Town of Framingham v. Department of Public Utilities

244 N.E.2d 281, 355 Mass. 138, 1969 Mass. LEXIS 754
CourtMassachusetts Supreme Judicial Court
DecidedJanuary 6, 1969
StatusPublished
Cited by18 cases

This text of 244 N.E.2d 281 (Town of Framingham v. Department of Public Utilities) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Framingham v. Department of Public Utilities, 244 N.E.2d 281, 355 Mass. 138, 1969 Mass. LEXIS 754 (Mass. 1969).

Opinion

Reardon J.

These are three petitions for appeal under G. L. c. 25, § 5, from a final decision of the Department of Public Utilities (Department) granting a petition by the intervener, Boston Edison Company (Edison), which under G. L. c. 40A, § 10, sought an exemption from zoning restrictions for a proposed line for the transmission of electricity at 230 kilovolts, strung on towers, to be constructed on its existing right of way between Medway and Sudbury. The line proposed will be approximately 17.25 miles in length and will pass through seven towns, three of which are the petitioners. Medway and Sherborn did not appeal and the towns of Holliston and Natick were not included as respondents in the Edison petition on the basis that the existing zoning by-laws of those towns do not prohibit the installation. The Department held hearings on four days and received evidence including expert testimony and exhibits. Edison’s petition asserted that the use of the right of way was reasonably necessary for the convenience and welfare of the public and the Department found this to be a fact.

The Department made numerous subsidiary findings and referred to the fact that the proposed line would be installed on Edison’s present right of way, 250 feet in width. Reference was also made to the increased electrical capacity requirements expected within the next few years in the area served by the present transmission system. The decision described the right of way as being presently occupied by two 115 kilovolt wood pole H-frame lines along a portion of the right of way to Framingham, with one such line extending to Waltham by way of Sudbury. The present poles *141 vary in height from sixty-five to eighty feet and the contemplated construction would consist of two circuit, wide base, lattice type steel towers varying in height from 110 to 125 feet, except at certain substations where the towers would be 160 feet in height. The. structures would be spaced approximately 1,000 feet apart. Clearance above the ground of the wires suspended from such structures would be not less than twenty-five feet, and over highways not less than twenty-eight feet. The Department also weighed evidence of the effect of the new fine on radio and television reception, reviewed the possibility of underground lines, and considered both cost and aesthetics in arriving at its decision. The cases came before the single justice who reserved and reported them without decision. At the hearing before the Department numerous requests for rulings were filed by the respective towns. Problems arising from the disposition of these requests, as well as those raised in other assignments of error, will be discussed seriatim.

1. It is argued by the towns that Edison must procure fresh approval from the Department under G. L. c. 164, § 72, before it can construct on its present right of way the taller and higher voltage fine. It is further argued that no valid exemption from local zoning by-laws can be given by the Department until, first, authority to construct a new fine has been extended under § 72. The towns in their appeals rely mainly on Sudbury v. Department of Pub. Util. 343 Mass. 428, 431-432 (the first Sudbury case), which concerned a petition for authority to construct a line on land on which Edison then had no rights, either through private negotiation or by eminent domain, wherein the court stated that G. L. c. 164, § 72, contemplates two separate permissions from the Department, one authorizing the construction of a line and the second authorizing requisite eminent domain takings. Reliance is also placed by the.petitioners on Hamilton v. Department of Pub. Util. 346 Mass. 130, which details at pages 144 and 145 those factors which the Department should consider in making determinations on petitions brought under G. L. c. 164, § 72.

*142 On the other hand, Edison, in asking that the question be determined in this case, contends that it is not required to seek approval of the Department under G. L. c. 164, § 72, unless eminent domain proceedings are necessary in order to secure the needed right of way. It buttresses its position by reference to the legislative history of that statute, the common understanding of § 72 by the Department and the electric companies over the years which' it states to be in accordance with its position, and the adequate protection which it alleges is afforded to the public by certain other statutes conferring powers of general and ample supervision on the Department over properties of electric companies. The Department holds the view that its power to grant zoning exemptions under G. L. c. 40A, § 10, is not dependent on prior permissions granted the utility under G. L. c. 164, § 72. The author of this opinion agrees with Edison that G. L. c. 164, § 72, has no applicability to the case at bar and that, consonant with the request expressed by Edison and the towns, that point should be decided now. The majority of the court, however, are of the view that it is not now necessary to determine whether in the first Sudbury case the court gave too wide a significance to the first few sentences of § 72 in deciding that case where a later eminent domain taking was contemplated. There was then no reason to consider those sentences in relation to a situation where no eminent domain takings would later be necessary. The scope of those sentences can be determined in other circumstances where such determination is required. The Department dealt with the issue which Edison now raises in refusing the first three requests of each town which are similar, first, on the ground that the requests had been “defectively drawn” and, second, in the following language: “We construe these requests to mean that on all the evidence a finding is required that some authority under § 72 is necessary and that this authority has not been given by the prior orders of the Department. We deny the requests because it is not necessary to make a determination of them in this proceeding, and, in any case, the evidence does not *143 require a finding as matter of law that such authority is now necessary” (emphasis supplied). The Department’s action was correct in that the requested rulings were not relevant, for a proceeding under c. 40A, § 10, as amended, is not necessarily dependent on any action under c. 164, § 72, as amended. Neither section refers to the other and a proceeding under c. 40A, § 10, may go forward independently of a proceeding under § 72. There was no error in the denial by the Department of the requests for rulings by the towns dealing with authority to construct under G. L. c. 164, §72.

2. We pass to a consideration of further contentions of the towns raising questions somewhat similar to those already discussed. They assign as error the refusal of the Department to grant certain requests for rulings dealing with permissions to cross public lands under G. L. c. 164, § 72, and public ways under G. L. c. 166, §§ 22 and 28. Relative to these requests, the Department takes the position on the authority of the second Sudbury case, 351 Mass. 214, 224, that its power to grant zoning exemptions pursuant to G. L. c. 40A, § 10, does not depend on prior permits which it may have granted to construct and use a fine, or permits granted by municipalities for wire crossings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. Schutte
756 N.E.2d 48 (Massachusetts Appeals Court, 2001)
Rate Setting Commission v. Baystate Medical Center
665 N.E.2d 647 (Massachusetts Supreme Judicial Court, 1996)
Commonwealth v. Sneed
597 N.E.2d 1346 (Massachusetts Supreme Judicial Court, 1992)
Grant v. Lewis/Boyle, Inc.
557 N.E.2d 1136 (Massachusetts Supreme Judicial Court, 1990)
Massachusetts Automobile Rating & Accident Prevention Bureau v. Commissioner of Insurance
516 N.E.2d 1132 (Massachusetts Supreme Judicial Court, 1987)
Fitchburg Gas & Electric Light Co. v. Department of Public Utilities
483 N.E.2d 76 (Massachusetts Supreme Judicial Court, 1985)
Fall River Savings Bank v. Callahan
463 N.E.2d 555 (Massachusetts Appeals Court, 1984)
Costello v. Department of Public Utilities
462 N.E.2d 301 (Massachusetts Supreme Judicial Court, 1984)
New England Power Co. v. Board of Selectmen
449 N.E.2d 648 (Massachusetts Supreme Judicial Court, 1983)
Trustees of Clark University v. Department of Public Utilities
361 N.E.2d 1285 (Massachusetts Supreme Judicial Court, 1977)
Maddocks v. Contributory Retirement Appeal Board
340 N.E.2d 503 (Massachusetts Supreme Judicial Court, 1976)
Kelly Realty Co. v. Commonwealth
323 N.E.2d 350 (Massachusetts Appeals Court, 1975)
Save the Bay, Inc. v. Department of Public Utilities
322 N.E.2d 742 (Massachusetts Supreme Judicial Court, 1975)
Town of Truro v. Department of Public Utilities
312 N.E.2d 566 (Massachusetts Supreme Judicial Court, 1974)
Town of Northborough v. Department of Public Utilities
282 N.E.2d 894 (Massachusetts Supreme Judicial Court, 1972)
Town of Westborough v. Department of Public Utilities
267 N.E.2d 110 (Massachusetts Supreme Judicial Court, 1971)
Boston Edison Co. v. Town of Sudbury
253 N.E.2d 850 (Massachusetts Supreme Judicial Court, 1969)
Hopkins v. Grimshaw
165 U.S. 342 (Supreme Court, 1897)

Cite This Page — Counsel Stack

Bluebook (online)
244 N.E.2d 281, 355 Mass. 138, 1969 Mass. LEXIS 754, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-framingham-v-department-of-public-utilities-mass-1969.