Nationwide Roofing & Sheet Metal Co. v. United States

34 Cont. Cas. Fed. 75,491, 14 Cl. Ct. 733, 1988 U.S. Claims LEXIS 83, 1988 WL 45950
CourtUnited States Court of Claims
DecidedMay 13, 1988
DocketNo. 187-87C
StatusPublished
Cited by7 cases

This text of 34 Cont. Cas. Fed. 75,491 (Nationwide Roofing & Sheet Metal Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nationwide Roofing & Sheet Metal Co. v. United States, 34 Cont. Cas. Fed. 75,491, 14 Cl. Ct. 733, 1988 U.S. Claims LEXIS 83, 1988 WL 45950 (cc 1988).

Opinion

OPINION

MARGOLIS, Judge.

Plaintiff seeks review of the contracting officer’s decision under the provisions of the Contract Disputes Act of 1978. The defendant moved for partial summary judgment, which plaintiff opposed. After consideration of the entire record and after hearing oral argument, the defendant’s motion for partial summary judgment is granted.

FACTS

On August 9, 1984, the Air Force invited several contractors to bid on certain construction work. The contract involved the repair and replacement of the roof of a building located on the Wright-Patterson Air Force Base. Three bids were submitted in response to the invitation.

The bid submitted by ABCO Roofing & Sheet Metal Company (ABCO) was the lowest bid received. ABCO, however, submitted its required bid bond guarantee on the wrong form. Specifically, ABCO used United States Postal Service (USPS) Bid Bond Form 7324 rather than the General Services Administration (GSA) Standard Form 24 (SF-24) specified in the invitation for bids. The contracting officer initially determined this technical deficiency sufficient to render ABCO’s bid nonresponsive.

On September 28, 1984, the contracting officer signed a determination of nonre-sponsiveness regarding ABCO’s bid. Accordingly, on September 29, 1984, the Air Force awarded contract No. F33601-84-C-0360 to plaintiff Nationwide Roofing and Sheet Metal Co., Inc. (Nationwide), the next lowest bidder. Nationwide’s contract contained provision 1-684, which incorporated the standard Termination for Convenience Clause, FAR 52.249-2 (48 C.F.R. § 52.249-2). On October 2, 1984, ABCO submitted a formal protest of the contracting officer’s nonresponsiveness determination.

While conducting legal research in reviewing ABCO’s protest, the Air Force discovered two General Accounting Office (GAO) bid protest decisions which held that bid bonds with deficiencies similar to those in ABCO’s bid bond do not render the bid nonresponsive. This discovery, defendant argues, rendered the Air Force’s award to Nationwide a violation of the procurement regulations, which require that the contract be awarded to the lowest-priced, responsive bidder. On the basis of these GAO prece[735]*735dents, the Air Force reversed its determination that ABCO’s bid was nonresponsive.

Therefore, to comply with procurement regulations that require a contract be awarded to the lowest responsive bidder, on or about October 11, 1984, the Air Force, pursuant to provision 1-684 of the contract, terminated the award to Nationwide for the convenience of the government. Nationwide then filed a bid protest with the GAO. On April 22, 1985, the Comptroller General issued a decision on Nationwide’s protest upholding the Air Force’s reliance on GAO precedent to establish ABCO’s bid as responsive and upholding the Air Force’s decision to terminate Nationwide’s contract for the convenience of the government.

On October 20, 1986, Nationwide filed a certified claim with the Air Force seeking $107,687.71 for breach of contract damages including attorney’s fees, bid preparation costs, material costs, and anticipatory profits. On December 4, 1986, the contracting officer issued a final decision denying Nationwide’s claim. On April 6, 1987, Nationwide filed this action, seeking to reverse the contracting officer’s final decision to terminate the contract and seeking breach of contract damages.

DISCUSSION

Both parties agree the termination for convenience clause set out at 48 C.F.R. § 52.249-2 is found in provision 1-684 of the contract. Nationwide argues that the Air Force’s termination of its contract constitutes, as a matter of law, a breach of contract. The Air Force counters that it properly terminated Nationwide’s contract pursuant to the standard termination for convenience clause incorporated into the contract and that there was no evidence offered by Nationwide to support its allegations of “bad faith.” In short, the Air Force claims it acted properly under the termination for convenience clause.

The doctrine of termination for convenience enables the government, under certain circumstances, to terminate a contract that is no longer in the government’s interest. See, e.g., United States v. Cor-liss Steam-Engine Co., 91 U.S. (1 Otto) 321, 23 L.Ed. 397 (1876); see also Moss & Gantt, A Steam Engine and Contract Termination Settlement Procedure, 8 Pub. Cont.L.J. 188 (1976). In the instant case, the language giving the Government the right to terminate is brief and very broad:

The Government may terminate performance of work under this contract in whole or, from time to time, in part if the Contracting Officer determines that a termination is in the Government’s interest.

48 C.F.R. 52.249-2 (1984).

While this language is broad, the courts have consistently recognized limitations on the government’s right to invoke this extraordinary doctrine. In Torncello v. United States, 231 Ct.Cl. 20, 681 F.2d 756 (1982), the Court of Claims limited the application of the termination for convenience clause to those instances involving “changed circumstances.” Torncello involved a requirements contract in which the termination for convenience clause was used to take advantage of another firm’s lower price, which the government had known about when awarding the contract to the contractor. The court held for the contractor and went on to state that “the government may not use the standard termination for convenience clause to dishonor, with impunity, its contractual obligations.” Id. at 47, 681 F.2d at 772. The court continued: “We cannot condone termination based on knowledge of a lower cost when that knowledge preceded award of the contract.” Id. at 49, 681 F.2d at 772. The gravamen of the court’s reasoning was that without requiring changed circumstances, the government’s use of the clause was so exculpatory that its contract would fail for lack of consideration. Id. at 44, 681 F.2d at 770.

In setting forth the limits on the use of the termination for convenience clause, the court in Torncello cites with approval a line of cases illustrating the requirement for a change in circumstances or expectations of the parties. Id. at 36-37, 681 F.2d at 766. Among the cases cited are several in which contracting officials believed that [736]*736as a result of a protest subsequent to award of the contract, the award had been improper. Accordingly, the contracting officials took corrective action that the court held entitled the terminated awardee to recover damages based on a termination for convenience. G.C. Casebolt Co. v. United States, 190 Ct.Cl. 783, 786-88, 421 F.2d 710, 712-13 (1970) (holding that a mistaken government directive to cease performance “will not be considered a breach but rather a convenience termination”); Warren Brothers Roads Co. v. United States, 173 Ct.Cl. 714, 722-23, 355 F.2d 612

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bannum, Inc. v. United States
Federal Claims, 2021
Dart Advantage Warehousing, Inc. v. United States
52 Fed. Cl. 694 (Federal Claims, 2002)
Metric Systems Corp. v. United States
42 Cont. Cas. Fed. 77,400 (Federal Claims, 1998)
Krygoski Construction Company, Inc. v. United States
94 F.3d 1537 (Federal Circuit, 1996)
Advanced Materials, Inc. v. United States
40 Cont. Cas. Fed. 76,868 (Federal Claims, 1995)
Salsbury Industries v. United States
35 Cont. Cas. Fed. 75,661 (Court of Claims, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,491, 14 Cl. Ct. 733, 1988 U.S. Claims LEXIS 83, 1988 WL 45950, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nationwide-roofing-sheet-metal-co-v-united-states-cc-1988.