MEMORANDUM OPINION
(September 23, 2011)
In this appeal, we are tasked with reviewing a breach of contract action arising out of a construction agreement between a private contractor and the government of the Virgin Islands.
I. FACTUAL AND PROCEDURAL BACKGROUND
On February 12, 2001, Delta Electric Inc. (“Delta”) entered into a construction contract (“contract” or “agreement”) with the government of the Virgin Islands (“Government”) to perform expansion work on the Youth Rehabilitation Center in Estate Anna’s Hope, St. Croix (“project”). The total contract price to complete the project was $1,004,040.00. The [878]*878Government was required to make periodic progress payments to Delta as work on the project progressed. The contract remained silent as to a time certain by which the Government was required to make its progress payments.1 The Government was to retain ten percent of total payments due to Delta, to be paid upon final completion and acceptance of the contract work. The contract further provided that a Contracting Officer would decide the parties’ factual disputes. Pending final decision of a dispute, Delta was required to proceed diligently with performance.2 The contract was signed by Charles King (“King”), Delta’s president3; Marc Biggs (“Biggs”), then-Commissioner of Property and Procurement4; and Sedonie Halbert (“Halbert”), then-Commissioner of Department of Human Resources.5 The agreement became effective on February 12, 2001 when it was executed by the Governor of the Virgin Islands.
Delta commenced work on the project on March 23, 2001.6 Shortly thereafter, on April 9, 2001, construction was suspended while Delta secured building permits from the Virgin Islands Department of Planning and Natural Resources. Work resumed on April 19, 2001.
On April 26, 2001, Delta sent a letter informing the Government that it would suspend performance because the Government had not yet paid Delta for its mobilization costs. The Government remitted payment on May 22, 2001. Work resumed on June 1, 2001. During that five-week period, the island of St. Croix experienced heavy rains that damaged a cistern that was part of the project.
Delta also submitted Contract Change Order Requests for $16,293.83 to re-excavate and to re-construct the cistern. The Government denied Delta’s request and Delta re-submitted its Change Order Requests. In a July 11,2001 letter, the Commissioner of Property and Procurement again denied the re-submitted request on the basis that Delta had no contractual [879]*879authority to suspend its performance prior to the rains. Under protest, Delta rebuilt the cistern without additional payment. Delta did, however, receive progress payments for its continued work.
Delta ceased work for a third time, from August 28, 2001 to October 8, 2001 because it objected to the timeliness of the Government’s progress payments.7 On October 24, 2001, Delta requested payment in the amount of $94,196.59. The request sought progress payments plus the $16,293.83 cost to rebuild the cistern.
On January 3, 2002, the parties’ relationship began to truly sour when Delta forwarded correspondence to the Commissioner of Property and Procurement informing the Government that it would stop work on the project until all payment issues, including the issues involving its denied Change Order Request, were resolved. Between January 2001 and May 2001, Delta and the Government met on several occasions to resolve outstanding issues. During this period the Government continued to make partial payments on the work Delta had completed.8 On May 9, 2001, the Government terminated its contract with Delta because the time had expired for Delta to complete the project.
On April 30,2002, Delta filed an action in the Superior court for breach of contract and damages. In the event that the trial court found that no enforceable contract existed between the parties, Delta also filed claims in the alternative, premised on unjust enrichment and quantum meruit.
On August 30,2004, the Superior Court held a bench trial. Under direct examination, King, the president, manager and owner of Delta testified that he had a contract with the Government and tendered a copy of that contract, which was admitted as Plaintiff’s Exhibit C. (Trial Tr. vol. 1 at 19:11-14.) At the conclusion of the trial, the Superior Court judge found that the parties had executed an enforceable contract and that the Government had not breached that contract. Because the express contract defined the parties’ respective rights, duties and expectations, the trial judge rejected Delta’s claim for restitution damages under a quantum meruit theory of relief. This timely appeal followed.
[880]*880II.ISSUES PRESENTED
On appeal, Delta’s sole issue is whether the trial court erred when it denied Delta’s unjust enrichment claim.
III.JURISDICTION AND STANDARD OF REVIEW
This Court has jurisdiction to review appeals from final decisions of the Superior Court of the Virgin Islands. See V.I. CODE Ann. tit. 4, § 33 (2006); Revised Organic Act of 1984, § 23A, 48 U.S.C. § 1613(a) (2006); see also Gabriel Joseph v. People of the Virgin Islands, 50 V.I. 873, 884 (D.V.I. App. Div. 2008) (the Appellate Division maintains jurisdiction over all pending appeals filed prior to January 29, 2007); see also Hypolite v. People of the Virgin Islands, 51 V.I. 97, 101 (2009) (same).
Contract construction or the legal operation of a contract is subject to plenary review. See In re Cendant Corp. Prides Litig., 233 F.3d 188, 193 (3d Cir. 2000); Nibbs v. Roberts, 31 VI. 196, 204 (D.V.I. App. Div. 1995) (“The trial court’s decision concerning the application of a legal precept is subject to plenary review.”). Contract interpretation, on the other hand, is a question of fact, which is reviewed under a clearly erroneous standard. See In re Cendant Corp., 233 F.3d at 193; Nibbs, 31 V.I. at 204.
IV.ANALYSIS
Delta’s only argument on appeal is that the Superior Court judge erred in not awarding Delta damages based upon a theory of unjust enrichment.
It is well established that, “[contracts are traditionally classified as express, implied-in-fact or implied-in-law.” Terrace v. Williams, 52 VI. 225, 241 (2009).9 Under the unjust enrichment10 theory that Delta [881]*881advances, the contract is one that is implied in law, and “not an actual contract at all.”11 Wayne Moving & Storage of N.J., Inc. v. Sch. Dist. of Philo., 625 F.3d 148 (3d Cir. 2010).
To prevail on a claim for unjust enrichment, Delta bore the burden of showing that (1) the Government was enriched, (2) enrichment came at Delta’s expense and (3) equity required the Government to return monies or property to Delta. Cruse v. Callwood, 55 V.I. 999 (D.V.I. App. Div.
Free access — add to your briefcase to read the full text and ask questions with AI
MEMORANDUM OPINION
(September 23, 2011)
In this appeal, we are tasked with reviewing a breach of contract action arising out of a construction agreement between a private contractor and the government of the Virgin Islands.
I. FACTUAL AND PROCEDURAL BACKGROUND
On February 12, 2001, Delta Electric Inc. (“Delta”) entered into a construction contract (“contract” or “agreement”) with the government of the Virgin Islands (“Government”) to perform expansion work on the Youth Rehabilitation Center in Estate Anna’s Hope, St. Croix (“project”). The total contract price to complete the project was $1,004,040.00. The [878]*878Government was required to make periodic progress payments to Delta as work on the project progressed. The contract remained silent as to a time certain by which the Government was required to make its progress payments.1 The Government was to retain ten percent of total payments due to Delta, to be paid upon final completion and acceptance of the contract work. The contract further provided that a Contracting Officer would decide the parties’ factual disputes. Pending final decision of a dispute, Delta was required to proceed diligently with performance.2 The contract was signed by Charles King (“King”), Delta’s president3; Marc Biggs (“Biggs”), then-Commissioner of Property and Procurement4; and Sedonie Halbert (“Halbert”), then-Commissioner of Department of Human Resources.5 The agreement became effective on February 12, 2001 when it was executed by the Governor of the Virgin Islands.
Delta commenced work on the project on March 23, 2001.6 Shortly thereafter, on April 9, 2001, construction was suspended while Delta secured building permits from the Virgin Islands Department of Planning and Natural Resources. Work resumed on April 19, 2001.
On April 26, 2001, Delta sent a letter informing the Government that it would suspend performance because the Government had not yet paid Delta for its mobilization costs. The Government remitted payment on May 22, 2001. Work resumed on June 1, 2001. During that five-week period, the island of St. Croix experienced heavy rains that damaged a cistern that was part of the project.
Delta also submitted Contract Change Order Requests for $16,293.83 to re-excavate and to re-construct the cistern. The Government denied Delta’s request and Delta re-submitted its Change Order Requests. In a July 11,2001 letter, the Commissioner of Property and Procurement again denied the re-submitted request on the basis that Delta had no contractual [879]*879authority to suspend its performance prior to the rains. Under protest, Delta rebuilt the cistern without additional payment. Delta did, however, receive progress payments for its continued work.
Delta ceased work for a third time, from August 28, 2001 to October 8, 2001 because it objected to the timeliness of the Government’s progress payments.7 On October 24, 2001, Delta requested payment in the amount of $94,196.59. The request sought progress payments plus the $16,293.83 cost to rebuild the cistern.
On January 3, 2002, the parties’ relationship began to truly sour when Delta forwarded correspondence to the Commissioner of Property and Procurement informing the Government that it would stop work on the project until all payment issues, including the issues involving its denied Change Order Request, were resolved. Between January 2001 and May 2001, Delta and the Government met on several occasions to resolve outstanding issues. During this period the Government continued to make partial payments on the work Delta had completed.8 On May 9, 2001, the Government terminated its contract with Delta because the time had expired for Delta to complete the project.
On April 30,2002, Delta filed an action in the Superior court for breach of contract and damages. In the event that the trial court found that no enforceable contract existed between the parties, Delta also filed claims in the alternative, premised on unjust enrichment and quantum meruit.
On August 30,2004, the Superior Court held a bench trial. Under direct examination, King, the president, manager and owner of Delta testified that he had a contract with the Government and tendered a copy of that contract, which was admitted as Plaintiff’s Exhibit C. (Trial Tr. vol. 1 at 19:11-14.) At the conclusion of the trial, the Superior Court judge found that the parties had executed an enforceable contract and that the Government had not breached that contract. Because the express contract defined the parties’ respective rights, duties and expectations, the trial judge rejected Delta’s claim for restitution damages under a quantum meruit theory of relief. This timely appeal followed.
[880]*880II.ISSUES PRESENTED
On appeal, Delta’s sole issue is whether the trial court erred when it denied Delta’s unjust enrichment claim.
III.JURISDICTION AND STANDARD OF REVIEW
This Court has jurisdiction to review appeals from final decisions of the Superior Court of the Virgin Islands. See V.I. CODE Ann. tit. 4, § 33 (2006); Revised Organic Act of 1984, § 23A, 48 U.S.C. § 1613(a) (2006); see also Gabriel Joseph v. People of the Virgin Islands, 50 V.I. 873, 884 (D.V.I. App. Div. 2008) (the Appellate Division maintains jurisdiction over all pending appeals filed prior to January 29, 2007); see also Hypolite v. People of the Virgin Islands, 51 V.I. 97, 101 (2009) (same).
Contract construction or the legal operation of a contract is subject to plenary review. See In re Cendant Corp. Prides Litig., 233 F.3d 188, 193 (3d Cir. 2000); Nibbs v. Roberts, 31 VI. 196, 204 (D.V.I. App. Div. 1995) (“The trial court’s decision concerning the application of a legal precept is subject to plenary review.”). Contract interpretation, on the other hand, is a question of fact, which is reviewed under a clearly erroneous standard. See In re Cendant Corp., 233 F.3d at 193; Nibbs, 31 V.I. at 204.
IV.ANALYSIS
Delta’s only argument on appeal is that the Superior Court judge erred in not awarding Delta damages based upon a theory of unjust enrichment.
It is well established that, “[contracts are traditionally classified as express, implied-in-fact or implied-in-law.” Terrace v. Williams, 52 VI. 225, 241 (2009).9 Under the unjust enrichment10 theory that Delta [881]*881advances, the contract is one that is implied in law, and “not an actual contract at all.”11 Wayne Moving & Storage of N.J., Inc. v. Sch. Dist. of Philo., 625 F.3d 148 (3d Cir. 2010).
To prevail on a claim for unjust enrichment, Delta bore the burden of showing that (1) the Government was enriched, (2) enrichment came at Delta’s expense and (3) equity required the Government to return monies or property to Delta. Cruse v. Callwood, 55 V.I. 999 (D.V.I. App. Div. 2010); Gov’t Guarantee Fund of Republic of Finland v. Hyatt Corp., 955 F. Supp. 441, 460, 35 V.I. 356 (D.V.I. App. Div. 1997); Martin v. Martin, 54 V.I. 379, 394 (2010).
Because unjust enrichment is an equitable doctrine that applies only in implied or quasi-contractual circumstances, the doctrine is triggered only where there is no contract or under an unconsummated or void contract.12 See Restatement (Second) of Contracts § 345(d)13; see also In re Penn Cent. Transp. Co., 831 F.2d 1221, 1229 (3d Cir. 1987); Steamfitters Local Union No. 420 Welfare Fund v. Philip Morris, Inc., 171 F.3d 912, 936 (3d Cir. 1999) (emphasis added); Trianco, LLC v. IBM, 271 Fed. Appx. 198, 202 (3d Cir. 2008) (unpublished) (unjust enrichment is a quasi contractual claim that the law creates in the absence of an agreement).
This bright-line rule embodies the principle that parties in contractual privity are not entitled to the remedies available under a judicially-imposed quasi-contract. In other words, the parties are not entitled to restitution based upon the doctrine of unjust enrichment, because the [882]*882terms of their agreement, express and implied, define their respective rights, duties and expectations.
In this case, the subject of the dispute was various work, including cistern construction, that was governed by an express contract. In its complaint, Delta grounded its breach of contract theory of recovery on the parties’ explicit contract. At trial, Delta’s president testified that he had executed a contract with the Appellee. Unjust enrichment was raised in Delta’s complaint only as an alternate theory of recovery, in the event that the trial court found that no contract existed.
The Superior Court, however, found that there was a valid and enforceable contract covering the work in dispute; and neither on appeal nor below, has Delta challenged the trial court’s finding that a valid and enforceable contract governed the parties’ dispute. Contrarily, in its opening appellate brief, Delta cites to terms of the express contract to support its claim for unjust enrichment. Delta’s brief specifically argues that, “[i]n this instance, the parties do have an agreement — the construction contract;” (Appellant’s Brief at 10 citing Paragraph 2(d) of the contract.) (emphasis added.)
Because Delta had an express contract to do the work it complains benefitted the Appellee, it could not properly invoke the implied contract doctrine of unjust enrichment. In re Penn Cent. Transp. Co., 831 F.2d at 1229 (“no implied-in-fact contract can be found when, as here, the parties have an express agreement dealing with the same subject.”). As the Supreme Court articulated in Klebe v. United States,
[a] contract implied in fact is one inferred from the circumstances or acts of the parties; but an express contract speaks for itself and leaves no place for implications. Giving application to this rule with respect to contracts implied... this court has said: There cannot be an implied contract either in law or in fact contrary in terms to a controlling express contract.
263 U.S. 188, 44 S. Ct. 58, 68 L. Ed. 244,59 Ct. Cl. 953 (internal citations and quotations omitted). In this litigation, it is undisputed that the controlling terms of Delta’s contract with the Government were explicit, express [883]*883and enforceable.14 (See Supplemental Appendix 7-37.) As such, unjust enrichment does not apply.15
Indeed, Delta does not highlight a single issue or contract term in dispute that is either distinguishable or unrelated to the terms and scope of the express contract. See, e.g., ITT Federal Support Services, Inc. v. United States, 531 F.2d 522, 528, 209 Ct. Cl. 157 (Ct. Cl. 1976) (an action under an equitable contract theory, if it is to be valid, must be unrelated to the express contract). For example, to be entirely unrelated to an express contract, an implied contract would at the least have to require the proponent to assume some duties different from those under the formal agreement. ITT Federal Support Services, Inc., 531 F.2d at 528. Here, Delta has neither demonstrated nor argued that any corresponding duties of performance arose as a result of the parties’ conduct or arose outside of the purview of their written contract. See, e.g., Somali Development Bank v. United States, 508 F.2d 817, 822, 205 Ct. Cl. 741 (1974); see also Hershey Foods Corp. v. Ralph Chapek, Inc., 828 F.2d 989, 999 (3d Cir. 1987) (“a contract implied in law imposes a duty, not as a result of any agreement, whether express or implied, but in spite of the absence of an agreement when one party receives an unjust enrichment at the expense of another”).
Because an express contract dictated the parties’ dealings and an unjust enrichment cause of action is inapplicable where an express contract governs the relationship between the parties, we AFFIRM the Superior Court’s decision.16 Morton, 202 F. Supp. 2d at [884]*88439817 (“claims arising from quasi-contracts and express contracts are mutually exclusive”).
V. CONCLUSION
As the trial court found, it is clear from the record below that the parties to this action manifested their mutual assent to be bound by contract. (App. 12.) Because an explicit enforceable contract existed between the parties, Delta’s claim for unjust enrichment must fail. On this basis, we AFFIRM.