Morton v. Hewitt

202 F. Supp. 2d 394, 2002 WL 1009171, 2002 U.S. Dist. LEXIS 9245
CourtDistrict Court, Virgin Islands
DecidedMay 13, 2002
DocketCIV.A.1999/93-A
StatusPublished
Cited by4 cases

This text of 202 F. Supp. 2d 394 (Morton v. Hewitt) is published on Counsel Stack Legal Research, covering District Court, Virgin Islands primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morton v. Hewitt, 202 F. Supp. 2d 394, 2002 WL 1009171, 2002 U.S. Dist. LEXIS 9245 (vid 2002).

Opinion

OPINION OF THE COURT

PER CURIAM.

Oliver Morton [“Morton” or “appellant”] appeals the Territorial Court ruling that an express contract existed between Morton and Abraham and Doreen Hewitt [collectively “Hewitts” or “appellees”] and awarding the Hewitts damages for Morton’s breach of that contract. For the reasons set forth below, we will affirm the Territorial Court’s judgment in favor of the Hewitts.

I. FACTUAL AND PROCEDURAL BACKGROUND

After Hurricane Hugo swept through the Virgin Islands in September of 1989, the Hewitts suffered extensive damage to two of their homes, Estate No. 37 Rattan [“Plot 37”] and Estate No. 22-B Rattan [“Plot 22-B”]. The appellees approached appellant Morton, a licensed repair and maintenance contractor, to give them estimates for the repair of both houses. Morton complied with the Hewitts’ request and provided estimates of $80,000 and $75,000 for Plots 37 and 22-B, respectively. The Hewitts then took these estimates to the Small Business Administration [“SBA”] to obtain a loan. Finding the estimates to be insufficient, the SBA informed the Hewitts that the estimates needed to be typewritten and in a certain format. The Hewitts subsequently informed Morton what the SBA required and provided him with an example of the format. Morton, in turn, had his estimates typed up in accordance with the SBA example. The Hewitts then took these typed documents back to the SBA and received loans with the amounts of $77,600 for Plot 37 and $34,900 for Plot 22-B. 1

Upon receiving the loans from the SBA, the Hewitts asked Morton to begin work reconstructing Plots 37 and 22-B. Sometime in June of 1990, Morton began work on Plot 37. He later started work on Plot 22-B in October of that same year. Each job was to take 90 days. Various problems arose during these construction periods, including, inter alia, the Morton’s absences from the work site, the Hewitts’ numerous changes to the reconstruction plans, and Morton’s unauthorized additions to the structures. As a result of these problems, Morton did not complete his work on Plot 37 until November of 1991 and eventually abandoned his work on Plot 22-B, leaving it 75-85 percent complete.

The Hewitts then brought suit against Morton in the Territorial Court for breach of contract. After a bench trial, the trial judge found that an express contract existed between the parties and that Morton had breached this contract. The trial judge then awarded the Hewitts $14,257.92 in actual damages and $3 in nominal- damages to Plot 37 and $34,317.18 in actual damages and $1 in nominal damages to Plot 22-B. Morton now timely appeals the Territorial Court’s judgment on the grounds that the trial court erred in (1) concluding that the estimates constituted *396 enforceable construction contracts; (2) concluding that appellant breached any construction contract by job delay; (3) assessing actual and nominal damages against the appellant; and (4) rejecting appellant’s counterclaim for quantum me-ruit damages.

II. DISCUSSION

A. Jurisdiction and Standard of Review

This Court has jurisdiction to review final judgments and orders of the Territorial Court in all civil matters. See 4 V.I.C. § 33. 2 Questions involving contract construction—the legal operation of a contract—is a question of law mandating plenary review. See In re Cendant Corp. Prides Litig., 233 F.3d 188, 193 (3d Cir.2000); Nibbs v. Roberts, 31 V.I. 196, 204, 1995 WL 78295 (D.V.I.App.Div.1995) (“The trial court’s decision concerning the application of a legal precept is subject to plenary review.”). Contract interpretation, on the other hand, is a question of fact, which is reviewed under a clearly erroneous standard. See In re Cendant Corp., 233 F.3d at 193; Nibbs, 31 V.I. at 204, 1995 WL 78295.

B. The Territorial Court Did Not Err in Concluding That An Express Contract Existed

It is well-settled law that “the test for enforceability of an agreement is whether both parties have manifested an intention to be bound by its terms and whether the terms are sufficiently definite to be specifically enforced.” See ATACS Corp. v. Trans World Communications, Inc., 155 F.3d 659, 665 (3d Cir.1998) (citations omitted). Although offer, acceptance, and consideration are required elements of contract formation, “the decisive inquiry in contract formation is the ‘manifestation of assent of the parties to the terms of the promise and to the consideration for it ....’” See id. at 665-66 (quoting 1 Samuel Williston, A Treatise on the Law of Contracts § 23, at 51 (Walter H.E. Jaeger ed., 3d ed.1957)) (alterations in original); see also Gardiner v. Virgin Islands Water & Power Auth., 896 F.Supp. 491, 497 (D.Vi.1995) (“The only essential prerequisite for creation of a valid contract is that the parties mutually assent to the terms and conditions of the agreement.”), aff'd, 145 F.3d 635 (3d Cir.1998). According to the Restatement (Second) of Contracts, 3 “[mjanifestation of mutual assent to an exchange requires that each party either make a promise or begin or render a performance.” Restatement (Second) of Contracts § 18; see also id. § 19(1) (“The manifestation of assent may be made wholly or partly by written or spoken words or by other acts or by failure to act.”). It is clear from the record below that the parties to this action manifested their mutual assent to be bound by contract.

Morton puts considerable effort into disproving the trial court’s determination that the estimate documents for Plots 37 and 22-B constituted express contracts by alleging that he did not sign the purported estimate agreements and that the signature on it was a forgery. The appellant *397 argues that this lack of signature rendered the contracts unenforceable. The appellant’s efforts are misplaced, however, as the trial court correctly noted that Morton’s performance of the contemplated work created an enforceable agreement between the parties. (J.A. at 16-17.) According to the Morton’s own testimony, the Hewitts asked him to start work reconstructing Plot 37. (Id. at 388.) Although Morton did not immediately accept this offer because he was busy with other projects, he stated that he would let them know once he had finished these other projects. (Id.) Sometime later, the Hew-itts again asked Morton to start work on Plot 37 and even provided him with a check for $10,000 and he thereafter began the work. (Id. at 388-94.) While Morton was working on Plot 37, the Hewitts asked him to start work on Plot 22-B as well and Morton did so. (Id.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Delta Electric v. Biggs
63 V.I. 876 (Virgin Islands, 2011)
Charleswell v. Chase Manhattan Bank, N.A.
308 F. Supp. 2d 545 (Virgin Islands, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
202 F. Supp. 2d 394, 2002 WL 1009171, 2002 U.S. Dist. LEXIS 9245, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morton-v-hewitt-vid-2002.