Natural Resources Defense Council v. U.S. Nuclear Regulatory Commission

823 F.3d 641, 422 U.S. App. D.C. 325, 46 Envtl. L. Rep. (Envtl. Law Inst.) 20082, 2016 U.S. App. LEXIS 7484
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 26, 2016
Docket14-1225
StatusPublished
Cited by8 cases

This text of 823 F.3d 641 (Natural Resources Defense Council v. U.S. Nuclear Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Natural Resources Defense Council v. U.S. Nuclear Regulatory Commission, 823 F.3d 641, 422 U.S. App. D.C. 325, 46 Envtl. L. Rep. (Envtl. Law Inst.) 20082, 2016 U.S. App. LEXIS 7484 (D.C. Cir. 2016).

Opinion

Opinion for the Court filed by Circuit Judge BROWN.

BROWN, Circuit Judge:

National Resources Defense Council (NRDC) challenges the Nuclear Regulatory Commission’s (NRC’s) denial of NRDC’s request for a hearing and subsequent application for a waiver, asserting this process was inconsistent with the procedural rigor mandated by the National Environmental Policy Act (NEPA). The denial thwarted NRDC’s attempt to intervene in the license renewal proceeding for Exelon’s Limerick nuclear power station in Pennsylvania. NRDC sought to present “new and significant” information regarding severe accident mitigation alternatives (SAMAs) relevant to Limerick. We find the Commission reasonably concluded NRDC’s request to intervene was a challenge to a general rule — 10 C.F.R. § 51.53(c)(3)(ii)(L) (Rule (L)) — improperly raised in an individual adjudication; and, contrary to NRDC’s view, while NEPA requires agencies to take a hard look before approving a major federal action, it does not mandate adoption of a particular process for doing so. Having failed to show its contentions were unique to Limerick, NRDC also was not entitled to a waiver. We conclude the Commission’s actions were not arbitrary and capricious and deny the petition.

*643 I.

The Atomic Energy Act (AEA) empowers the Commission to issue and renew nuclear power plant licenses. See 42 U.S.C. § 2133. The Act limits initial licenses to a forty-year term but otherwise grants the Commission wide authority to regulate the license issuance and renewal process. See id. at § 2133(c). In 10 C.F.R. Part 54, the Commission laid out the general framework for renewal. The Commission also promulgated 10 C.F.R. Part 51 to deal with its obligations under NEPA. NEPA requires preparation of an Environmental Impact Statement (EIS) before undertaking any “major Federal action[ ] significantly affecting the quality of the human environment.” 42 U.S.C. § 4332(2)(C); see also New York v. NRC, 681 F.3d 471, 476 (D.C.Cir.2012). This requirement ensures each agency “consider[s] every significant aspect of the environmental impact of a proposed action” and “inform[s] the public that it has indeed considered environmental concerns in its decisionmaking process.” Balt. Gas & Elec. Co. v. NRDC, 462 U.S. 87, 97, 103 S.Ct. 2246, 76 L.Ed.2d 437 (1983). The issuance or renewal of a nuclear power plant license qualifies as a “major federal action” triggering the Commission’s obligations under NEPA. See New York, 681 F.3d at 476.

The AEA also provides that “the Commission shall grant a hearing upon the request of any person whose, interest may be affected by the proceeding.” 42 U.S.C. § 2239(a)(1)(A). In 10 C.F.R. § 2.309, the Commission laid out the specific procedures an intervening party must follow. The interested party must file a written request listing the specific contentions the party seeks to litigate. See id. at § 2.309(a), (f)(1). If a party’s contentions do not meet the Commission’s specificity or relevancy requirements, the agency may deny the hearing request. See id. Finally, the AEA subjects all final Commission orders to judicial review. 42 U.S.C. § 2239(b). “Any party aggrieved” by a final order of the Commission may “file a petition to review the order in the court of appeals.” 28 U.S.C. § 2344. This court has “routinely interpreted [the phrase ‘any party aggrieved’] to allow petitions by parties who were intervenors before the Commission.” State of Alaska v. FERC, 980 F.2d 761, 763 (D.C.Cir.1992). To challenge the Commission’s grant of a license renewal, then, a party must have successfully intervened in the proceeding by submitting adequate contentions under 10 C.F.R. § 2.309.

II.

NRDC here sought to intervene in the-relicensing of Exelon’s Limerick power station. To understand how this relicens-ing process works, a brief history of the power plant at issue is helpful. The Limerick Generating Station is a dual-unit nuclear power plant with two boiling water reactors located in Limerick Township, Pennsylvania, approximately 35 miles outside of Philadelphia. The Commission first licensed Limerick in 1984 after conducting ninety-five days of hearings and “generating a 20,000-page transcript.” Limerick Ecology Action, Inc. v. NRC, 869 F.2d 719, 728 (3d Cir.1989). Various environmental petitioners challenged NRC’s grant of a full power license to Limerick, alleging the Commission failed to adequately consider several environmentally relevant factors in violation of NEPA. Specifically, petitioners contended the Commission improperly declined • to consider severe accident mitigation design alternatives (SAMDAs) 1 on the basis of the Agen *644 cy’s policy statement that read: “[NRC will] exclude consideration of design alternatives as a matter of Commission policy while research into design alternatives [is] ongoing.” Id. at 734. SAMDAs are defined as “possible plant design modifications that are intended not to prevent an accident, but to lessen the severity of the impact of an accident should one occur.” Id. at 731.

The Third Circuit held NEC’s policy statement — unlike a notice-and-comment rulemaking — was not entitled to deference. See id. at 729-31. Moreover, the court rejected NRC’s Final Environmental Impact Statement (FEIS) for Limerick as inadequate under NEPA because it did not include “the requisite careful consideration of the environmental consequences [of SAMDAs].” Id. at 723. But the court did not foreclose the possibility that SAMDAs could be dealt with “generically” through a subsequent rulemaking. 2 See id. (“Although NEPA requires the Commission to undertake ‘careful consideration’ of environmental consequences, ... it may issue a rulemaking to address and evaluate environmental impacts that are ‘generic,’ i.e.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
823 F.3d 641, 422 U.S. App. D.C. 325, 46 Envtl. L. Rep. (Envtl. Law Inst.) 20082, 2016 U.S. App. LEXIS 7484, Counsel Stack Legal Research, https://law.counselstack.com/opinion/natural-resources-defense-council-v-us-nuclear-regulatory-commission-cadc-2016.