R.E. Holland Excavating Co. v. Montgomery County Board of Commissioners

729 N.E.2d 1255, 133 Ohio App. 3d 837, 1999 Ohio App. LEXIS 2915
CourtOhio Court of Appeals
DecidedJune 25, 1999
DocketC.A. Case No. 17633. T.C. Case No. 96-5441.
StatusPublished
Cited by6 cases

This text of 729 N.E.2d 1255 (R.E. Holland Excavating Co. v. Montgomery County Board of Commissioners) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.E. Holland Excavating Co. v. Montgomery County Board of Commissioners, 729 N.E.2d 1255, 133 Ohio App. 3d 837, 1999 Ohio App. LEXIS 2915 (Ohio Ct. App. 1999).

Opinion

Fain, Judge.

Plaintiff-appellant, R.E. Holland Excavating Company, Inc. (“Holland”), contends that the trial court erred by rendering summary judgment against it on its complaint for breach of contract. In support, Holland contends that although the trial court correctly found that the sixty-day limitations period contracted for by Holland was unreasonably short, the trial court erred by then failing to apply the statutory limitations period contained in R.C. 2305.06 (claims for breach of contract). Therefore, Holland contends, the trial court erred in determining that it had not filed its complaint in a timely manner.

We need not reach this issue because we conclude that the limitations- period provided for in the contract executed by Holland was reasonable and binding. *839 Accordingly, based upon different reasoning, we find that the trial court correctly rendered summary judgment in favor of appellee.

I

In 1993, the city of Trotwood and Randolph Township applied to the Montgomery County Economic Development and Government Equity Program (“EDGE”) for a grant to construct a sanitary sewer to extend from the city of Trotwood to Randolph Township. EDGE approved monies for the completion of the project.

Upon request by the city of Trotwood and Randolph Township, the Montgomery County sanitary engineers agreed to bid, and to oversee the construction of, the project. Holland made the lowest bid. The Board of County Commissioners of Montgomery County (“board”) awarded Holland the contract.

Article 11.2 of the contract between the parties governs how the parties would address unanticipated and unforeseeable events resulting in a change in the agreed contract price. That provision provides as follows:

“The Contract Price may only be changed by a Change Order or by a Written Amendment. Any claim for an adjustment in the Contract Price shall be based on written notice delivered by the party making the claim to the other party and to ENGINEER promptly (but in no event later than thirty (30) days) after the start of the occurrence or event giving rise to the claim and stating the general nature of the claim. Notice of the amount of the claim with supporting data shall be delivered within sixty (60) days after the start of such occurrence or event (unless ENGINEER allows additional time for claimant to submit additional or more accurate date in support of the claim) and shall be accompanied by claimant’s written statement that the adjustment claimed covers all known amounts to which the claimant is entitled as a result of said occurrence or event.”

Article 9.11 of the contract made the following provision for the resolution of disputes between the parties:

“Claims, disputes and other matters relating to the acceptability of the Work or the interpretation of the requirements of the Contract Documents pertaining to the performance and the furnishing of the Work and under Articles 11 and 12 in respect of changes in the Contract Price or Contract Times will be referred initially to ENGINEER in -writing with a request for a formal decision in accordance with this paragraph. Written notice of each such claim, dispute or other matter will be delivered by the claimant to ENGINEER and the other party to Agreement promptly (but in no event later than thirty (30) days) after the start of the occurrence or event giving rise thereto, and written supporting date will be submitted to ENGINEER and the other party within (60) days after the start of such occurrence or event unless ENGINEER allows an additional *840 period of time for the submission of additional or more accurate date in support of such claim, dispute or other matter. The opposing party shall submit any response to ENGINEER and the claimant within thirty (30) days after receipt of the claimant’s last submittal * * *. ENGINEER will render a formal decision in writing within thirty (30) days after receipt of the opposing party’s submittal, if any, in accordance with this paragraph. ENGINEER’S written decision on such claim, dispute or other matter will be final and binding upon OWNER and CONTRACTOR unless a written notice of intention to appeal from ENGINEER’S written decision is delivered by OWNER or CONTRACTOR to the other and to ENGINEER within thirty (30) days after the date of such decision and a formal proceeding is instituted by the appealing party in a forum of competent jurisdiction to exercise such rights or remedies as the appealing party may have with respect to such claim, dispute or other matter in accordance with applicable laws and Regulations within sixty (60) days of the date of such decision, unless otherwise agreed to in writing by OWNER and CONTRACTOR.”

On November 28,1994, Holland provided written notice that it had encountered an unforeseen condition during excavation; specifically, Holland claimed that the project site was saturated with excessive water, which it would be required to remove. In the notice, Holland stated that it would keep track of the extra costs incurred by reason of the excessive water.

Thereafter, numerous letters regarding the unforeseen condition were exchanged between the parties. The letters relevant to this appeal are as follows. In a letter dated December 21,1994, the project’s chief engineer denied the claim, stating that the water conditions were not unexpected. By letter dated January 19, 1995, Holland informed the engineer that it could not report all costs until completion of the project. Holland also stated that it disputed the determination that the excess water was not an unforeseen condition.

After completing the pumping on May 31, 1995, Holland sent a letter to the engineer stating that the project was close to completion and that a cost justification would be forwarded. The engineer responded by letter dated, July 19, 1995 in which the claim for dewatering the site was again denied. Thereafter, Holland sent a letter, dated July 24, in which it stated that the claim for dewatering had been completed and that Holland was interpreting the July 19 letter from the engineer as the “final decision” on the matter. The letter also informed the engineer that legal action would be taken. Another letter was sent by the engineer, stating that the decision denying the claim was still in effect. Finally, on July 31, 1995, Holland sent the engineer a letter containing the cost justification for the extra cost incurred on the site for dewatering. The letter *841 also stated that “[biased on [the engineer’s] most recent final decision, we are proceeding with litigation.”

Holland filed a complaint for breach of contract against the board on December 30, 1996. The complaint was later amended to include the city of Trotwood as a defendant. On October 30, 1998 the board filed a motion for summary judgment claiming that Holland had failed to file its lawsuit within the time provided for by the contract. In granting the motion, the trial court found that the period set forth in the contract for filing a legal action was unreasonably short and, therefore, invalid. However, the court granted the motion, finding that the seventeen months from July 24, 1995 until the complaint was filed was unreasonable. It is from this order that Holland appeals.

II

In its sole assignment of error, Holland argues:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cita Trust Company AG v. Fifth Third Bank
879 F.3d 1151 (Eleventh Circuit, 2018)
Arlington Video Productions, Inc. v. Fifth Third Bancorp
569 F. App'x 379 (Sixth Circuit, 2014)
Monreal Funeral Home, Inc. v. Ohio Farmers Insurance
189 Ohio App. 3d 1 (Ohio Court of Appeals, 2010)
Arcade Co. v. Arcade, LLC
105 F. App'x 808 (Sixth Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
729 N.E.2d 1255, 133 Ohio App. 3d 837, 1999 Ohio App. LEXIS 2915, Counsel Stack Legal Research, https://law.counselstack.com/opinion/re-holland-excavating-co-v-montgomery-county-board-of-commissioners-ohioctapp-1999.