Not Another Power Plant v. Connecticut Siting Council

340 Conn. 762
CourtSupreme Court of Connecticut
DecidedSeptember 28, 2021
DocketSC20464
StatusPublished
Cited by2 cases

This text of 340 Conn. 762 (Not Another Power Plant v. Connecticut Siting Council) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Not Another Power Plant v. Connecticut Siting Council, 340 Conn. 762 (Colo. 2021).

Opinion

Page 2 CONNECTICUT LAW JOURNAL January 18, 2022

762 JANUARY, 2022 340 Conn. 762 Not Another Power Plant v. Connecticut Siting Council

NOT ANOTHER POWER PLANT v. CONNECTICUT SITING COUNCIL ET AL. (SC 20464) Robinson, C. J., and McDonald, D’Auria, Mullins, Kahn and Ecker, Js.

Syllabus

Pursuant to statute (§ 16-50k (a)), ‘‘no person shall . . . commence the construction or supplying of a facility . . . that may, as determined by the [Connecticut Siting] [C]ouncil, have a substantial adverse environ- mental effect in the state without having first obtained a certificate of environmental compatibility and public need . . . issued with respect to such facility or modification by the council.’’ Pursuant further to statute (§ 16-50p (a) (3) (B)), ‘‘[t]he council shall file, with its order, an opinion stating in full its reasons for the decision. The council shall not grant a certificate, either as proposed or as modified by the council, unless it shall find and determine . . . [t]he nature of the probable environmental impact of the facility alone and cumulatively with other facilities, including a specification of every significant adverse effect . . . .’’ The plaintiff, a nonprofit association formed to promote environmental conservation in the town of Killingly, appealed to the trial court from the decision of the defendant council, which approved the application of the defendant energy company, N Co., for a certificate of environmental compatibility and public need in connection with an electric generating facility that N Co. sought to construct in the town. The plaintiff had intervened in the administrative proceeding pursuant to statute (§ 22a- 19 (a) (1)), claiming that approval of the facility would result in the unreasonable pollution and impairment of the public trust in the environ- ment. According to N Co.’s application, the facility would be supplied with natural gas by E Co., which owns a distribution pipeline that extends from a mainline to the site of the proposed facility. For the facility to function, however, E Co. would need to replace approximately two miles of its existing distribution pipeline with an upgraded pipeline that would cross or abut wetlands, a river, and certain preserved or undeveloped lands. The plaintiff moved to dismiss or to stay N Co.’s application, claiming that the council was required to consider the envi- ronmental impact of the upgraded pipeline when weighing the public benefit of the facility against the harm that it would cause to the environ- ment under § 16-50p (c) (1) of the Public Utility Environmental Standards Act (act) and that N Co. had neither obtained a commitment as to the design of the upgraded pipeline from E Co. nor fully assessed the environmental impact the upgraded pipeline would have. The council denied the plaintiff’s motion and, after hearings, approved N Co.’s appli- January 18, 2022 CONNECTICUT LAW JOURNAL Page 3

340 Conn. 762 JANUARY, 2022 763 Not Another Power Plant v. Connecticut Siting Council cation for a certificate, without ever considering the potential environ- mental effects of the upgraded pipeline. The council found that the facility was necessary for the reliability of the electric power supply of the state and, therefore, would be a public benefit, and that the adverse impacts of the facility were not disproportionate, either alone or cumula- tively, when compared to the public benefit. On appeal to the trial court, the plaintiff claimed that the council had improperly segmented the project into two components, namely, N Co.’s electric generating facility and E Co.’s upgraded pipeline, to avoid a comprehensive review of the project’s overall environmental impact. After rejecting N Co.’s special defense that the plaintiff lacked standing to appeal, the trial court con- cluded that, although the facility was intertwined with the upgraded pipeline insofar as the facility, as planned, could not operate without it, the council reasonably decided to consider them separately because, under the act, electric generating facilities and fuel transmission lines are separate facilities to be considered under different provisions and submitted by two unrelated parties. The court also observed that E Co. would need to apply for a certificate of environmental compatibility and public need under § 16-50k (a) to construct the upgraded pipeline and stated that it would consider the pipeline’s environmental impact at that time. Further, the trial court concluded that the plaintiff had neither pointed to any environmental concerns with the facility itself nor claimed that combining the environmental impact of the facility with that of the upgraded pipeline would result in an increased environmental impact. Accordingly, the trial court rejected the plaintiff’s improper segmentation claim, concluded that the plaintiff failed to establish that the council had improperly approved N Co.’s application, and rendered judgment dismissing the plaintiff’s administrative appeal. On the plain- tiff’s appeal, held: 1. The trial court correctly concluded that the plaintiff had standing to appeal under § 22a-19 (a) (1) from the council’s decision, the plaintiff having asserted a colorable claim of potential impairment of or destruc- tion to the environment by alleging in its complaint that the council’s improper segmentation of the project into two separate components, in order to avoid a comprehensive review of the project’s overall impact, would result in a substantial likelihood of such impairment or destruction. 2. The plaintiff could not prevail on its claim that the trial court incorrectly determined that the council’s failure to consider the environmental impact of E Co.’s future, upgraded pipeline when weighing the public benefit of the electric generating facility against the harm that it would cause to the environment was not arbitrary and capricious: a. Contrary to the council’s claim, the plaintiff did not waive its claim regarding the council’s refusal to consider the environmental impact of the upgraded pipeline by failing to challenge the council’s finding that the facility would provide a public benefit in the trial court; the very Page 4 CONNECTICUT LAW JOURNAL January 18, 2022

764 JANUARY, 2022 340 Conn. 762 Not Another Power Plant v. Connecticut Siting Council reason that the plaintiff argued that the council was required to consider the impact of the upgraded pipeline was that, if it had done so, it might have concluded that the adverse environmental impact of the facility and the upgraded pipeline together outweighed the public benefit, and the plaintiff’s counsel expressly raised that argument in the trial court. b.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Commissioner of Correction
345 Conn. 1 (Supreme Court of Connecticut, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
340 Conn. 762, Counsel Stack Legal Research, https://law.counselstack.com/opinion/not-another-power-plant-v-connecticut-siting-council-conn-2021.