Moulden & Sons, Inc. v. Osaka Landscaping & Nursery, Inc.

584 P.2d 968, 21 Wash. App. 194, 25 U.C.C. Rep. Serv. (West) 454, 1978 Wash. App. LEXIS 2005
CourtCourt of Appeals of Washington
DecidedAugust 23, 1978
Docket2715-2
StatusPublished
Cited by37 cases

This text of 584 P.2d 968 (Moulden & Sons, Inc. v. Osaka Landscaping & Nursery, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moulden & Sons, Inc. v. Osaka Landscaping & Nursery, Inc., 584 P.2d 968, 21 Wash. App. 194, 25 U.C.C. Rep. Serv. (West) 454, 1978 Wash. App. LEXIS 2005 (Wash. Ct. App. 1978).

Opinion

Soule, J.

— Plaintiff brought an action to recover the unpaid portion of the price of a quantity of cinders delivered to the defendant. Defendant counterclaimed for expenses incurred because the plaintiff initially delivered cinders which failed to meet the size specifications. Plaintiff recovered on its action and defendant's claim was dismissed. Defendant appeals the dismissal of its counterclaim.

In July of 1973, Osaka Landscaping & Nursery, Inc. (defendant), placed an oral order with Moulden & Sons, Inc. (plaintiff), for the delivery of cinders which were to be no larger than 1/4 inch in size. These cinders were to be used in fulfilling a contractual obligation of the defendant, as a subcontractor, to install a playfield for the Mukilteo School District. The cinders were delivered to the work site in August and September of 1973. Defendant spread the cinders and installed the playfield. Following the annual rainy season of 1973-74 and the children's use of the playground, it was discovered that substantial portions of the cinders were larger than the size ordered. This resulted in the children receiving scratches as they played on the cinder playfield. The school district informed the contractor and defendant of this nonconformity. Defendant, in turn, notified plaintiff in September of 1974. 1 Subsequently, by a letter dated November 6, 1974, defendant demanded that plaintiff correct the problem or defendant would do so and charge plaintiff for the expense.

*196 Plaintiff then made an unsuccessful attempt at sifting out the larger cinders. Finally, in December of that year, plaintiff agreed to replace the cinders at its own expense. However, the parties gave conflicting evidence as to who was to bear the cost of regrading the cinders. Plaintiff contended that defendant had agreed to hire one Fred LaCount to perform this task and assume the cost thereof. Defendant testified that he only suggested that LaCount be hired to do the work, but did not agree to bear the cost of such a hiring. Nevertheless, in January 1975, LaCount performed the bulk of the grading necessary for the reinstallation of the playfield. He apparently returned in the following May to provide some finishing touches. On June 11, LaCount tendered a bill for his services to defendant, who, in turn, deducted this cost (plus the cost of extra labor incurred as a result of the breach) from the amount due to plaintiff on the original contract and tendered payment for the difference to plaintiff on July 30. Plaintiff rejected that tender and this action resulted.

The only issue raised on appeal is whether the trial court correctly denied defendant's counterclaim for the cost of LaCount's regrading plus the extra labor costs incurred due to the plaintiff's breach. 2

Defendant's counterclaim was denied apparently on the basis that: (1) plaintiff had cured the breach; and (2) the defendant had failed to make a seasonable demand for reimbursement of the expense of reinstalling the playfield. Defendant argues that the plaintiff had no right to "cure" the breach since this was a revocation of acceptance situation, and that its demand for reimbursement was seasonable. We reverse the trial court's denial of defendant's counterclaim for the reasons set out below.

Defendant initially contends that a seller has no right to provide any "cure" in a revocation situation. While such a contention is not without support, 3 there is also authority *197 to the contrary.* * 4 However, under the facts of this case, we need not decide that question. While a seller may not have a right to cure the nonconformity in a revocation situation, the defendant by its letter of November 6, 1974, conferred upon the plaintiff-seller the opportunity to cure the breach. As a result, the primary issue in this case comes down to whether the plaintiff did "cure" the breach as that term is used in RCW 62A.2-508.

The trial court stated as a finding of fact that the plaintiff had cured the breach. The fact that a court designates its determination as a "finding" does not make it so if it is in reality a conclusion of law. Under Washington practice, a conclusion of law mislabeled as a finding will be treated as a conclusion. McClendon v. Callahan, 46 Wn.2d 733, 284 P.2d 323 (1955); Hauser v. Arness, 44 Wn.2d 358, 267 P.2d 691 (1954); 2 Orland, Wash. Prac. § 311, at 338 n.38 (1972).

In Leschi Improvement Council v. State Highway Comm'n, 84 Wn.2d 271, 283, 525 P.2d 774 (1974), a finding of fact was defined as an

assertion that a phenomenon has happened or is or will be happening independent of or anterior to any assertion as to its legal effect.'"

In applying that definition to the facts at hand, it is clear that whether the plaintiff had provided new cinders would be a finding of fact. However, whether the replacement of the cinders constituted a "cure" is a determination of the legal effect of that action and is thus a conclusion, of law. 5 Therefore, the pertinent standard of review is whether the conclusion of law, that a cure resulted, is supported by the evidence. McClendon v. Callahan, supra.

*198 Since the Uniform Commercial Code does not define the term "cure," resort must be made to other case law and the policy of the code's remedy provisions. A case which concerned substantially similar issues as the one at hand was Great American Music Mach., Inc. v. Mid-South Record Pressing Co., 393 F. Supp. 877, 882 (M.D. Tenn. 1975). In that case, the defendant was under contract to manufacture and supply to the plaintiff a large quantity of record albums. When the albums were received, an inspection revealed substantial defects. Defendant agreed to replace the albums with a new pressing. Plaintiff accepted this replacement delivery and brought suit for, among other things, the incidental expense of the extra handling costs attributable to the defective first pressing. The court allowed recovery of these expenses, finding that the mere

delivery of the second batch of records did not constitute a cure within the meaning of . . . [RCW 62A.2-508] . . . as the damage had already occurred and the time set for performance had expired.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In the Matter of the Dependency of: I.A.L. & L.J.
Court of Appeals of Washington, 2025
Scott & Cathleen Brueske v. Chelan County
Court of Appeals of Washington, 2023
Hpep, Llc, V. Qian Meng
Court of Appeals of Washington, 2023
William Forsman, et ux v. Loiace W. Greene, et ux
Court of Appeals of Washington, 2023
Othelo Quilang v. Dep't of Social & Health Services
Court of Appeals of Washington, 2022
William Pearson, V. Hana Yohannes
Court of Appeals of Washington, 2022
State Of Washington, V. Dusten J. Owens
Court of Appeals of Washington, 2022
In the Matter of the Guardianship of: Joan N. Mesler
Court of Appeals of Washington, 2022
Scott M. Hodges v. Karynn M. Pauley
Court of Appeals of Washington, 2021
Gravity Segregation, Llc v. Jerry C. Reeves
Court of Appeals of Washington, 2021
In Re: The Gordon & Frances Sales Family Trust
Court of Appeals of Washington, 2020
Seven Hills, LLC v. Chelan County
Court of Appeals of Washington, 2020
Lester And Susan Riley v. David And Susan Valaer
Court of Appeals of Washington, 2020
In re the Guardianship of: Anna May Black
Court of Appeals of Washington, 2019
In Re The Welfare Of A.l.c.
439 P.3d 694 (Court of Appeals of Washington, 2019)
In Re The Dependency Of A.z.b., Jr.
Court of Appeals of Washington, 2017
James Goughnour, V Mark And Carolyn Doyle
Court of Appeals of Washington, 2016

Cite This Page — Counsel Stack

Bluebook (online)
584 P.2d 968, 21 Wash. App. 194, 25 U.C.C. Rep. Serv. (West) 454, 1978 Wash. App. LEXIS 2005, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moulden-sons-inc-v-osaka-landscaping-nursery-inc-washctapp-1978.