National Whistleblower Center v. Nuclear Regulatory Commission

208 F.3d 256, 341 U.S. App. D.C. 28, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20493, 2000 U.S. App. LEXIS 6493, 2000 WL 339526
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 11, 2000
Docket99-1002, 99-1043
StatusPublished
Cited by4 cases

This text of 208 F.3d 256 (National Whistleblower Center v. Nuclear Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Whistleblower Center v. Nuclear Regulatory Commission, 208 F.3d 256, 341 U.S. App. D.C. 28, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20493, 2000 U.S. App. LEXIS 6493, 2000 WL 339526 (D.C. Cir. 2000).

Opinion

Opinion for the Court filed by Chief Judge HARRY T. EDWARDS.

HARRY T. EDWARDS, Chief Judge:

The petition for review in this case presents a claim by the National Whistleblower Center (“Center”) seeking to overturn a decision by the Nuclear Regulatory Commission (“NRC” or “Commission”) denying intervention by the Center in a nuclear power plant license renewal proceeding. The relicensing at issue involves the Calvert Cliffs nuclear facilities operated by Baltimore Gas & Electric (“BG&E”). This is the second time that this matter has come before this court. On November 12, 1999, the court issued a judgment holding that the NRC erred in rejecting the Center’s petition to intervene in the Calvert Cliffs license renewal proceeding. See National Whistleblower Center v. NRC, No. 99-1002, Slip. Op., 1999 WL 1024662 (D.C.Cir. Nov. 12, 1999). Following a sua sponte inquiry by the court, however, this judgment was vacated, see National Whistleblower Center v. NRC, 196 F.3d 1271 (D.C.Cir.1999), and the case was reargued before the court on March 2, 2000. Upon reconsideration, we deny the Center’s petition for review.

Any third party seeking to participate in a relicensing proceeding must file a motion to intervene, followed by a timely submission of “contentions.” A contention is a specific issue of law or fact that the third party seeks to have adjudicated; it must be substantiated by an explanation of its bases, a statement of supporting facts or expert opinion, appropriate references and citations, and sufficient information to indicate that a genuine dispute exists between the party seeking to intervene and the applicant. The Center’s problems in this case arose when it failed to make a timely filing of contentions in support of its petition to intervene in the Calvert Cliffs reli-censing proceeding.

The Center complains that the NRC erred in applying an overly rigid standard in assessing their requests for extensions of time. According to the Center, the Commission was required to adhere to a well-established “good cause” test in considering petitions for extensions of time. The NRC replies, in turn, that it gave clear notice in a published policy statement and in a subsequent referral order in the Calvert Cliffs proceeding that the agency intended to adopt a streamlined schedule in license renewal proceedings. The referral order specifically directed that “the Licensing Board should not grant requests for extensions of time absent unavoidable and extreme circumstances.” In re Baltimore Gas & Elec. Co., Order Referring Petition for Intervention and Request for Hearing to Atomic Safety and Licensing Board Panel, CLI-98-14,6 (Aug. 19, 1998), reprinted in Joint Appendix (“J.A.”) 28, 28.

We hold, first, that the NRC was free to adopt, without resort to notice-and-comment rulemaking, the “unavoidable and extreme circumstances” standard for application in the Calvert Cliffs proceeding, so long as affected parties had proper notice of the standard and it was not arbitrary and capricious, or otherwise in violation of the law. There is no doubt here that the agency’s policy statement and subsequent referral order at the start of the Calvert Cliffs proceeding gave the Center and other interested parties adequate notice. Furthermore, the agency’s adoption of the “unavoidable and extreme circumstances” standard did not reflect any arbitrary and capricious, or otherwise unlawful action. The revised standard was not an extreme departure from the “good cause” standard and it was adequately explained by the Commission; and the agency was not bound by any law to adhere to the old “good cause” standard.

Furthermore, on the record at hand, the Center can show no cognizable injury. The disputed “unavoidable and extreme *259 circumstances” test was undoubtedly applied once, when the Licensing Board denied the Center’s request for an extension of time to file contentions. However, that action was reversed by the NRC when it granted the Center’s petition for more time. The Center thereafter failed to meet the extended deadline. The Center claims that it filed a subsequent motion for an extension upon missing the extended deadline, but the record belies this claim. And, even assuming, arguendo, that the October 1, 1998 filings to which the Center refers can be viewed as a request for an additional extension of time, it is clear that those filings do not indicate even good cause for the purported request. In other words, the Center was not denied any extension of time that might otherwise have been obtained if the Commission had applied the “good cause” standard. Thus, the Center suffered no prejudice from the agency’s application of the disputed “unavoidable and extreme circumstances” test.

The record in this case indicates that the contested motion to intervene was properly denied by the Commission, because the Center failed to submit the required contentions within the prescribed deadline. Accordingly, the petition for review is hereby denied.

I. BackgrouND

The Calvert Cliffs relicensing process officially commenced on April 8, 1998, when BG&E applied to renew its licenses to operate the nuclear power plant. A few weeks later, the application was made public and the Commission announced that interested third parties would have an opportunity to request a hearing. See Notice of Receipt of Application, 63 Fed.Reg. 20,-663 (1998). On May 19,1998, the Commission accepted BG&E’s application for docketing, again noted that the application was publicly available, and again announced that third parties would be afforded an opportunity to request a hearing. See Notice of Acceptance for Docketing of the Application, 63 Fed.Reg. 27,601 (1998). On July 8, 1998, the NRC published a notice outlining the rights of third parties to seek a hearing in the Calvert Cliffs proceeding. See Notice of Opportunity for a Hearing, 63 Fed.Reg. 36,966 (1998). The July 8 Notice indicated that anyone seeking a hearing would be required to file a request and an application to intervene by August 7, 1998. The Notice also indicated that such parties would be required to file “a supplement to the petition to intervene which must include a list of contentions which are sought to be litigated in the matter.” Id. at 36,966.

The Calvert Cliffs ease is the first of many nuclear power plant license renewal proceedings. In view of the anticipated large number of license renewal applications, and also in response to “recent experience and criticism of agency proceedings,” the Commission announced its intention to streamline procedures for adjudicatory actions before the agency. Policy on Conduct of Adjudicatory Proceedings, 63 Fed.Reg. 41,872, 41,873 (1998). The NRC recognized that “the opportunity for hearing should be a meaningful one”; the Commission, however, noted that “applicants for a license are also entitled to a prompt resolution of disputes concerning their applications.” Id. Accordingly, in this policy statement, the Commission “identified certain specific approaches for its boards to consider implementing in individual proceedings, if appropriate, to reduce the time for completing licensing and other proceedings.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
208 F.3d 256, 341 U.S. App. D.C. 28, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20493, 2000 U.S. App. LEXIS 6493, 2000 WL 339526, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-whistleblower-center-v-nuclear-regulatory-commission-cadc-2000.