Gardiner v. Virgin Islands Water & Power Authority

896 F. Supp. 491, 32 V.I. 408, 1995 WL 505127
CourtDistrict Court, Virgin Islands
DecidedAugust 17, 1995
DocketCiv. No. 1990/295
StatusPublished
Cited by2 cases

This text of 896 F. Supp. 491 (Gardiner v. Virgin Islands Water & Power Authority) is published on Counsel Stack Legal Research, covering District Court, Virgin Islands primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gardiner v. Virgin Islands Water & Power Authority, 896 F. Supp. 491, 32 V.I. 408, 1995 WL 505127 (vid 1995).

Opinion

BROTMAN, U.S. District Judge

(Sitting by Designation)

MEMORANDUM OPINION

Before the Court are plaintiff's motion for summary judgment, filed June 28, 1991, and defendant's opposition to plaintiff's motion, filed October 17,1994. In addition to these filings, plaintiff filed a Statement of Material Facts Not in Issue, in compliance with LRCi 56.1, on July 14, 1995. On July 25, 1995, defendant filed its *409 Response to Plaintiff's Statement of Material Undisputed Facts. On July 28, 1995, plaintiff filed a reply to defendant's response taking issue with several of the facts defendant claimed were undisputed. For the reasons discussed herein, plaintiff's motion for summary judgment is granted with respect to liability and a trial will be scheduled to determine damages.

BACKGROUND AND FACTS

On September 17 and 18,1989, Hurricane Hugo struck the Virgin Islands with tremendous destructive force leaving most essential services on St. Croix destroyed or badly damaged. On September 19 the government of the Virgin Islands declared a state of emergency. On September 20, 1989 the President of the United States declared that a major disaster existed in the Virgin Islands, thus authorizing federal disaster relief efforts. FEMA-Territory Agreement ("FEMA-Terr Agrmnt") at 1.

It was apparent to both federal and local officials in the immediate aftermath of Hugo that the water delivery system on St. Croix was severely damaged and that providing fresh water to the citizens of St. Croix would have to be a top priority. See, e.g. Deposition of Bruce Green, employee of the U.S. Geological Survey "USGS" ("Green Dep.") at 13, 15; Deposition of Steven Singer, FEMA coordinating officer for St. Croix ("Singer Dep.") at 26; Deposition of Alberto Bruno-Vega, Executive Director of the V.I. Water and Power Authority "WAPA" ("Bruno-Vega Dep.") at 8; Deposition of Romeo Cipriani, Superintendent of the Water Distribution System for WAPA on St. Croix, ("Cipriani Dep.") at 8. It is clear from the exhibits submitted to the Court that there was much confusion and disorder in the days immediately following the hurricane due to inoperative communications systems, blocked roads and decimated basic services. Cipriani Dep. at 7,8,35. Green Dep. at 13-14. For this reason, it is difficult to piece together the exact chronological order of events during this time period. Nevertheless, the Court has found that there is no dispute with respect to the events relevant to the contract claim at issue.

After the storm, Mr. Cipriani made his way to his office at WAPA on September 19 and 20 and began to assess the damage and make plans. Cipriani Dep. at 8-9. Cipriani's job was to "oversee the entire *410 operation of ... the water distribution system in St. Croix (Bruno-Vega at 7) and Mr. Cipriani was very concerned about the potential dire public health effects of the hurricane's damage to the water system. Cipriani Dep. at 9.

By September 21 federal officials of various agencies had begun to arrive in substantial numbers to assist Territorial government officials deal with the disaster. The group of federal and local officials who were attempting to coordinate a response to the disaster apparently identified Bruce Green of the USGS as someone who could assist in the effort to restore water service. On September 21, Mr. Green was located by the National Guard and brought to emergency headquarters. Green Dep. at 10-11. Because of previous work in cooperation with WAPA, Mr. Green knew of some wells fields, owned by WAPA, that might be used to provide fresh water. He brought the wells to the attention of the group at emergency headquarters and explained what equipment would be needed to make the wells operational. 1 Green Dep. at 13, 15-18. The Army Corps of Engineers ("COE") was assigned the task of obtaining pumps and generators for the project. Singer Dep. at 26.

Whatever the exact order of events, one thing is clear from the documents submitted to the Court, by Thursday September 21, Mr. Cipriani and Mr. Green were working together closely to achieve the goal of using the Concordia and Adventure well fields (comprising about 45 wells) to provide fresh water for the citizens of St. Croix. Within approximately three weeks — or by early October— the system was ready to operate. Green Dep. at 26. The plan to utilize the well fields was complicated, however, by the need to provide 24-hour security for the equipment that was needed at each well site. The generators and pumps needed for the project were in extremely short supply on St. Croix and theft was a real concern. Green Dep. at 27-28; Bruno-Vega Dep. at 16; Cipriani at 10-11. Initially, in the first days of October, security for the equipment at the well sites was provided by WAPA personnel. On October 2, however, several of these employees were accosted by *411 people attempting to obtain the generators and, fearing for their safety, the WAPA employees refused to provide security services. Cipriani at 13; Bruno-Vega at 16. Federal armed forces and the local National Guard also refused to provide the necessary around the clock security. Green Dep. at 28.

Mr. Cipriani of WAPA and Mr. Green of the USGS, worked together to identify and locate a private contractor who could provide the requisite security. Both men knew of Mr. Fitzroy Gardiner and his Western Trading Enterprises corporation ("WTE") because he had done work in the past for WAPA. 2 Cipriani Dep. at 14; Green Dep. at 36. Ultimately, both men approached Mr. Gardiner together in La Reine, and discussed the scope of security and maintenance needs of the well field project. The men also discussed the fact that Mr. Gardiner would submit his invoices to WAPA. Green Dep. at 36; Cipriani Dep. at 14. It is not clear when Mr. Gardiner first learned that disbursements by WAPA would be reimbursed by the federal government for WAPA's payments to Mr. Gardiner after the submission of the requisite Damage Survey Reports ("DSRs"). Mr. Green's deposition testimony suggests that this subject arose at the first meeting in La Reine, while Mr. Gardiner remembers learning this fact only later, after he had submitted his first invoices. Green Dep. at 37; Deposition of Mr. Fitzroy Gardiner, president and sole proprietor of WTE ("Gardiner Dep.") at 20. Following this conversation between the three men, Mr. Gardiner agreed to undertake the project and began work immediately.

There is no dispute among the parties that Mr. Gardiner performed the tasks he had been assigned exceptionally well. There does, however seems to have been some concern about the prices Mr. Gardiner charged for his services. On October 25, 1989, at a meeting attended by Mr. Gardiner, Mr. Cipriani, and Mr. Fred Rounsaville of the Army COE, 3 Mr. Gardiner was asked to, and *412 agreed to, lower his hourly rates somewhat from $ 30/hr. during the day and $ 35/hr. during the night, to $ 22.50/hr. during the day and $ 27.50/hr. at night. It is the recollection of the participants of this meeting that Mr. Rounsaville actively participated in the negotiation and made arguments about why the rates should be lower. Green Dep. at 41; Gardiner Dep.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morton v. Hewitt
202 F. Supp. 2d 394 (Virgin Islands, 2002)
Gardiner v. VIRGIN ISLANDS WATER & POWER AUTHORITY
32 F. Supp. 2d 816 (Virgin Islands, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
896 F. Supp. 491, 32 V.I. 408, 1995 WL 505127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gardiner-v-virgin-islands-water-power-authority-vid-1995.