Moyer Bros. v. United States

156 Ct. Cl. 120, 1962 U.S. Ct. Cl. LEXIS 46, 1962 WL 9330
CourtUnited States Court of Claims
DecidedJanuary 12, 1962
DocketNo. 428-57
StatusPublished
Cited by2 cases

This text of 156 Ct. Cl. 120 (Moyer Bros. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moyer Bros. v. United States, 156 Ct. Cl. 120, 1962 U.S. Ct. Cl. LEXIS 46, 1962 WL 9330 (cc 1962).

Opinion

Laramore, Judge,

delivered the opinion of the court:

This is a claim for damages arising from acts of the United States which plaintiff alleges constituted a breach of a contract between plaintiff and the United States for construction work at the Greater Pittsburgh Air Force Base.

The case was tried by a commissioner of this court who, on May 31,1961, filed detailed findings of fact.

On October 13,1961, plaintiff filed a “statement” submitting its claim without brief, electing to submit the case on the commissioner’s report.

On November 3,1961, defendant’s motion to dispense with oral argument and submit on the commissioner’s report and defendant’s brief was allowed.

Under these circumstances it is unnecessary at this time to summarize the facts since the facts as found by the commissioner, which are adopted by the court, are dispositive of the issues, and in the absence of exceptions thereto by plaintiff are taken to be correct. (Buie 48 of the Buies of this court.)

Plaintiff’s claim is twofold. The first is a claim for equitable adjustment by reason of the allegation that “* * * Defendant knew or should have known that contractor’s bid for the gas distribution system did not include an item for [122]*122excavation and backfilling” and that “Contractor believes that it is entitled to an equitable adjustment * * * for the trench excavation and backfill * *

Finding 16 discloses that if plaintiff did not include any amount in its bid for items 104-113, to cover the cost of trench excavation for gas lines, as stated in the petition, such omission constituted a mistake, or misunderstanding, of the contract provision, paragraph 8-22 of the technical provisions, which provided that payment for pipe in the gas lines at the applicable unit price per linear foot included trench excavation and backfill.

Finding 16 also discloses (footnote 3) that there was nothing in the price plaintiff bid which would have placed defendant on notice that the cost of excavation and backfill was not included in the figure submitted, if in fact it was not.

Since the contract clearly provided that payment for the gas mains at the unit price bid included payment for excavation and backfill and plaintiff has been paid for all the gas mains at the contract price, there is no basis upon which it can recover an additional amount for excavation and backfill. Hyde Park Clothes, Inc. v. United States, 114 Ct. Cl. 424, 435-436; S. N. Nielsen Company v. United States, 141 Ct. Cl. 793.

In connection with the above, it is also noted that the Armed Services Board of Contract Appeals denied plaintiff’s claim, and the findings show that this decision was not arbitrary and was supported by substantial evidence. In the absence of a showing that the decision is arbitrary or not supported by substantial evidence, this court will not disturb the decision of the Board.

Plaintiff’s second claim is for an additional amount alleged to be owing its subcontractor because a slag-gravel combination was employed for the four-inch select base course material rather than the “red dog” upon which its bid was based.

In respect to this claim, the facts show that at no time was the contract changed to upgrade the specification requirements for the four-inch select base course material. Since there was no change in the requirements under the contract, and plaintiff merely performed its contractual obligation, [123]*123there is no basis for recovery herein. Kenneth Ward Anderson, et al. v. United States, 143 Ct. Cl. 729.

Moreover, the contracting officer also denied this portion of plaintiff’s claim and this denial was upheld on appeal by_ the Corps of Engineers Claims and Appeals Board and the Armed Services Board of Contract Appeals. The facts show that the Armed Services Board of Contract Appeals’ decision was not arbitrary and was supported by substantial evidence. Absent a showing to the contrary, this court will not disturb the decision of the Board.

Upon the facts as found, the court finds that plaintiff has proven no basis upon which recovery could be granted. Accordingly, plaintiff’s petition will be dismissed.

It is so ordered.

Durfee, Judge; Whitaker, Judge; and Jones, Chief Judge, concur.

FINDINGS OF FACT

The court, having considered the evidence, the report of Trial Commissioner Paul H. McMurray, and the briefs and argument of counsel, makes findings of fact as follows:

1. Plaintiff Moyer Brothers is a partnership consisting of A. C. Moyer and J. E. Moyer, engaged in general contracting business; and the plaintiff Moyer Brothers brings this action in its own right and to the use of Kean-Wise, Inc., its subcontractor, who furnished labor and material for construction of the select material base course.

2. Invitation for bids was issued by the defendant June 21, 1951, for the construction of buildings, utilities, taxiways, and aprons at the Greater Pittsburgh Air Force Base, Allegheny County, Pennsylvania. The invitation for bids was amended by Addenda Nos. 1, 2,3,4,5, and 6, dated June 26, July 2, July 2, July 6, July 9, and July 11,1951, respectively. Opening of bids took place on July 17, 1951.

,3. The plaintiff prepared its cost estimates prior to receiving any of the six addenda to the invitation for bids.1

[124]*124The original invitation for bids, issued June 21,1951, contained a Unit Price Schedule, a section entitled Special Conditions 15 “Estimated Quantities.” The relevant portions of these provisions are as follows:

The invitation for bids also included a Technical Provisions section in which were the following relevant sections:

4-01 Scope. The work covered hj this section of the specifications consists in furnishing all plant, labor, equipment, appliances, and materials, and in performing all operations in connection with the excavation, trenching, and backfilling for utilities systems beyond a line 5 feet outside of all buildings and structures, for all utilities connected thereto, complete, in strict accordance with this section of the specifications and the applicable draw[125]*125ings, and subject to the terms and conditions of the contract.
4-06 Methods of measurement. Trench excavation, rock excavation, refill replacing unstable material, and the sheeting and bracing ordered left in place and to be paid for will be the measured quantities involved in the completed work.
a. Trench excavation. The trench excavation to be paid for will be the lineal feet of trench measured along the center line and excavated within the limiting depths shown on the Drawings. In the measurement for trench excavation no deduction will be made for rock excavation.
$ # ‡ $
4-07 Basis of payment. All payments will be based on completed work performed in strict accordance with the Drawings and this specification, and on the contract bid and payment schedules.
a. Trench excavation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AAB Joint Venture v. United States
75 Fed. Cl. 414 (Federal Claims, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
156 Ct. Cl. 120, 1962 U.S. Ct. Cl. LEXIS 46, 1962 WL 9330, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moyer-bros-v-united-states-cc-1962.