Moorhead Drainage Dist. v. Pedigo

49 So. 2d 378, 210 Miss. 284, 1950 Miss. LEXIS 348
CourtMississippi Supreme Court
DecidedDecember 18, 1950
DocketNo. 37654
StatusPublished
Cited by7 cases

This text of 49 So. 2d 378 (Moorhead Drainage Dist. v. Pedigo) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moorhead Drainage Dist. v. Pedigo, 49 So. 2d 378, 210 Miss. 284, 1950 Miss. LEXIS 348 (Mich. 1950).

Opinion

Ethridge, C.

The Moorhead Drainage District, situated in Sunflower County, Mississippi, was created in 1912. Miss. Laws of 1912, Chapter 195. It is a corporate political subdivision with local commissioners. Miss. Code of 1942, Sec. 4675 et seq. Moorhead Bayou is a deep, natural draining channel, which carries the water from the District into the Quiver Eiver, furnishing the outlet for the waters of the District. The District originally contained 14,990 acres, but only 13,720 acres were assessed originally for [287]*287benefits. Shortly after its creation there was assessed against the stated lands in the District under a chancery court’s decree benefits and betterments in the amount of $146,436.55. The original bond issue at that time was in the amount of $80,000.00, and two later ones were about $25,000.00 each, making a total of $130,000.00.

Since the District was organized it has lost lands by sales to the state for delinquent taxes and by incorporation of some territory into the Town of Moorhead. Hence the basis of its original assessed benefits was reduced to $137,336.73. Prior to 1932 the original bond issues had been paid off from taxes levied by the District against these assessed benefits. The aggregate of the original bond issues, interest on them, and other costs consumed the entire original assessed benefits. According to a stipulation filed herein by all counsel, all of the original assessed benefits of the District, serving as the basis of the taxing power of the District, had been consumed at the time the District made the engineering contract with E. H. Pedigo, appellee.

Early in 1937 the three Commissioners for the Moor-head Drainage District were desirous of having an engineering survey made of the District’s lands in order to see what was needed to be done to repair and reclaim the canals and channels of the District, and how much such a project would cost. At the request of the Commissioners of appellant Drainage District, appellee, on June 9, 1947, made a written proposal to the District on the cost of his services as consulting engineer for a reclamation project. By letter, appellee proposed to make a “preliminary survey, reports, estimates, specifications, notices to bidders, advertisements of contracts, forms for contracts, forms for surety bonds, and all other necessary data preliminary to the letting of the contract for the construction of clean-out work on approximately 30 to 35 miles of drainage canals, including Moorhead Bayou, for five per cent of the estimated bond prices for the work . . . .” Appellee also proposed to do “all the preliminary work as outlined above, and further to set the construction [288]*288stakes, grades, slopes, keep field notes, progress reports, and make up estimates for the contractor on monthly intervals until work is finished, and follow with any inspections that are necesary during the time.” He also proposed: “I further propose to furnish advice in the preparation for bond issue, for the selection of bidders, advertisements, and the letting of contracts; and to carefully protect the Moorhead Drainage District’s interest during the life of the contract. This second phase of my employment will justify another 5% fee based on the actual cost of the project. (Please note that the first phase of the preliminary work of 5% is based entirely on estimated costs, and the additional 5% noted in the second phase is based on the actual cost of the project).”

On June 13, the Commissioners accepted appellee’s offer by a resolution entered on their minutes. The next day the contracting parties, at the request of the attorney for the District, agreed to add to the employment contract the following clause: “Upon completion of the preliminary work hereinafter referred to, and the payment therefor by the District, the plans and specifications will become the property of the District, and the District is not obligated to proceed with the second phase of the work. ’ ’

After execution of the contract, appellee spent several months making an engineering survey for the reconstruction of the District by repairing its existing drains. At times he had two' field parties working, and some of them would have six or seven men cutting lines. These men were employed and paid by appellee for this job, although under the contract the District agreed to “reimburse the engineer for the field party working at the rate of $35.00 per day, to be deducted from the total amount on completion and submission to the Commissioners, of the preliminary engineering data . . . .” On April 27, 1948, appellee submitted his preliminary engineering report. The total estimated cost for the work recommended by him was $159,868.41. On the basis of that estimate, appellee’s five per cent fee was [289]*289$7,993.42. On May 4, 1948, the Commissioners of appellant by resolution accepted appellee’s report as “in accordance with the contract heretofore entered into by Commissioners with said engineer”, and ordered the payment of $2,500.00 to be made to appellee “to apply to the fee of the said R. H. Pedigo under said contract.” The $2,500.00 accordingly was paid to appellee, leaving a balance due him under the contract of $5,493.42.

The three Commissioners who were in office at the time the report of April 27th was made testified that they thought the estimate made in it was not excessive and that it recommended needed reclamation work, but that the District could not “accumulate that much money”, and it was “too big a burden on the District to spend that much money. ’ ’ Hence the Commissioners requested appellee to bring in another engineering report on a project requiring less work. Pedigo then made a suggested report of a project estimated to cost $26,000.00, which was adopted by the Commissioners. On May 12, 1948, they petitioned the chancery court for authority to borrow that sum and to levy in that amount additional benefits against the lands of the District. The chancery court authorized $26,000.00 of additional assessments, but that decree was reversed by this Court because of failure to make parties to the District’s petition the owners of lands outside the District who would be benefited by the improvements. Hobbs v. Moorhead Drainage District, 1949, 205 Miss. 679, 39 So. (2d) 307.

•In April, 1949, the three Commissioners for the District were changed, and the District refused to pay appellee the balance of his contract price for the engineering survey, being $5,493.42. Subsequently, in September, 1949, upon the petition by the District, the chancery court authorized the District to make additional assessed benefits of $50,000.00, and to sell $50,000.00' of new bonds to defray the cost of the proposed reclamation work, under specified conditions. The decree with a few modifications was affirmed ip Moorhead Drainage District v. [290]*290Jackson, 1950, 208 Miss. 594, 45 So. (2d) 234, but is not involved herein.

On July 26, 1949, appellee, E. H. Pedigo, filed a declaration in the Circuit Court of Sunflower County, Mississippi, in which he set up the employment contract with the District and the partial payment which had been made to him -by the District. He prayed for judgment in the amount of the balance, $5,493.42, together with interest and costs. In its answer the District alleged that the estimated cost of the project was “unreasonable, impractical, excessive, and unlawful, and was rejected by defendant . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Mound Bayou v. Roy Collins Const. Co.
457 So. 2d 337 (Mississippi Supreme Court, 1984)
Terry v. Long Creek Watershed Drainage District
380 So. 2d 1270 (Mississippi Supreme Court, 1980)
Antley v. Mississippi State Highway Com.
318 So. 2d 847 (Mississippi Supreme Court, 1975)
City of Jackson v. Reed
102 So. 2d 342 (Mississippi Supreme Court, 1958)
Rankin County, Miss. v. Wallace, Minor
92 So. 2d 661 (Mississippi Supreme Court, 1957)
Edward E. Morgan Co. v. State Highway Commission
54 So. 2d 742 (Mississippi Supreme Court, 1951)
Eden Drainage District v. Swaim
54 So. 2d 547 (Mississippi Supreme Court, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
49 So. 2d 378, 210 Miss. 284, 1950 Miss. LEXIS 348, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moorhead-drainage-dist-v-pedigo-miss-1950.