MUNICIPAL LIGHT CO, ASHBURNHAM v. Commonwealth

608 N.E.2d 743, 34 Mass. App. Ct. 162, 1993 Mass. App. LEXIS 150
CourtMassachusetts Appeals Court
DecidedFebruary 25, 1993
Docket91-P-910
StatusPublished
Cited by20 cases

This text of 608 N.E.2d 743 (MUNICIPAL LIGHT CO, ASHBURNHAM v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MUNICIPAL LIGHT CO, ASHBURNHAM v. Commonwealth, 608 N.E.2d 743, 34 Mass. App. Ct. 162, 1993 Mass. App. LEXIS 150 (Mass. Ct. App. 1993).

Opinion

Kass, J.

In their brief, the plaintiffs, who are municipal light companies or departments, state a prodigious twenty-six issues on appeal but these rather quickly boil down to three. All are based on actions taken by the Commonwealth to delay the operation of Seabrook Nuclear Power Plant Unit 1 (“Seabrook”) in Seabrook, New Hampshire. Seabrook, since the plan for its construction surfaced in 1968, has generated seemingly countless reactions of super-heated litigation and civil disobedience. As a consequence of the Commonwealth’s delaying actions, the plaintiffs (which we shall sometimes refer to as the light companies) claim financial losses attributable to Seabrook having come on line several years later than would have been the case, but for the Commonwealth’s machinations. The three issues to which the many urged can be reduced are: (1) whether the Commonwealth 3 is liable for damages to the light companies on theories of estoppel or implied contract; (2) whether the Commonwealth made a de facto taking of property without just compensation; and (3) *164 whether the Commonwealth unconstitutionally impaired contractual obligations of which the light companies had the benefit.

A judge of the Superior Court, acting on a motion to dismiss under Mass.R.Civ.P. 12(b), 365 Mass. 755 (1974), dismissed the complaint for failure to state a claim for which relief can be granted. We affirm.

We summarize facts alleged in the complaint which, for purposes of reviewing dismissal of a complaint under Mass.R.Civ.P. 12(b)(6), we accept as true. Nader v. Citron, 372 Mass. 96, 98 (1977). We do not purport to make any determination whether the facts alleged and which we recite are accurate.

During the early to mid-1970’s, in response to a felt need for capacity to generate more electric power, the Legislature, by the enactment of St. 1973, c. 571, 4 created the New England Power Pool and, by St. 1975, c. 775, created the Massachusetts Municipal Wholesale Electric Company (“MMWEC”). 5 Those statutes enabled, and thereby encouraged, electric utility companies in Massachusetts to participate in jointly owned power plants in or out of the Commmonwealth. In 1975, Seabrook was the only jointly owned power plant planned in New England available to outside participants, and the immediate purpose of the MMWEC legislation was to facilitate and encourage participation in Seabrook.

Also in 1975, the Department of Public Utilities (DPU) determined that the Seabrook plant was necessary to meet the future power needs of the Commonwealth. The following year, 1976, the Energy Facilities Siting Council approved MMWEC’s participation in the Seabrook project. From mid-1976 to late 1979, the DPU approved four bond issues (presumably the issuer of the bonds was MMWEC — the corn- *165 plaint does not say) which enabled MMWEC to acquire its interest (11.59340%) in Seabrook. Relying on those authorizations and approvals, the light companies acquired a substantial interest in Seabrook through the medium of membership in MMWEC, memberships which involved entry by the light companies into power sales agreements (“PSAs”) with MMWEC. Under the PSAs, the light companies were obligated to buy a stated percentage of the generating capacity of Seabrook. 6 The PSAs contain what the parties call a “take or pay” provision, whereby the light companies pay their pro rata share of MMWEC’s costs applicable to the shared facility, irrespective of whether the light companies buy electricity and, indeed, irrespective of whether the facility has electricity to sell. 7

Contrary to its encouragement of Seabrook through the various authorizations and approvals (so the complaint continues), the Commonwealth, acting through its director of civil defense, its Governor, and its Attorney General, impeded the licensure of Seabrook by the United States Nuclear Regulatory Commission (NRC). The Massachusetts authorities delayed licensure by persistently raising questions about the safety of Seabrook, notably the means to evacuate population from the environs of Seabrook in the event of a radiological emergency. Apart from objecting that inadequate safety precautions were being taken, the Commonwealth declined to formulate an emergency response plan. On March 27, 1986, the Governor stated publicly that he would oppose final licensure of Seabrook unless fallout shelters were provided on nearby beaches.

On October 8, 1986, the Seabrook plant was complete and stood ready for commercial operation. All conditions for operation had been satisfied except for the Massachusetts portion of the radiological emergency response plan. Successive *166 Attorneys General 8 continued to oppose the grant of an operating license by the NRC. On February 3, 1988, the Attorney General wrote a letter to the light companies which restated his and the Governor’s view that the Seabrook plant should and would not operate and urged the light companies to withdraw from the project, even if that were a default of their obligations under the PSAs. Approximately two years later, on March 15, 1990, the NRC issued a full power operating license to Seabrook.

As a consequence of the delays engineered by the Commonwealth through its officers, the plaintiffs suffered damage because they had to pay their share of the carrying costs (e.g., bond interest) and suffered further damage on account of the electric power they did not obtain from Seabrook and had to buy elsewhere.

It is familiar doctrine that a complaint can be dismissed for failure to state a claim for which relief can be granted only if a reading of the complaint establishes beyond doubt that the facts alleged, accepting them as true and drawing all inferences in the plaintiff’s favor, do not add up to a cause of action which the law recognizes. The plaintiff has to plead itself out of court. Nader v. Citron, 372 Mass, at 98. Connerty v. Metropolitan Dist. Commn., 398 Mass. 140, 143 (1986). New England Insulation Co. v. General Dynamics Co., 26 Mass. App. Ct. 28, 29-30 (1988). A complaint should not be dismissed because it asserts a novel or extreme theory of liability or improbable facts. Coolidge Bank & Trust Co. v. First Ipswich Co., 9 Mass. App. Ct. 369, 370 (1980). Jenkins v. Jenkins, 15 Mass. App. Ct. 934 (1983).

1. Liability based on implied contract and estoppel. Through establishment of the New England Power Pool and MMWEC, approval of the Seabrook site by the Energy Facilities Siting Council, and approval (through the DPU) of MMWEC’s bonding authority, the plaintiffs say that the Commonwealth encouraged their investment in Seabrook. On that encouragement the plaintiffs claim to have reasona *167 bly relied and spent a great deal of money.

Related

Burke v. Board of Appeal on Motor Vehicle Liability Polices and Bonds
90 Mass. App. Ct. 203 (Massachusetts Appeals Court, 2016)
Commonwealth v. H&R Block, Inc.
25 Mass. L. Rptr. 92 (Massachusetts Superior Court, 2008)
Clemmer v. Cullinane
815 N.E.2d 651 (Massachusetts Appeals Court, 2004)
Sheriff v. Labor Relations Commission
805 N.E.2d 46 (Massachusetts Appeals Court, 2004)
Machado v. Leahy
17 Mass. L. Rptr. 263 (Massachusetts Superior Court, 2004)
Tierney v. John Hancock Mutual Life Insurance
791 N.E.2d 925 (Massachusetts Appeals Court, 2003)
EIC Development, LLC v. Mystic Valley Development Commission
16 Mass. L. Rptr. 138 (Massachusetts Superior Court, 2003)
Independent Bank Corp. v. Spence
15 Mass. L. Rptr. 609 (Massachusetts Superior Court, 2003)
Massachusetts Federation of Teachers v. Board of Education
436 Mass. 763 (Massachusetts Supreme Judicial Court, 2002)
Alvares v. Microsoft Corp.
13 Mass. L. Rptr. 315 (Massachusetts Superior Court, 2001)
Pontremoli v. Spaulding Rehabilitation Hospital
747 N.E.2d 1261 (Massachusetts Appeals Court, 2001)
Farragut Mortgage Co. v. Arthur Andersen LLP
10 Mass. L. Rptr. 285 (Massachusetts Superior Court, 1999)
Mitzan v. Medview Services, Inc.
10 Mass. L. Rptr. 242 (Massachusetts Superior Court, 1999)
Grasso v. City of New Bedford
9 Mass. L. Rptr. 289 (Massachusetts Superior Court, 1998)
Burman v. Bell & Howell Phillipsburg Co.
6 Mass. L. Rptr. 424 (Massachusetts Superior Court, 1997)
Scanlan v. W.C. Canniff & Sons, Inc.
5 Mass. L. Rptr. 578 (Massachusetts Superior Court, 1996)
Canha v. LaRoche
5 Mass. L. Rptr. 704 (Massachusetts Superior Court, 1996)
A P East, Inc. v. Board of Assessors
661 N.E.2d 1344 (Massachusetts Appeals Court, 1996)
National Engineering Service v. Galello
3 Mass. L. Rptr. 683 (Massachusetts Superior Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
608 N.E.2d 743, 34 Mass. App. Ct. 162, 1993 Mass. App. LEXIS 150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/municipal-light-co-ashburnham-v-commonwealth-massappct-1993.