A.2d 98 (2001) ("whether a party has standing, based upon a given set of facts, is a question of law for the court").

Under our law, there is both classical and statutory aggrievement. SeeTerese B. v. Commissioner of Children and Families, 68 Conn. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Not Another Power Plant v. Connecticut Siting Council
340 Conn. 762 (Supreme Court of Connecticut, 2021)
Brouillard v. Connecticut Siting Council
39 A.3d 1241 (Connecticut Superior Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
2002 Conn. Super. Ct. 10678, 33 Conn. L. Rptr. 187, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-haven-v-ct-siting-council-no-cv-02-0513195-s-aug-21-2002-connsuperct-2002.