Neiditz v. Morton S. Fine & Associates, Inc.

479 A.2d 249, 2 Conn. App. 322, 1984 Conn. App. LEXIS 657
CourtConnecticut Appellate Court
DecidedFebruary 29, 1984
Docket(2275)
StatusPublished
Cited by19 cases

This text of 479 A.2d 249 (Neiditz v. Morton S. Fine & Associates, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neiditz v. Morton S. Fine & Associates, Inc., 479 A.2d 249, 2 Conn. App. 322, 1984 Conn. App. LEXIS 657 (Colo. Ct. App. 1984).

Opinion

Dupont, J.

The plaintiffs 1 seek the recovery from the defendant, a professional corporation engaged in the *324 business of land surveying and civil engineering, of damages for the alleged negligent preparation of a boundary survey of the plaintiffs’ land. The plaintiffs allege that errors in a site plan, which delineated the boundaries, courses and dimensions of their land and which had been prepared by the defendant for submission to the town of West Hartford in connection with an application for a zone change, resulted in economic loss to them. A state referee, Hon. Alva P. Loiselle, sitting as the trial court, awarded damages to the plaintiffs for the increased costs of developing their realty which it found were causally connected to the errors in the site plan 2 and awarded statutory interest at the rate of 8 percent from June 11, 1973. From this judgment, the defendant appeals. 3

The defendant, on appeal, claims that the trial court erred (1) in finding the defendant negligent without expert testimony as to its standard of care and in finding negligence in the performance of a 1972 contract; (2) in awarding some damages without evidence that *325 they were actually incurred by the plaintiffs; (3) in awarding property taxes as damages; (4) in awarding damages arising out of conditions imposed on the approval of the plaintiffs’ second application for a zone change; and (5) in awarding interest. 4 The defendant also claims that it has been denied a full and fair review of its appeal because two of its trial exhibits have been lost. 5

The trial court found the following: the site plan prepared by the defendant and dated March 21,1972, contained the words “Note - Boundary Based on Field Survey of Morton S. Fine & Assoc. August, 1955”; the site plan was in error; a new site plan was prepared by the defendant correcting the error after the town of West Hartford deemed the error to be a material one requiring a second application for a zone change; the approval of the second application was based upon compliance with eight conditions; an appeal was taken from the second application, and dismissed; the defendant did field work at the premises; the parties did not agree that the defendant was to perform particular services but that the defendant was engaged in 1972 to depict, describe and locate the boundaries of the realty; and the defendant was negligent in 1972 in its depiction of the plaintiffs’ land on its survey. The trial court *326 further found that the plaintiffs informed the defendant in 1972 that a site plan was needed for an application for a zone change, and that the defendant’s principal stockholder had been a member of the planning and zoning commission of West Hartford and was familiar with the requirements of applications for such zone changes.

The defendant argues that it did not contract with the plaintiffs in 1972 to perform a boundary survey but contracted, instead, to perform the minimum work necessary to comply with the town’s regulations for a zone change application. The defendant’s claim is that it did not contract to do any topographic or field work for the plaintiffs in February of 1972 and, therefore, it could not have been negligent in the preparation of its site plan of March, 1972. The defendant argues, in essence, that whatever error was found on that plan originated in 1955 when the defendant originally contracted with the plaintiffs to prepare a boundary plot of the land. The plaintiffs, however, do not claim that the defendant was negligent in 1955 but, rather, that it was negligent in the preparation of the 1972 site plan. 6 The trial court made specific findings that the parties entered into a contract in 1972, and that the defendant’s negligence occurred in 1972 when it prepared the site plan and certified it as being substantially correct based on a field survey. The trial court also found that the defendant knew or should have known that an exterior angle had not been checked, either by reference to an existing deed or in the field, *327 and that the defendant knew that the site plan was requested for use in an application for a zone change. The facts found are supported by the evidence and are not clearly erroneous. Pandolphe’s Auto Parts, Inc. v. Manchester, 181 Conn. 217, 221-22, 435 A.2d 24 (1980). On such facts, no statute of limitations barred suit by the plaintiffs. See General Statutes § 52-577.

The defendant claims that the court could not find the defendant negligent in 1972 because no expert testimony was produced as to the standard of care required in the preparation of the 1972 map. An expert witness for the plaintiffs did testify, however, that in his opinion a land surveyor acting as such in 1972 would not be in conformity with the standard of due care for registered land surveyors in Connecticut if he did not go into the field but, nevertheless, prepared the site plan in question. Although the defendant produced other experts who testified that the work of the defendant in 1972 did conform to the standard of care required of land surveyors in Connecticut, it was for the trier to determine the credence to be given to the testimony of the various experts, in view of the other evidence proffered by the parties. Bond v. Benning, 175 Conn. 308, 313, 398 A.2d 1158 (1978).

The remaining claims of error relate to the damages found by the trier to be due, and to the interest awarded on the judgment. The general rule for the measure of damages is that the damages are to equate that monetary amount which will place the injured party in the same position it would have been in had the defendant not breached its contract. Danpar Associates v. Somersville Mills Sales Room, Inc., 182 Conn. 444, 446, 438 A.2d 708 (1980). Eight conditions were imposed by West Hartford in order for the plaintiffs to obtain the zone change. These conditions were not required when the first application for a zone change was granted and are causally connected to the negligence *328 of the defendant. 7 But for the defendant’s negligence, the plaintiffs would not have had to comply with the conditions. One of the plaintiffs was obliged to give a surety bond to the town in order to guaranty the implementation of some of the conditions. These conditions mandated the construction of a traffic lane, a sewer line, and sidewalks. Although not all of the work and expense incident to such construction had been completed and paid at the time of trial, the plaintiffs were bound by the surety bond to complete the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moss v. Foster
900 A.2d 548 (Connecticut Appellate Court, 2006)
Lisiewski v. Seidel
899 A.2d 59 (Connecticut Appellate Court, 2006)
Advanced Financial v. Associated Appr., No. Cv 98-0580372 (Jul. 23, 2001)
2001 Conn. Super. Ct. 9949 (Connecticut Superior Court, 2001)
State v. Admin. Residual Emp. Union, No. Cv 96 056 58 03 (Jun. 5, 1998)
1998 Conn. Super. Ct. 7137 (Connecticut Superior Court, 1998)
Foley v. Huntington Co.
682 A.2d 1026 (Connecticut Appellate Court, 1996)
Sears, Roebuck Co. v. Board of Tax Review, No. 381310 (Apr. 9, 1996)
1996 Conn. Super. Ct. 2851-AA (Connecticut Superior Court, 1996)
Ted Rosick Construction v. Rjb Contracting, Inc., No. 381108 (Feb. 29, 1996)
1996 Conn. Super. Ct. 1353 (Connecticut Superior Court, 1996)
Solomon v. Wmn Associates, Inc., No. 391793 (Oct. 21, 1994)
1994 Conn. Super. Ct. 10731 (Connecticut Superior Court, 1994)
Barry v. Posi-Seal International, Inc.
647 A.2d 1031 (Connecticut Appellate Court, 1994)
Federal Deposit Ins. Corp. v. Stevens, No. Cv91-0502379 (Apr. 23, 1993)
1993 Conn. Super. Ct. 4149 (Connecticut Superior Court, 1993)
Wilcox Trucking v. First Hartford Realty, No. 366925 (Nov. 23, 1992)
1992 Conn. Super. Ct. 10510 (Connecticut Superior Court, 1992)
Pergament v. Green, No. Cv86 0084907 S (Jun. 12, 1992)
1992 Conn. Super. Ct. 5875 (Connecticut Superior Court, 1992)
Galazan v. Connecticut Housing Fin., No. Cv91 050 39 51 (Jun. 12, 1992)
1992 Conn. Super. Ct. 5854 (Connecticut Superior Court, 1992)
Prishwalko v. Schaefer Insp. Serv., No. 286826. (Jan. 31, 1991)
1991 Conn. Super. Ct. 270 (Connecticut Superior Court, 1991)
Hart, Nininger & Campbell Associates v. Rogers
548 A.2d 758 (Connecticut Appellate Court, 1988)
Simonetti v. Lovermi
546 A.2d 331 (Connecticut Appellate Court, 1988)
Neiditz v. Morton S. Fine & Associates, Inc.
483 A.2d 1098 (Supreme Court of Connecticut, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
479 A.2d 249, 2 Conn. App. 322, 1984 Conn. App. LEXIS 657, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neiditz-v-morton-s-fine-associates-inc-connappct-1984.