Fitchburg Gas & Electric Light Co. v. Department of Public Utilities

483 N.E.2d 76, 395 Mass. 836, 1985 Mass. LEXIS 1798
Massachusetts Supreme Judicial Court·Decided September 12, 1985·Published·Cited by 17 cases

Opinion

Hennessey, C.J.

We review, on reservation and report by a single justice of this court, consolidated appeals by Fitchburg Gas and Electric Light Company (Fitchburg), New England Power Company (New England), Canal Electric Company (Canal), and Massachusetts Municipal Wholesale Electric Company (MMWEC) from an order by the Department of Pub- *839 lie Utilities (department). 2 In that April 4, 1985, order (D.P.U. 84-152) the department announced it would deny the financing application of each investor-owned utility (Fitchburg, New England, and Canal) unless it received “adequate enforceable assurances and binding obligations” committing each investor-owned utility to three conditions (reproduced in the margin 3 ). Each investor-owned utility declined to provide the assurances, and appeals from the effective denial of its individual application for financing. The department, unconditionally and without reference to any “assurances,” also denied MMWEC’s financing request 4 and stated that it would “permit MMWEC to issue only such bonds as . . . [it finds] are reasonably necessary to mitigate the adverse consequences of . . . rate shock associated with its investment to date,” but would not permit it “to issue bonds to pay for further construction costs” of the Seabrook Nuclear Project Unit I (Seabrook I). We affirm the department’s decision and orders in so far as they concern the Seabrook I financing applications. We remand to the depart *840 ment for further consideration the applications of the investor-owned utilities for approval of non-Seabrook financing.

The three investor-owned utilities are private corporations which supply electric power. MMWEC is a public corporation formed under c. 775 of the Acts of 1975 to develop a bulk power supply program for Massachusetts municipal electric systems, with authority to acquire, construct, and finance ownership interests in electric generating units to serve the municipalities who are members. Neither the investor-owned utilities nor MMWEC must get permission of the department to invest in power sources, but all must get approval of the department for bond or stock issue. G. L. c. 164, § 14 (1984 ed.) (investor-owned utilities). St. 1975, c. 775, § 17 (MMWEC). Each petitioner had at least one financing case pending before the department when, on July 13, 1984, they filed a joint petition requesting that the department conduct a single investigation of the cost and schedule for the completion of Seabrook I. The petitioners sought findings of fact on those issues and requested that the findings be incorporated into the pending individual applications by which each sought authorization and approval of stock and bond issuances related, at least in part, to Seabrook I construction costs. 5 In response, the department decided that it would investigate: “(1) the estimated cost of completing Seabrook I, including construction and financing costs; (2) the estimated completion date and commercial on-line date of Seabrook I; and (3) the estimated operating characteristics of Seabrook I.”

The department’s findings in this, the “generic case,” include: that “serious questions remain” as to whether Seabrook I will be completed; “that the [petitioners’] failure to present a reasonable range of possible cost estimates supported by reviewable and more realistic construction schedules” was *841 fatal; and that they had “failed to meet their burden of providing ... a credible analysis of the potential costs of the project.” It also found that the issuances proposed in the individual financing cases could not be determined to be reasonably necessary based on an economic analysis of the project; that in the absence of assurances that the public interest would be protected it found that the requests could not be approved “consistent with the requirements of G. L. c. 164, § 14,” and St. 1975, c. 775; and that “the degree of risk associated with increased costs and potential future abandonment. . . precludes a finding that the plant is reasonably necessary.” However, the department also found that the statutory standard would permit approval of the financing applications of the three investor-owned companies without such an economic analysis if it were assured that the risks were fully disclosed to investors and were not being borne by the ratepayers. Hence, it announced the requirements set out in the margin (note 3). The department considered itself to be unable to similarly insulate MMWEC’s ratepayers from the high level of risk associated with the project, 6 could not find its proposed bond issue to be reasonably necessary, and unconditionally denied MMWEC’s financing application.

The investor-owned utilities and MMWEC argue that the department inappropriately exercised its statutory authority in denying the requests, deprived them of particular protections of G. L. c. 30A (1984 ed.), and violated certain constitutional rights. We now consider these challenges. 7

I. Department’s Authority.

We first examine the nature and scope of the department’s authority. Gas and electric companies are permitted to issue “only such . . . stock and bonds ... as the department may . . . vote is reasonably necessary for the purpose for which such *842 issue . . . has been authorized.” G. L. c. 164, § 14. In Fitchburg Gas & Elec. Light Co. v. Department of Pub. Utils., 394 Mass. 671, 678 (1985) (Fitchburg I), we reiterated our determination that the statute’s purposes include the vesting “in public officers [of] the right to determine the general question of the reasonable necessity of the issue”; and repeated our statement that “the department must inquire whether the declared purpose of the proposed issue is . . .in the circumstances a reasonably necessary purpose. . . . ‘[Reasonably necessary’ means reasonably necessary for the accomplishment of some purpose having to do with the obligations of the company to the public and its ability to carry out those obligations with the greatest possible efficiency. . . Id., quoting Lowell Gas Light Co. v. Department of Pub. Utils., 319 Mass. 46, 52 (1946). Thus, the department’s authority is not limited to “a perfunctory review” of the proposed financing. 8 Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Fitchburg Gas & Electric Light Co. v. Department of Public Utilities, 483 N.E.2d 76, 395 Mass. 836, 1985 Mass. LEXIS 1798 (Mass. 1985).

483 N.E.2d 76 (Fitchburg Gas & Electric Light Co. v. Department of Public Utilities) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Boston Globe Media Partners, LLC v. Retirement Board
33 Mass. L. Rptr. 374 (Massachusetts Superior Court, 2016)
Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Board
858 N.E.2d 294 (Massachusetts Supreme Judicial Court, 2006)
Town of Hingham v. Department of Telecommunications & Energy
433 Mass. 198 (Massachusetts Supreme Judicial Court, 2001)
National Ass'n of Government Employees v. Commonwealth
2 Mass. L. Rptr. 21 (Massachusetts Superior Court, 1994)
Shelby Mutual Insurance v. Commonwealth
631 N.E.2d 63 (Massachusetts Appeals Court, 1994)
MUNICIPAL LIGHT CO, ASHBURNHAM v. Commonwealth
608 N.E.2d 743 (Massachusetts Appeals Court, 1993)
Reliance Insurance v. Commissioner of Insurance
581 N.E.2d 1027 (Massachusetts Appeals Court, 1991)
Massachusetts Municipal Wholesale Electric Co. v. Energy Facilities Siting Council
580 N.E.2d 1028 (Massachusetts Supreme Judicial Court, 1991)
Alliance for Aff. Energy v. New Orleans
578 So. 2d 949 (Louisiana Court of Appeal, 1991)
Massachusetts Automobile Rating & Accident Prevention Bureau v. Commissioner of Insurance
516 N.E.2d 1132 (Massachusetts Supreme Judicial Court, 1987)
Martorano v. Department of Public Utilities
516 N.E.2d 131 (Massachusetts Supreme Judicial Court, 1987)
Solimeno v. State Racing Commission
509 N.E.2d 1167 (Massachusetts Supreme Judicial Court, 1987)
Hull Municipal Lighting Plant v. Massachusetts Municipal Wholesale Electric Co.
506 N.E.2d 140 (Massachusetts Supreme Judicial Court, 1987)
Nationwide Mutual Insurance v. Commissioner of Insurance
491 N.E.2d 1061 (Massachusetts Supreme Judicial Court, 1986)
Appeal of Conservation Law Foundation of New England, Inc.
507 A.2d 652 (Supreme Court of New Hampshire, 1986)