Nelson v. Heine Boiler Co.

20 S.W.2d 906, 323 Mo. 826, 1929 Mo. LEXIS 522
CourtSupreme Court of Missouri
DecidedSeptember 13, 1929
StatusPublished
Cited by7 cases

This text of 20 S.W.2d 906 (Nelson v. Heine Boiler Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nelson v. Heine Boiler Co., 20 S.W.2d 906, 323 Mo. 826, 1929 Mo. LEXIS 522 (Mo. 1929).

Opinion

*831 ATWOOD, P. J.

This is an action to recover damages for personal injuries alleged to have been sustained by plaintiff on September 30, 1924, while in the employ of defendant. From a judgment in favor of plaintiff for $15,000 defendant has appealed.

Plaintiff went to trial on his second amended petition which alleged negligence on the part of defendant in the following particulars: (1) that defendant caused a piece of sheet iron to be moved at a time when plaintiff was in a position of danger and defendant knew or should have known that in thus causing the iron to be moved plaintiff was likely to be struck and injured thereby ; (2) that defendant negligently moved said iron without allowing plaintiff reasonably sufficient time to reach a place of safety; (3) that defendant negligently failed to furnish plaintiff a reasonably safe place in which to work in that plaintiff’s place of work was insufficient, narrow and crowded; and (4) that defendant did negligently so attach the sheet iron to the chain by which it was to be moved by an overhead crane that the said sheet iron was likely to strike plaintiff if moved, because said chain was twisted so as to cause the sheet iron to swing toward plaintiff and plaintiff’s safety was thereby endangered, and the manner of doing said work was unsafe and dangerous. As the alleged result of the aforesaid negligence it is charged that the sheet iron when moved did come in eon- *832 tact with and strike plaintiff, inflicting serious and permanent injuries to his back, spine, vertebrae and sacral joints.

Defendant’s answer consisted of a general denial and of affirmative allegations to the effect that whatever injuries, if any, were sustained by plaintiff were produced by the usual and ordinary risks incident to his employment, which he knew or should have known and which risks he assumed. Plaintiff’s reply was a general denial.

Plaintiff’s evidence shows that he was about forty years old when he was injured and for about two years prior to the date of his injury he had been working for defendant as a member of a laboring gang earning $24.90 a week. In addition to plaintiff this group of laborers consisted of Jake King, Charles Leffler, two foreigners called Matt and Julius, and a crane operator. King was the foreman and directed the other men in their work. On the day plaintiff was injured these men were engaged in moving sheet iron from the sheet iron shop to the boiler shop of defendant’s building, a task which thejr had performed on previous occasions. The sheets of iron were eight feet wide, twelve feet long, one-fourth of an inch thick, and weighed about 500 pounds. The long sides extended from east to west, the west end being about four feet above the floor on a platform, and the east end being on the floor. The iron was moved by an electric crane with a ball-bearing arrangement at the top to permit turning. The method employed for attaching the sheet iron to the crane was to place one shoe on the north and another on the south side of the iron near the middle to keep it from slipping, and then hook heavy chains attached to the crane onto these shoes. The middle of the iron on this occasion was about five feet west of the chains as they hung straight down from the crane. Plaintiff and one helper were stationed on the south side of the sheet of iron to attach the shoe and chain, while Leffler and another helper were on the other side, assigned to a similar duty. The foreman, King, was eight or ten feet east of the iron in a position to give signals to the crane man, who was seated thirty feet in the air directly above, the iron. The signal consisted of raising the arm above the head. South of the sheet of iron and to the east of plaintiff was an iron column fourteen inches wide. Immediately west of this was an aisle about two feet wide leading to the south, and west of the aisle and about two feet south of where plaintiff was standing was a pile of angle pieces. When the sheet iron was lifted from the floor the west end swung to the south hitting plaintiff in the small of the back on the right side, pressing him against the north side of the iron column. Plaintiff further testified that he put on one shoe and Lef-fler put on the other, and when King went to give the signal plaintiff said: “Wait; -Jake, the chain is twisted;” that King then said, *833 “All right, go ahead;” that he then swerved southeast toward the aisle to get out of the way, but was struck by the west end of the iron before he could get behind the column; that the chain was twisted on the north side, making it shorter and causing the iron to swing around south; that there was nothing to obstruct the view between King and himself. On cross-examination he said that the operation of the derrick was all right; that Leffler attached the shoe to the north side, and either Leffler or his helper pulled the chain over and hooked it on; that the crane had a third_ chain which was used in other work; that the east end of the post and the east end of the iron were about opposite each other with a space of about two feet between; that he was standing about three and a half feet west of the column; that he first noticed the twist of chain as King went to give the signal, that is, when he got his hand partly up; that the metal had not then begun to move; that the crane man was not near enough to hear what plaintiff said, but that King and Leffler could have heard him; that King, when he said, “All right, go ahead,” was looking at plaintiff and was talking to him; that this crane man saw the chains; that it was twisted so one twirl could have taken the twist out; that the metal hit on one else; that he turned to get away and was caught between the iron and the north side of the column while facing southeast, and that he had not come in contact with the post until he was struck and forced against it by the west end of the iron; that he had never previously complained of pains in his back while at work; had never previously experienced such pains, and had not asked to be relieved of any tasks.

Jake King, the foreman, testifying for defendant, said that the east end of the sheet was about three and one-half feet east of the east end of the column; that the column was two feet south of the iron; that there wa£ an open four-foot passage way west of the column, and that plaintiff was standing about the middle of the sheet in line with the edge of the aisle; that he was close enough to plaintiff to converse with him, but did not hear him say anything, nor did he say anything himself; that he did not pause at any time in giving his signal; that the only effect a twist in a chain would lie to cause one side of the chain to be slightly higher than the other. His version of the occurrence was that the sheet iron slid eastward and the northeast corner caught on a water leg, causing the west end to swing' south and strike plaintiff; that the other man on the south side was in the passageway west of the column and out of the way, but plaintiff tried to stop the movement of the sheet iron toward him and tried to step aside too late; that plaintiff had complained of pains in his back before this date and other men had relieved him of work. On cross-examination King admitted that a *834

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tile-Craft Products Co. v. Colonial Properties, Inc.
498 S.W.2d 547 (Supreme Court of Missouri, 1973)
Hancock v. Crouch
267 S.W.2d 36 (Missouri Court of Appeals, 1954)
Riley v. St. Louis Public Service Co.
245 S.W.2d 666 (Missouri Court of Appeals, 1952)
Davis v. F. M. Stamper Co.
148 S.W.2d 765 (Supreme Court of Missouri, 1941)
State Ex Rel. S. S. Kresge Co. v. Shain
101 S.W.2d 14 (Supreme Court of Missouri, 1936)
Kelso v. W. A. Ross Construction Co.
85 S.W.2d 527 (Supreme Court of Missouri, 1935)
Marlow v. Nafziger Baking Co.
63 S.W.2d 115 (Supreme Court of Missouri, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
20 S.W.2d 906, 323 Mo. 826, 1929 Mo. LEXIS 522, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nelson-v-heine-boiler-co-mo-1929.