Ted Rosick Construction v. Rjb Contracting, Inc., No. 381108 (Feb. 29, 1996)

1996 Conn. Super. Ct. 1353, 16 Conn. L. Rptr. 239
CourtConnecticut Superior Court
DecidedFebruary 28, 1996
DocketNo. 381108
StatusUnpublished

This text of 1996 Conn. Super. Ct. 1353 (Ted Rosick Construction v. Rjb Contracting, Inc., No. 381108 (Feb. 29, 1996)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ted Rosick Construction v. Rjb Contracting, Inc., No. 381108 (Feb. 29, 1996), 1996 Conn. Super. Ct. 1353, 16 Conn. L. Rptr. 239 (Colo. Ct. App. 1996).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION The present action arises out of a dispute between Ted Rosick Construction (Ted Rosick) and RJB Contracting, Inc. (RJB) regarding their rights and liabilities under a construction contract. The parties agreed in writing to submit their dispute to arbitration. On November 14, 1995, upon the completion of the arbitration hearings, the arbitrator, taking into account all credits and "extras," rendered an award in favor of Ted Rosick for the sum of $24,117.40 plus 10% interest, pursuant to General Statutes § 37-3a, from November 4, 1993, to the date of payment.

On November 27, 1995, the claimant, Ted Rosick, filed an application to confirm the arbitration award pursuant to General Statutes § 52-417. Thereafter, on December 14, 1995, the respondent, RJB, filed an application to correct and/or modify the arbitration award pursuant to General Statutes § 52-419 on the ground that the arbitrator's award of prejudgment interest was beyond the scope of the submission of the parties. The claimant then filed an objection to the respondent's motion on December 18, 1995, along with a memorandum of law in support of the claimant's motion to confirm.

The issue presented by the present applications is whether the arbitrator's award of prejudgment interest pursuant to General Statutes § 37-3a was beyond the scope of the submission of the parties. RJB essentially argues that the arbitrator improperly awarded statutory interest in this matter and that the award must be corrected and/or modified, pursuant to General Statutes §52-4191, to exclude interest as an element of damages.

The scope of judicial review of an arbitration award is limited. "[W]hen arbitration is consensual, rather than CT Page 1353-A statutorily imposed, judicial review is limited in scope. . . . [T]he resulting award is not reviewable for errors of law or fact. . . . Judicial review of unrestricted submissions is limited to a comparison between the submission and the award to see whether . . . their award conforms to the submission." (Internal quotation marks omitted.) Bodner v. United Services Automobile Assn., 222 Conn. 480,487-88, 610 A.2d 1212 (1992). "Every reasonable presumption and intendment will be made in favor of the award and of the arbitrator's acts and proceedings. Hence, the burden rests on the party challenging the award to produce evidence sufficient to show that it does not conform to the submission." (Internal quotation marks omitted.) Board of Education v. Waterbury Teachers Assn.,216 Conn. 612, 618, 583 A.2d 626 (1990).

"Unless the submission provides otherwise, an arbitrator has authority to decide factual and legal questions, and courts will not review the evidence, or, where the submission is unrestricted, the arbitrator's determination of legal questions." O G/O'ConnellJoint Venture v. Chase Family Ltd. Partnership No. 3, 203 Conn. 133,153-54, 523 A.2d 1271 (1987). "The authority of an arbitrator to adjudicate the controversy is limited only if the agreement contains express language restricting the breadth of issues, reserving explicit rights, or conditioning the award on court review. In the absence of any such qualifications, an agreement is unrestricted." Garrity v. McCaskey, 223 Conn. 1, 5, 612 A.2d 742 (1992).

The agreement in the present case provides that the parties "hereby agree to submit these issues between them arising out of contract entitled Purchase Order #2226 dated July 9, 1993 to the honorable Edward Fitzpatrick, arbitrator." (Claimant's Application to Confirm Arbitration Award, Exhibit B, Agreement.) The parties agreed to the following relevant issues in their submission: "What sums are due Ted Rosick Construction from RJB Contracting, Inc.; What credits are due to RJB Contracting, Inc. from Ted Rosick Construction." (Claimant's Application to Confirm Arbitration Award, Exhibit B, Submission.) In the absence of any such qualifications in the agreement or the submission, the court finds that the parties' submission in the present case is unrestricted.

Following the arbitration hearings, the arbitrator concluded that Ted Rosick's damages, taking into account all credits to RJB and all "extras" to which Ted Rosick was entitled, totaled "$24,117.40 plus 10% interest pursuant to Section 37-3a of the General Statutes from November 4, 1993 to the date of payment." CT Page 1353-B (Claimant's Application to Confirm Arbitration Award, Exhibit A, Finding and Award, p. 6.) "Whether or not an award conforms to the submission is an inquiry which asks simply whether or not the arbitrator has answered the questions lawfully put to him. If he answers those questions and no others, then his award conforms to the submission." Metropolitan Dist. Comm. v. American Fed'n, Superior Court, judicial district of Hartford-New Britain at Hartford, Docket No. 704644 (June 8, 1995, Sheldon, J.). the arbitrator's award in the present case answers the question presented by the parties' submission and therefore conforms to the submission. An award of interest simply recognizes the fact that "[m]oney awarded at a later time, in some financial climates, is worth less than if it had been paid when due." Neiditz v. Morton S.Fine Associates, Inc., 2 Conn. App. 322, 331, 479 A.2d 249 (1984), modified, 199 Conn. 683, 508 A.2d 438 (1986). "Since the award conforms to the submission, the defendants' claim that the arbitrators exceeded their powers is without merit." O G/O'ConnellJoint Venture v. Chase Family Ltd. Partnership No. 3, supra, 203 Conn. 154.

Under Connecticut law, "interest at a rate of ten per cent a year, and no more, may be recovered and allowed in civil action and arbitration proceedings under chapter 909 . . . as damages for the detention of money after it becomes payable." General Statutes § 37-3a; Middlesex Mutual Assurance Co. v. Walsh, 218 Conn. 681,701, 590 A.2d 957 (1991).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Neiditz v. Morton S. Fine & Associates, Inc.
479 A.2d 249 (Connecticut Appellate Court, 1984)
Neiditz v. Morton S. Fine & Associates, Inc.
508 A.2d 438 (Supreme Court of Connecticut, 1986)
O & G/O'Connell Joint Venture v. Chase Family Ltd. Partnership No. 3
523 A.2d 1271 (Supreme Court of Connecticut, 1987)
Board of Education of Waterbury v. Waterbury Teachers Ass'n
583 A.2d 626 (Supreme Court of Connecticut, 1990)
Middlesex Mutual Assurance Co. v. Walsh
590 A.2d 957 (Supreme Court of Connecticut, 1991)
Bodner v. United Services Automobile Ass'n
610 A.2d 1212 (Supreme Court of Connecticut, 1992)
Garrity v. McCaskey
612 A.2d 742 (Supreme Court of Connecticut, 1992)
Stephan v. Pennsylvania General Insurance
621 A.2d 258 (Supreme Court of Connecticut, 1993)
City of Hartford v. IAFF, Local 760
587 A.2d 435 (Connecticut Appellate Court, 1991)
Solomon v. Hall-Brooke Foundation, Inc.
619 A.2d 866 (Connecticut Appellate Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
1996 Conn. Super. Ct. 1353, 16 Conn. L. Rptr. 239, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ted-rosick-construction-v-rjb-contracting-inc-no-381108-feb-29-connsuperct-1996.