Monreal Funeral Home, Inc. v. Ohio Farmers Insurance

189 Ohio App. 3d 1
CourtOhio Court of Appeals
DecidedAugust 13, 2010
StatusPublished
Cited by5 cases

This text of 189 Ohio App. 3d 1 (Monreal Funeral Home, Inc. v. Ohio Farmers Insurance) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Monreal Funeral Home, Inc. v. Ohio Farmers Insurance, 189 Ohio App. 3d 1 (Ohio Ct. App. 2010).

Opinions

Mary Jane Trapp, Presiding Judge.

{¶ 1} The Monreal Funeral Home, Inc. (“Monreal”) appeals from a judgment of the Lake County Court of Common Pleas granting a directed verdict in favor of Ohio Farmers Insurance Company (“Ohio Farmers”). The case arose from disputes between Monreal and Olympic Building Company (“Olympic”) regarding the construction of a funeral home. Monreal filed a complaint against Ohio Farmers to recover under the performance bond that it issued for this construction project. The trial court found that Monreal’s claim under the bond is time-barred. We agree and therefore affirm.

{¶ 2} Substantive Facts and Procedural History

{¶ 3} In 2002, Monreal contracted with Olympic to build a funeral home for Monreal in Eastlake, Ohio, for the amount of $1,450,000. From the beginning, various disputes arose between Olympic and Monreal concerning the progress, scope, quality, and cost of the construction. Some of the problems allegedly arose from deficiencies in the plans and specifications prepared by Monreal’s architect.

{¶ 4} Central to this case is a performance bond issued by Ohio Farmers. The contract between Monreal and Olympic required Olympic to obtain a performance bond for $350,000 naming Monreal as the primary obligee.1 In July 2002, a performance bond was issued by Ohio Farmers as surety to insure Olympic’s performance under the contract. A limitation-of-action clause in the bond states that “[a]ny suit under this bond must be instituted before the expiration of two (2) years from the date which Contractor ceases work on the Contract.”

{¶ 5} By December 2002, Olympic had begun to submit various change-order requests to Monreal due to the alleged deficiencies in the plans. In February 2003, Monreal issued a “punch list,” which was disputed by Olympic. By May 2003, Olympic’s subcontractors were seeking assurances for payment from Mon-real.

{¶ 6} On July 23, 2003, Monreal notified Olympic of its decision to declare Olympic in default. After negotiations, Monreal rescinded its declaration of default. However, the problems continued, and in March 2004, Olympic stopped work on the funeral home. On March 26, 2004, Monreal notified Olympic of Monreal’s termination of Olympic for cause effective April 5, 2004. It is undisputed that Olympic performed no work after April 5, 2004.

[4]*4{¶ 7} On April 9, 2004, Monreal notified Ohio Farmers that it was making a claim under the performance bond. In a letter dated June 29, 2004, Ohio Farmers rejected the claim. Ohio Farmers stated that its obligations under the bond had “not arisen” for several reasons: (1) it believed Monreal’s failure to pay Olympic for changes and to timely replace the architect constituted a breach of contract; (2) Olympic disputed the termination declared by Monreal and had offered to complete the undisputed contract items and also requested mediation, and, if necessary, arbitration of any dispute between Monreal and Olympic;2 (3) Olympic claimed additional change orders and disputed many “back charges” claimed by Monreal; (4) the project had been substantially completed except for Monreal and Olympic’s disagreement as to the appropriate remedies for the “punch list” items; (5) Olympic was prepared to complete the undisputed scope of the project and objected to owner completion; and (6) Monreal did not have standing to bring a claim because Great Lakes Bank, the bank that financed the construction project, was the “owner” named in the bond.

{¶ 8} After citing these reasons for its rejection of the claim, Ohio Farmers stated: “For the above reasons, [Ohio Farmers] believes [Ohio Farmers’] obligations under the bond have not arisen. In any case, given the disputes regarding the scope of completion, including the lack of definition of certain fixes, [Ohio Farmers] is unable to obtain bids for completion. Also, the Monreals and Olympic have agreed to arbitrate their disputes. It would not be appropriate for [Ohio Farmers] to act as an arbitrator by resolving on its own the scope of completion and the other disputes between the Monreals and Olympic. [Ohio Farmers] therefore intends to not complete the project. It appears, however, that the balance of the contract price as quantified by the CSL Consulting LLC is sufficient to cover the reasonable cost to complete the undisputed punch list items.” Ohio Farmers ended the letter by stating that it continued “to reserve any and all rights of the surety and the principal.”

{¶ 9} After Monreal and Olympic failed to resolve their dispute through mediation, Olympic filed a demand for arbitration with the American Arbitration Association on May 17, 2005, seeking $239,199 in damages. Olympic claimed that Monreal breached the contract and its warranty regarding the accuracy, completeness, and suitability of the construction plans and specifications. The arbitration, however, was considerably delayed by Olympic’s noncompliance with [5]*5various orders by the arbitrator. Olympic and its president, Paul Globokar, failed to participate in discovery.

{¶ 10} On June 9, 2005, Monreal notified Ohio Farmers of the pending arbitration and “invited” Ohio Farmers to participate in the arbitration. Ohio Farmers declined.

{¶ 11} The arbitration process did not go well due to Olympic’s lack of cooperation. An arbitration hearing was finally scheduled for April 4, 2006. Olympic did not appear at the hearing.3 Based on the exhibits submitted by Monreal, the arbitrator found that Monreal owed Olympic a balance of $26,2284 but the amount of funds needed to complete the project was $255,152. Therefore, the arbitrator found Monreal entitled to $228,924.00 from Olympic. However, the arbitrator limited the award to only $75,000, the amount Monreal sought in its counterclaim.

{¶ 12} On April 27, 2006, Monreal notified Ohio Farmers of the arbitration award and requested compensation under the bond. On June 19, 2006, Ohio Farmers notified Monreal that it would not pay the claim. It cited the expiration of the two-year limitation period for suit under the bond, which contained no arbitration provision, and also noted a lack of notice to Ohio Farmers that the arbitration had proceeded on a default basis.

{¶ 13} On June 29, 2006, Monreal filed the instant action against Ohio Farmers alleging three causes of action: breach of contract (count one), bad-faith breach of contract (count two), and declaratory judgment (count three).5 Ohio Farmers raised the affirmative defense that the complaint was time-barred by the bond’s •two-year limitation-of-action clause.

{¶ 14} In the lengthy and protracted litigation that ensued, the parties’ attention focused on the June 29, 2004 letter from Ohio Farmers to Monreal. Monreal claimed that this letter constituted a waiver of the two-year time [6]*6limitation and also that it had relied on the letter to its detriment. It also claimed that the limitation clause was unreasonable.

{¶ 15} Monreal filed a motion for summary judgment, seeking a ruling that Ohio Farmers was obligated under the bond as a matter of law based upon the arbitration award. It also sought a ruling that Ohio Farmers’ refusal to pay its claim constituted bad faith as a matter of law. Ohio Farmers also moved for summary judgment, based on the limitation-of-action clause in the bond.

{¶ 16} The trial court denied both motions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoague v. Cottrill Servs., L.L.C.
2024 Ohio 531 (Ohio Court of Appeals, 2024)
USPG Portfolio Six, L.L.C. v. Dick's Sporting Goods, Inc.
2023 Ohio 550 (Ohio Court of Appeals, 2023)
City of Lancaster v. FLAGSTAR BANK, FSB
789 F. Supp. 2d 873 (S.D. Ohio, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
189 Ohio App. 3d 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/monreal-funeral-home-inc-v-ohio-farmers-insurance-ohioctapp-2010.